THIS PROJECT IS COMPLETE!
On behalf of The Vermont Agency of Transportation and myself, we would like to thank everyone for your patience and understanding during the intersection reconstruction project. We hope you enjoy the improvements.
Stay safe and buckle up!
US2 / Industrial Avenue Intersection reconstructed
This week ending 11/17/23: Worked continued on various punch-list items.
Below is the anticipated work schedule for the week beginning November 20, 2023.
Monday through Wednesday - 6:30 a.m. to 4:30 p.m.
- If necessary, completion of some minor punch list items to complete this project.
Thursday and Friday:
- No work due to the Thanksgiving Day holiday.
This week ending 11/10/23: Worked continued on various punch-list items.
Below is the anticipated work schedule for the week beginning November 13, 2023.
Monday through Friday - 6:30 a.m. to 4:30 p.m.
- If necessary, completion of some minor punch list items to complete this project.
This week ending 11/03/23: Worked continued on various punch-list items.
Below is the anticipated work schedule for the week beginning November 6, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.
- If necessary, completion of some minor punch list items to complete this project.
This week ending 10/27/23: Worked continued on various punch-list items.
Below is the anticipated work schedule for the week beginning October 30, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.
- Complete various punch-list items throughout the project in anticipation of finalizing the project.
US2 eastbound view
This week ending 10/20/23: Worked on various punch-list items.
Below is the anticipated work schedule for the week beginning October 23, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.
- Complete various punch-list items throughout the project in anticipation of finalizing the project.
US2 eastbound view - Seeded and stablized disturbed ground
This week ending 10/13/23: Pavement markings were completed earlier this week; Signs were installed; Began work on various punchlist items.
Below is the anticipated work schedule for the week beginning October 16, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.
- Complete various punch-list items to complete throughout the project.
View from Industrial Avenue - Pavement markings are complete
This week ending 10/05/23: Prepped the pavement for inlaid pavement markings and all markings should be completed tonight.
Below is the anticipated work schedule for the week beginning October 9, 2023.
Sunday and Monday:
- No work due to the Columbus / Indigenous Peoples' Day holiday.
Tuesday through Friday - 6:30 a.m. to 6:00 p.m.
- Installation of signs throughout the project.
- Various punch-list items to complete throughout the project.
U.S. Route 2 installation of pavement markings began this week
This week ending 9/28/23: Prepped the roadway for permanent pavement markings throughout the project; General site cleanup.
Below is the anticipated work schedule for the week beginning October 2, 2023.
Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:
- Grinding of the asphalt on the line striping layout in anticipation of the inlaid final pavement markings.
Thursday and Friday - 6:30 a.m. to 6:00 p.m.
- If grinding work is completed by Thursday at 6:00 a.m. then motorists can expect lane closures for the start of the installation of pavement markings on U.S. Route 2.
U.S. Route 2 line striping layout
This week ending 9/22/23: Completed the final paving throughout the project; Continued sidewalk and curb installation.
Below is the anticipated work schedule for the week beginning September 24, 2023.
Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:
- Line striping layout in anticipation of final pavement markings. Please note, this work should not take all week.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Topsoil, driveway tie-ins and general site cleanup work throughout the project limits.
Final paving completed - U.S. Route 2 and Industial Avenue intersection view
This week ending 9/15/23: Continued sidewalk and curb installation. Completed installation of catch basin grates.
Below is the anticipated work schedule for the week beginning September 17, 2023.
Sunday through Wednesday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, final paving throughout the project limits. Please note, if paving is rained out, paving will take place the next available night.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Topsoil and general site cleanup work throughout the project limits.
Eastbound U.S. Route 2 sidewalk prep for concrete placement
This week ending 9/8/23: Continued sidewalk and curb installation.
Below is the anticipated work schedule for the week beginning September 11, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue prepping and pouring the remaining sidewalks within the project.
- Complete the installation of the catch basin grates
Prepping for granite curb installation on the corner of U.S. Route 2 and Industrial Avenue
This week ending 9/1/23: Continued sidewalk installation and finished raising the grates for the catch basins/drainage inlets.
Below is the anticipated work schedule for the week beginning September 5, 2023.
Tuesday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue sidewalk and potential curb installation, weather permitting.
