CMS2: Deck Replacement of I-89 Bridges with Weekend Closures

Brief Project Description: The deck replacement of I-89 bridges calls for a very aggressive construction schedule, replacing bridge decks of 4 bridges using 6 weekend closures (59 hours for each closure). VTRANS, upon the contractor’s recommendation, uses the innovative AccelBridge precast deck system for the project. AccelBridge is relatively simple and fast to construct. It simplifies deck construction by eliminating the typical cast-in-place joint between precast deck panels.