The Vermont Agency of Transportation in conjunction with Kubricky Construction Corporation is reconstructing U.S. Route 2 from the Richmond-Williston town line extending easterly for approximately 8.25 miles to approximately halfway between the Notch Road and the Bolton Access Road in Bolton.
During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present. During one of the culvert replacements, a overnight closure of US-2 will be required. Motorists should also expect to be traveling on a gravel surface during construction.
The posted speed limit will be strictly enforced as the safety of the workers along with the motorists is of the utmost importance. We ask motorists to use extreme caution while traveling through the zone. Please note the fines for speeding within the construction zone will be doubled.
No traffic interruptions anticipated. Please follow the posted speed limits.
WEEKLY CONSTRUCTION UPDATE:
THIS PROJECT IS COMPLETE!
On behalf of the Vermont Agency of Transportation and myself, we would like to thank everyone for your patience and understanding during this construction project.
We hope you enjoy the improvements, not only for your safety, but also for the smooth ride.
Stay safe and buckle up!
Completed project - VT Route 2 facing west near River View Cemetery
There is no work scheduled for the week of July 22, 2024.
PROJECT UPDATE: No work performed.
The following is the anticipated work schedule for the week beginning Monday, July 15, 2023:
Monday through Friday - 7:00 a.m. to 6:00 p.m.:
- No work anticipated this week.
PROJECT UPDATE: No work performed.
The following is the anticipated work schedule for the week beginning Monday, July 8, 2023:
Monday through Friday - 7:00 a.m. to 6:00 p.m.:
- Continue with completion of punch list items and general project clean-up work.
PROJECT UPDATE: No work performed.
The following is the anticipated work schedule for the week beginning Monday, July 1, 2023:
Monday and Tuesday - 7:00 a.m. to 6:00 p.m., Wednesday 7:00 a.m. to Noon:
- Continue with completion of punch list items and general project clean-up work.
PROJECT UPDATE: Completed driveway tie-ins; Continued project clean-up.
The following is the anticipated work schedule for the week beginning Monday, June 24, 2023:
Monday through Friday - 7:00 a.m. to 6:00 p.m. (daytime work):
- Continue with completion of punch list items and general project clean-up work.
Final driveway tie-in on U.S. Route 2
PROJECT UPDATE: Completed 90% of the driveway tie-ins; Began project clean-up.
The following is the anticipated work schedule for the week beginning Monday, June 17, 2023:
Monday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, continue driveway tie-ins between Willis Farm Road Road and Kenyon Road.
- Project clean-up.
Monday through Friday - 7:00 a.m. to 6:00 p.m. (daytime work):
- Punch list items and general project clean-up work.
Driveway tie-in on U.S. Route 2
PROJECT UPDATE: Shoulder work continued; Pavement markings were installed; Conducted structure clean-out work as well as driveway tie-ins.
The following is the anticipated work schedule for the week beginning Sunday, June 9, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, continue driveway tie-ins between Kenyon Road and Lemroy Court.
- Begin project punch list items.
Final pavement markings on U.S. Route 2 near the I-89 interchange
PROJECT UPDATE: Completed paving the final wearing course on the abutting side roads; Shoulder work; Installed audio messaging for pedestrian crossing at the Main Street and Jericho/Bridge Street intersection.
The following is the anticipated work schedule for the week beginning Sunday, June 2, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, driveway tie-ins between Kenyon Road and Lemroy Court.
- Structure clean-out.
- Weather permitting, complete final pavement markings.
- Begin project punch list items.
Placed shoulder material along U.S. Route 2 between Kenyon Road and Lemroy Court
PROJECT UPDATE: Completed paving the final wearing course on U.S. Route 2; Completed the installation of bridge joints.
The following is the anticipated work schedule for the week beginning Sunday, May 26, 2023:
Sunday and Monday:
- No work due to the Memorial Day Holiday.
Tuesday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, continue the installation of the wearing course of pavement (final) on the side road aprons between Willis Farm Road and Lemroy Court.
- Installation of shoulder material between Kenyon Road and Lemroy Court.
- Driveway tie-ins between Willis Farm Road and Lemroy Court.
- Weather permitting, final pavement markings.
Tuesday through Friday - 7:00 a.m. to 7:00 p.m.:
- Driveway tie-ins between Kenyon Road to Willis Farm Road.
Paving wearing course on U.S. Route 2 along side the Riverview Cemetery
PROJECT UPDATE: Completed paving the leveling course on US Route 2 between Kenyon Road and I-89 Exit 11 southbound On-Ramp; Began paving the wearing course of paving (final) began at approximately Kenyon Road and proceed east towards the Richmond Village; Installed new sidewalk ramps at the intersection of U.S. Route 2 and Bridge Street/Jericho Road.