Sidewalk work continues on the south side of U.S. Route 2, Williston
This week: Work to raise the grates for the catch basins/drainage inlets.
Below is the anticipated work schedule for the week beginning August 28, 2023.
Monday through Thursday-6:30 a.m. to 6:00 p.m., Friday 6:30 a.m. to noon:
- Continue sidewalk and curb installation, weather permitting.
- Continue raising the catch basin grates.
Curb and earthwork complete on south side of U.S. Route 2, Williston
This week: Continued the installation of concrete sidewalks and placed topsoil in various areas along U.S. Route 2.
Below is the anticipated work schedule for the week beginning August 21, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue sidewalk installation, weather permitting.
- Continue curb installation.
Sidewalk installation continues on the south side of U.S. Route 2, Williston
This week: Began concrete sidewalk installation in various areas throughout the project limits.
Below is the anticipated work schedule for the week beginning August 14, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue sidewalk installation.
- Continue placement of topsoil in various areas throughout the project.
Pouring concrete for sidewalk along U.S. Route 2
This week: Began the preparation for sidewalk installation in various areas throughout the project limits.
Below is the anticipated work schedule for the week beginning August 8, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue sidewalk preparation work with pouring concrete, weather permitting.
- Continue installation of granite curbing.
Prepping for sidewalk installation
This week: There was no activity this week.
Below is the anticipated work schedule for the week beginning July 31, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Begin sidewalk preparation work with potential curb installation, as well.
The Sand Filter installation is complete
This week: The installation of the sand filter will be complete by the end of work, tomorrow.
Below is the anticipated work schedule for the week beginning July 24, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Begin sidewalk preparation work with potential curb installation, as well.
Backfilling operations down to the Sand Filter
This week: Work to backfill around the sand filter continued.
Below is the anticipated work schedule for the week beginning July 17, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Work to continue around the Sand Filter.
- General cleanup work throughout the project.
Backfilling operations around the Sand Filter on the south side/eastbound US Route 2
This week: Gulliver's Doggie Daycare driveway tie-in off Industrial Avenue was paved.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Work continues around the Sand Filter.
- General cleanup work throughtout the project limits.
This week: Poured concrete on the top of the Sand Filter.
Below is the anticipated work schedule for the week beginning July 3, 2023.
Monday and Tuesday:
- No work due to the Independence Day holiday.
Wednesday through Friday-6:30 a.m. to 6:00 p.m.:
- Weather permitting, paving the driveway tie-in at Gulliver's Doggie Daycare.
- General cleanup work around the Sand Filter.
Concrete poured on the Sand Filter on the south side/eastbound US Route 2
This week: Work continued on the Sand Filter; Sidewalk preparation began; Curb installation continued.
The anticipated work schedule for the week beginning June 26, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue sidewalk preparation with potential concrete pour later in the week.
- Continue form work on the Sand Filter.
Form work and rebar installed on the Sand Filter on the south side/eastbound US Route 2
This week: Installation of curbing began. Work continued on the Sand Filter.
The anticipated work schedule for the week beginning June 19, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue curb installation throughout the project limits.
- Prepare sidewalk areas for concrete pour.
- Continue form work on the Sand Filter.
Curb installation on the north side/westbound US Route 2
This week: Work continued on the installed Sand Filter along with curb preparation.
The anticipated work schedule for the week beginning June 12, 2023 is as follows:
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Curb installation to begin throughout the project limits.
- Continue work on the Sand Filter.
Work continues on the Sand Filter south side of US Route 2
This week: Stripped the forms for the newly poured Sand Filter walls; Began curb preparation; Paved the leveling course throughout the project.
Below is the anticipated work schedule for the week beginning June 5, 2023.
Monday through Friday-6:30 a.m. to 6:00 p.m.:
- Continue excavation work along the shoulder areas to prep for curbing installation to begin later in the week.
Paving leveling course on Industrial Avenue
This week: Installed Sand Filter wall forms and poured concrete.
Below is the anticipated work schedule for the week beginning May 30, 2023.
Tueday through Friday-6:30 a.m. to 6:00 p.m.:
- Excavation work along the shoulder areas to prep for curbing installation and to remove "extra" pavement placed for the lane shift implementation.
- Continued work on the Sand Filter to include backfilling around the walls.
