Brief Project Description: The deck replacement of I-89 bridges calls for a very aggressive construction schedule, replacing bridge decks of 4 bridges using 6 weekend closures (59 hours for each closure). VTRANS, upon the contractor’s recommendation, uses the innovative AccelBridge precast deck system for the project. AccelBridge is relatively simple and fast to construct. It simplifies deck construction by eliminating the typical cast-in-place joint between precast deck panels.
Poster: [Click to enlarge]
Fact Sheet Other Q&A
Related Report
Presenters: Eddie He, AccelBridge
Questions or comments about the Poster? Contact the researcher ehe@accelbridge.com. The researcher will assemble a Q and A document reflecting all queries received by 9 AM September 14th. The Q and A should be posted by September 15.