Tueday and Wednesday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, paving leveling course in various areas throughout the project limits.
TRAFFIC IMPACT: Flaggers will be present during daytime work hours to allow for construction vehicles in/out of the construction area with minimal impact on the traveling motorists.
Motorists can expect flaggers present during Tuesday and Wednesday night work hours allowing for one-lane of alternating travel for paving operations.
Sand Filter walls formed in preparation for concrete
This week: Support excavation work continued for the Sand Filter.
Below is the anticipated work schedule for the week beginning May 22, 2023.
Monday through Thursday-6:30 a.m. to 6:00 p.m., Friday - 6:30 a.m. to noon:
- Continue placement of forms and pouring the concrete walls for the Sand Filter near Muddy Brook at the Williston/So. Burlington Town line.
Base mat for Sand Filter ready for concrete
This week: Support excavation work continued for the Sand Filter.
Below is the anticipated work schedule for the week beginning May 15, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Placement of forms for the pouring of concrete for the base mat of the Sand Filter near Muddy Brook at the Williston/So. Burlington Town line.
Continued support excavation for a stormwater Sand Filter near Muddy Brook on US Route 2, Williston
Minimal work this week due to the rain.
Below is the anticipated work schedule for the week beginning May 8, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- To complete the installation of the support of excavation for the Sand Filter near Muddy Brook at the Williston/So. Burlington Town line.
- Begin form and prep work for the Sand Filter.
Base preparation for a storm water Sand Filter near Muddy Brook on US Route 2, Williston
Work began on the installation of support excavation for the Sand Filter near Muddy Brook.
Below is the anticipated work schedule for the week beginning May 1, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Complete the installation of the support of excavation for the Sand Filter near Muddy Brook at the Williston/So. Burlington Town line.
Excavation for a Sand Filter near Muddy Brook on US Route 2, Williston
Below is the anticipated work schedule for tonight, April 19, 2023 and the week beginning April 24, 2023.
Tonight, April 19, 2023 - 7:00 p.m. to 6:00 a.m.:
- Installation of a long-term temporary lane shift in anticipation of work to begin on the final phase of the new drainage infrastructure installed during the 2022 season. Lane shifts will be between Gregory Drive, So. Burlington and Adams Court, Williston.
TRAFFIC CONTROL: Motorists can expect traffic control present allowing for one lane of alternating traffic within the work area. Two lanes of traffic will resume by 6:00 a.m. Friday morning.
Friday-April 20, Monday through Friday (Next week) - 6:30 a.m. to 6:00 p.m.:
- Begin to install the support of excavation for the Sand Filter near Muddy Brook at the Williston/So. Burlington Town line.
- Installation of erosion control throughout the project limits.
TRAFFIC CONTROL: Flaggers will be present to allow for construction vehicles in/out of the construction area with minimal impact on the traveling motorists.
Work to resume on US Route 2/Industrial Avenue, Williston
There was no work was performed this week.
The following is the anticipated work schedule for the week beginning Monday, November 28, 2022.
Monday through Thursday - Daytime:
- Project cleanup throughout.
The following is the anticipated work schedule for the week beginning Monday, November 21, 2022.
Monday & Tuesday - Daytime and Wednesday until noon:
- Project cleanup throughout with no traffic impact.
Thursday & Friday - No work due to the Thanksgiving Day holiday.
The following is the anticipated work schedule for the week beginning Monday, November 14, 2022.
Monday through Friday - Daytime:
- Weather permitting, installation of pavement markings.
- Minimal site cleanup work throughout the project limits.
- Potential opening of the second left turn lane on US Route 2 eastbound onto Industrial Avenue.
Winter shut-down preparation continues.
The following is the anticipated work schedule for the week beginning Monday, November 7, 2022.
Monday through Friday - Daytime:
- Continued winter shut-down preparation work to include various items throughout the project limits.
- Weather permitting, line striping throughout.
- The second left turn lane on US Route 2 eastbound onto Industrial Avenue will be opened.
CONSTRUCTION UPDATE: Winter shut-down preparation continues.
The following is the anticipated work schedule for the week beginning Monday, October 31, 2022.
Monday through Friday - Daytime:
- Continued winter shut-down preparation work to include various items throughout the project limits.
CONSTRUCTION UPDATE: Shoulder material has been placed throughout the project limits and structures were lowered.
Tomorrow, Friday, October 21, 2022 paving along the edge lines on Industrial Avenue between US Route 2 and Avenue A. Motorists can expect moderate traffic delays.
The following is the anticipated work schedule for the week beginning Monday, October 24, 2022.
Monday through Friday - Daytime:
- Continued winter shut-down preparation work to include various items throughout the project limits.
The following is the anticipated work schedule for the week beginning Monday, October 17, 2022.
Monday through Friday - Daytime:
- Installation of shoulder material throughout the project limits.
- Winter shut-down preparation work to include various items throughout the project limits.
There was no work performed this week.
There will not be any work taking place on this project for the week beginning Monday, October 10, 2022.
Due to the weather this week, there was no work performed.
There will not be any work taking place on this project for the week beginning Monday, October 3, 2022.
The following is the anticipated work schedule for the week beginning Sunday, September 25, 2022:
Sunday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, paving project approaches to include Industrial Avenue at Avenue A, US Route 2 both east and west ends of the project.
Monday through Friday - Daytime:
- General clean-up work throughout the project preparing for winter shut-down.
There will not be any work taking place on this project for the week beginning Monday, September 19, 2022.
There will not be any work taking place on this project for the week beginning Monday, September 12, 2022.
The following is the anticipated work schedule for the week beginning Monday, September 5, 2022:
Monday:
- No work due to the Labor Day holiday.
Tuesday through Wednesday - Daytime:
- Minimal work to include continued project clean-up and top soil work.
NEW TRAFFIC PATTERN ALERT!
Motorists be aware the US Route 2/Industrial Avenue intersection has been updated with new traffic signal and lane assignments. We ask all motorists to proceed with caution while passing through this intersection, allowing everyone to become familiar with these changes.
Installation of new traffic signals
The following is the anticipated work schedule for the week beginning Monday, August 29, 2022:
Monday through Wednesday - Daytime:
- Project clean-up in preparation for curb installation
- Top soil and seeding throughout the project with minimal traffic disruption
Thursday and Friday - Daytime:
- Drainage work on the western end of the project with no impact to the traveling motorists
The following is the anticipated work schedule for the week beginning Monday, August 22, 2022:
- Top soil and seeding throughout the project with minimal traffic disruption
- Traffic signal work within the US Route 2 and Industrial Avenue intersection
- Grading and prep work for a shoulder apron on the northeast corner of Industrial Avenue
- Installation of new traffic signal mast arms
- Installation of temporary line striping on the intermediate level of pavement throughout the project limits
The following is the anticipated work schedule for the week beginning Monday, August 15, 2022:
- Lane shifts on Industrial Avenue for revegetation work on the west side embankment north of Doggy Day Care
- Roadway preparation and paving the second lift on Industrial Avenue to include Avenue A intersection and the Asten Johnson driveway apron
- Roadway preparation and paving the second lift within the US Route 2 and Industrial Avenue intersection - MOTORISTS WILL FOLLOW A SIGNED DETOUR USING US ROUTE 2 AND VT ROUTE 2A DURING THIS POSTED TIME
The following is the anticipated work schedule for the week beginning Sunday, August 7, 2022:
- Milling the existing pavement on the west end of the project on US Route 2
- Roadway excavation and removal of the concrete slabs on the west end of the project on US Route 2
- Continue with roadway excavation and backfilling with select materials
- Paving the excavated area on the west end of the project on US Route 2
The following is the anticipated work schedule for the week beginning Sunday, July 31, 2022:
- Continued full-depth reconstruction and drainage on the west end of the project on US Route 2.
- Weather permitting, paving the reconstructed area worked on this week.
Motorists can expect to be traveling on a gravel surface this week. During the nighttime work hours, expect traffic control allowing for one-lane of alternating travel within the work area on US Route 2.
The following is the anticipated work schedule for the week beginning Monday, July 25, 2022:
- Continued full-depth reconstruction and drainage on Industrial Avenue near Avenue A. Motorists can expect one lane of alternating travel with traffic control present.
- Full-depth reconstruction on US Route 2 from Adams Drive working westerly within the closure area.
7:00 p.m. to 6:00 a.m. Industrial Avenue will be closed from the intersection of U.S. Route 2 to the north side of Avenue A. All motorists on U.S. Route 2 wanting to travel onto Industrial Avenue will follow a signed detour to VT Route 2A northbound, back to Industrial Avenue. All motorists on VT Route 2A will still be able to access Industrial Avenue up to and including Avenue B, otherwise will follow the signed detour to U.S. Route 2. Motorists on US Route 2 will encounter traffic control allowing for one-lane of alternating travel.
WORK SCHEDULE FOR THE REMAINDER THIS WEEK 7:00 p.m. to 6:00 a.m. WITH INDUSTRIAL AVENUE DETOUR:
- Paving on US Route 2 east of the Industrial Avenue intersection.
- Installation of under drain across Avenue A. Avenue A will be closed. Emergency access will be provided.
- Continued full-depth reconstruction on Industrial Avenue near Avenue A.
- Begin full-depth reconstruction on the westerly end of the project on US Route 2 within the closure area.
REMINDER: Tomorrow, Friday July 8: 7:00 p.m. to 6:00 a.m. WITH DETOUR:
- Paving on VT Route 2 on the reconstructed areas worked on this week. The Industrial Avenue detour will be implemented.
- Continued full-depth reconstruction on the east end of US Route 2 on both sides of the Industrial Avenue intersection. US Route 2 will be down to one lane of alternating travel with traffic control present.
The following is the anticipated work schedule for the week beginning Monday, July 4, 2022:
- No work due to the Independence Day holiday.
- Continued full-depth reconstruction on the east end of US Route 2 in the westbound lane. Industrial Avenue will be closed and the detour will be in affect. US Route 2 will be down to one lane of alternating travel with traffic control present.
- Paving the reconstructed areas worked on this week.
The following is the anticipated work schedule for the week beginning Sunday, June 26, 2022:
- Continued full-depth reconstruction on Industrial Avenue working north to Avenue A.
- Continued full-depth reconstruction on US Route 2 east of the traffic signal.
- Paving the reconstructed areas worked on this week.
The following is the anticipated work schedule for the week beginning Monday, June 20, 2022:
- Continued full-depth reconstruction of the roadway on the eastern end of the project on both Industrial Avenue and US Route 2.
This work will cause Industrial Avenue will be closed from the intersection of U.S. Route 2 to the north side of Avenue A. All motorists on U.S. Route 2 wanting to travel onto Industrial Avenue will follow a signed detour to VT Route 2A northbound, back to Industrial Avenue. All motorists on VT Route 2A will still be able to access Industrial Avenue up to and including Avenue B, otherwise will follow the signed detour to U.S. Route 2. Motorists on US Route 2 will encounter traffic control allowing for one-lane of alternating travel.
The following is the anticipated work schedule for the week beginning Monday, June 13, 2022:
- Full-depth reconstruction of the roadway on the eastern end of the project on both Industrial Avenue and the eastbound lane of US Route 2.
Industrial Avenue will be closed from the intersection of U.S. Route 2 to the north side of Avenue A. All motorists on U.S. Route 2 wanting to travel onto Industrial Avenue will follow a signed detour to VT Route 2A northbound, back to Industrial Avenue. All motorists on VT Route 2A will still be able to access Industrial Avenue up to and including Avenue B, otherwise will follow the signed detour to U.S. Route 2. Motorists on US Route 2 will encounter traffic control allowing for one-lane of alternating travel.
The following is the REVISED anticipated work schedule for the week beginning Monday, June 6, 2022:
- Project cleanup work throughout the project limits
- Realignment of the concrete barriers as the crew prepare for nighttime activities on Industrial Avenue. Motorists should expect moderate traffic delays.
The following is the anticipated work schedule for the week beginning Monday, June 6, 2022:
- Project cleanup work along with realignment of the concrete barriers as the crew prepare for nighttime activities on Industrial Avenue. Motorists should expect moderate traffic delays.
- Begin full-depth reconstruction of the roadway on Industrial Avenue from the U.S. Route 2 intersection to the north side of Avenue A.
DETOUR ALERT
Beginning June 7, 2022, Tuesday through Thursday from 7:00 p.m. to 6:00 a.m., Industrial Avenue will be closed from the intersection of U.S. Route 2 to the north side of Avenue A, allowing for the contractor to complete full-depth reconstruction of the roadway. All motorists on U.S. Route 2 wanting to travel onto Industrial Avenue will follow a signed detour to VT Route 2A northbound, back to Industrial Avenue. All motorists on VT Route 2A will still be able to access Industrial Avenue up to and including Avenue B, otherwise will follow the signed detour to U.S. Route 2. This detour is expected to be in effect for 2 to 3 weeks. Industrial Avenue will be open to through traffic during daytime hours and weekends. Updates will be made on the weekly alerts.
The following is the anticipated work schedule for the week beginning Monday, May 23, 2022:
- Installation of drainage across Industrial Avenue adjacent to Avenue A.
- General cleanup throughout the project.
- Preparation grading on the north side of US Route 2 in anticipation of base paving.
The following is the anticipated work schedule for the week beginning Monday, May 16, 2022:
- Continue with the installation of new drainage system on Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, May 9, 2022:
- Installation of new drainage system crossing over to the west side Industrial Avenue. Motorists will encounter a lane closure allowing for one lane of alternating travel.
- Continue with the installation of new drainage system on Industrial Avenue.
- Temporary paving of the road cuts on Industrial Avenue.
- Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction on Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:
- Continue with the installation of new drainage system on Industrial Avenue.
The following is a revised anticipated work schedule for the remainder of the week beginning Wednesday, April 20, 2022 @ 7:00 p.m.:
- Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction within the Industrial Avenue intersection.
- No work on the project.
The following is the anticipated work schedule for the week beginning Monday, April 18, 2022:
- Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
- Continue full-depth reconstruction east of Miller Lane
The following is the anticipated work schedule for the week beginning Monday, April 11, 2022:
- Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
- Continue full-depth reconstruction between Adams Drive and Industrial Avenue.
Nighttime drainage installation on VT Route 2 through the Miller Lane Intersection
The following is the anticipated work schedule for the week beginning Monday, April 4, 2022:
- Continue with the installation of storm drain through the Miller Lane intersection.
- Continue installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.
- Continue with the installation of storm drain from Miller Lane proceeding east.
New drainage installation continues easterly on VT Route 2
The following is the anticipated work schedule for the week beginning Monday, March 28, 2022:
- Mobilization of construction equipment back on site the beginning of the week.
- Continue with the installation of storm drain just east of Miller Lane proceeding east to Industrial Avenue.
- Installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.
The following is the anticipated work schedule for the week beginning Monday, February 7, 2022:
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 31, 2022:
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 24, 2022:
- Installation of trench boxes to facilitate auger boring.
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
- Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 across Miller Lane working on half the Lane at a time to allow for motorists access.
- Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 east of Miller Lane working to Industrial Avenue.
- Directional boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 10, 2022:
- Continue installation of new drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, January 3, 2022:
- Continue installation of drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, December 27, 2021:
- Continued work on new signal foundations
Thursday and Friday:
- No work scheduled
- Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
- Continue work on the installation of a new signal for the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, December 13, 2021:
- Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
- Continue work on the installation of a new signal for the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, December 6, 2021:
- General operations and clean up work throughout the project.
- Boring operations to install conduit under US Route 2 at the Industrial Avenue intersection in preparation for a new signal installation.
The following is the anticipated work schedule for the week beginning Monday, November 29, 2021:
- Continue full depth reconstruction and drainage improvements on the north side of Route 2.
The following is the anticipated work schedule for the week beginning Monday, November 22, 2021:
- No work schedule for this week.
- Continue full depth reconstruction on the north side (westbound) of Route 2
- Continue drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, November 8, 2021:
- Begin full depth reconstruction on the north side (westbound) of Route 2
- Begin drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, November 1, 2021:
- Begin full depth reconstruction on the north side (westbound) of Route 2
- Begin drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, October 25, 2021:
- Line striping the newly paved roadway on the south side of US Route 2
- Driveway and side road approaches to be tied into the new eastbound lane
- Work necessary to change over the traffic pattern to include the newly paved south side of US Route 2. Motorists can expect traffic control to be present allowing for 1-lane of alternating travel.
- General work throughout the project
The following is the anticipated work schedule for the week beginning Monday, October 18, 2021:
- Fine grading the newly installed subbase roadway on the south side of US Route 2
- Paving the fine graded south side of US Route 2
- Weather permitting, installation of pavement markings
- General cleanup work within the southside of US Route 2 work area
The following is the anticipated work schedule for the week beginning Monday, October 11, 2021:
- No work due to the Indigenous Person's Day holiday
- Installation of the enclosed drainage system within the Industrial Avenue intersection, traffic control will be present allowing for 1 lane of alternating travel
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side working easterly
- Fine grading the southside work area on Route 2 in anticipation of base paving
The following is the anticipated work schedule for the week beginning Monday, October 4, 2021:
- Signal work at Industrial Avenue with no traffic disruptions
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side from Adams Drive working east
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction moving across US 2 from the south side over to the north side
Motorists can expect a lane closure with traffic control present during the nighttime work
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side on the western end of the project working east
The following is the anticipated work schedule for the week beginning Monday, September 20, 2021:
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
- Begin installation of the enclosed drainage system (stormwater) and full depth reconstruction across US 2
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side of US 2 at the west end of the project near Muddy Brook.
The following is the anticipated work schedule for the week beginning Monday, September 6, 2021:
- No work due to the Labor Day holiday
- Continue work on enclosed drainage system (storm water) within the US 2 and Industrial Avenue intersection
- Continue full depth reconstruction on the south side of Route 2 within the US 2 and Industrial Avenue intersection
The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Continue full depth reconstruction on the south side of Route 2 easterly from Engineers Drive
The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Continue full depth reconstruction on the south side of Route 2
The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Begin full depth reconstruction on the south side of Route 2
The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
- Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2
Monday 7:00 p.m. to 6:00 p.m.:
- Weather permitting, line striping the detour area in anticipation of opening the lane on Tuesday.
- Work on enclosed drainage system at the eastern limit of the project
The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:
- Completion of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Lane shifts to begin onto the detoured roadway
- Continue work on enclosed drainage system (storm water) on Route 2
The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
- Continue construction of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Waterline testing on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:
- Continue construction of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Continue waterline work on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:
- No work due to the Independence Day holiday
- Continue construction of the detour on the north side of Route 2.
- Begin work on enclosed drainage system (storm water) on Route 2
Designated lane shifts in both travel lanes within the construction area during working hours.
The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:
- Continue waterline installation on Industrial Avenue
- Continue construction of the detour on the north side of Route 2. This work will require designated lane shifts in both travel lanes within the construction area during working hours.
The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
- Continue waterline installation on Industrial Avenue
- Continue construction of the detour on the north side of Route 2. This work will requre designated lane shifts in both travel lanes within the construction area during working hours.
The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:
- New waterline tie-ins to existing services
- Continue waterline installation on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:
- Continue flushing, testing and chlorinating new waterline installed on Route 2
- Continue waterline installation on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:
- No work due to the Memorial Day holiday
- Flushing, testing and chlorinating new waterline installed on Route 2
- Continue waterline installation on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:
- Continue waterline work on both Route 2 and moving onto Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
- Continue waterline work throughout the project limits
- Installation of water line sleeve across VT Route 2/Industrial Avenue intersection
The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
- Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
- Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
- The main entrance to Engineers Drive will be closed to motorists to allow for the waterline installation.
- Continue waterline work on the south side of Route 2 working from west to east.
The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:
- Continue waterline work on the south side of Route 2 working from west to east.
The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:
- Continue waterline work on the south side of Route 2 working from west to east.
The following is the anticipated work schedule for the week beginning Monday, April 12, 2021:
- Continue water line work on the south side of Route 2 working from west to east.
- Continue erosion control measures throughout the project limits
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
The following is the anticipated work schedule for the week beginning Monday, April 1, 2021:
- Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So. Burlington town line.
- Project delineation and erosion control measures to be installed throughout the project limits
- Tree removal within the State Right of Way within the Industrial Avenue section.
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
The following is the anticipated work schedule for the week beginning Monday, March 29, 2021:
- Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.
Motorists can expect minimal impact on the traffic within the work area.
The following is the anticipated work schedule for the week beginning Monday, March 22, 2021:
- Water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.
Motorists can expect intermediate impact on the traffic within the work area.
The following is the anticipated work schedule for the week beginning Monday, March 15, 2021:
- Installation of construction signs
- Tree cutting