The following is the anticipated work schedule for the week beginning Sunday, May 19, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, continue the installation of the wearing course of pavement (final) from approximately Kenyon Road proceeding to Lemroy Court.
- Bridge joint work on the bridges near Snipe Ireland Road and VT Route 117.
Monday through Thursday - 7:00 a.m. to 7:00 p.m.; Friday - 7 a.m. to noon:
- Continue the installation of new roadway signage.
New sidewalk ramps at the intersection of U.S. Route 2 and Bridge Street/Jericho Road
PROJECT UPDATE: Completed milling on US Route 2 in various locations in preparation for pavement; Reset curb in and around the US Route 2 and Bridge Street/Jericho Road intersection; Adjusted drainage and sewer structures in preparation for final paving.
The following is the anticipated work schedule for the week beginning Sunday, May 12, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Weather permitting, begin installing the leveling course of pavement between Kenyon Road and and I-89 Exit 11 southbound On-Ramp.
- After the leveling course is paved and weather permitting, begin installing the wearing course (final) of pavement from Kenyon Road proceeding to Lemroy Court.
- Sidewalk installation within the U.S. Route 2 and Bridge Street/Jericho Road intersection.
Milling US Route 2 in preparation for paving of leveling course
PROJECT UPDATE: Completed the installation of new guardrails along US Route 2 between the Exit 11 interchange and VT Route 117; Continued work on the new traffic signal at the US Route 2 and Bridge Street/Jericho Road intersection; Began installation of new traffic signs.
The following is the anticipated work schedule for the week beginning Sunday, May 5, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Begin milling sideroad abutments within Richmond Village and various locations on U.S. Route 2 between River View Cemetery and Willis Farm Road.
- Begin milling on U.S. Route 2 between Kenyon Road and I-89 Exit 11 southbound On-Ramp.
- Beginning Monday night - structure adjusment on Baker, Millet and Bridge Streets along with Jericho Road.
- Sidewalk and curb installation within the U.S. Route 2 and Bridge Street/Jericho Road intersection.
- Tentative paving late in the week to install a leveling course between Kenyon Road and I-89 Exit 11 southbound On-Ramp.
Monday through Friday - Daytime:
- Continue installation of new traffic signs with little to no traffic interruptions.
New signal installed at the intersection of US Route 2 and Bridge Street/Jericho Road
PROJECT UPDATE: Installed new guardrails along US Route 2 between the Exit 11 interchange and VT Route 117; Completed the new traffic signal at the US Route 2 and Bridge Street/Jericho Road intersection; Repaired the slope near the Riverview Cemetary.
The following is the anticipated work schedule for the week beginning Sunday, April 28, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Continue installation of new gaurdrail between Kenyan Road and the I-89 southbound Exit 11 on-ramp.
Monday through Friday - Daytime:
- Continue work on the newly installed traffic signal with little to no traffic interruptions.
US Route 2 new guardrail installation
PROJECT UPDATE: Completed all mainline structure adjustements in preparation for final paving; Installation of the new mast pole foundations for the new traffic signals.
The following is the anticipated work schedule for the week beginning Sunday, April 21, 2023:
Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Continue installation of a new traffic signal infrastructure at the intersection of US Route 2 and Jericho/Bridge Street.
- Installation of new gaurdrail between Kenyan Road and the I-89 southbound Exit 11 on-ramp.
US2 and Jericho Road intersection mast pole foundation work for traffic signal
PROJECT UPDATE: A temporary pedestrian crossing was installed; Installation of a new mass pole foundation.
The following is the anticipated work schedule for the week beginning Friday, April 12, 2023:
Friday, Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Continue installation of a new traffic signal infrastructure at the intersection of US Route 2 and Jericho/Bridge Street.
PROJECT UPDATE: Work resumed with the contractor remobilizing to the project.
The following is the anticipated work schedule for the week beginning April 8, 2023:
Monday:
- No work due to the anticipated influx of motorists in Vermont for the Solor Eclipse.
Tuesday Through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):
- Begin installation of a new traffic infrastructure at the intersection of US Route 2 and Jericho/Bridge Street intersection.
US2 and Jericho/Bridge Street intersection facing west
This project is shut down for the 2023 construction season.
Project updates will resume in spring 2024, prior to any construction work.
Have a safe and happy holiday season / winter.
This week ending 11/16/23: Completed driveway tie-ins throughout the project; Installed guardrail delineations; Project clean up.
Culvert installed near the Riverview Cemetery due to the July 16 storm event
This week ending 11/10/23: Backfilled the newly installed concrete curbing west of the Richmond Village: Installation a new culvert near the Riverview Cemetery; Completed driveway tie-ins throughout the project.
The following is the anticipated work schedule for the week beginning November 13, 2023:
Monday Through Friday - 7:00 a.m. to 4:30 p.m.:
- Backfilling the newly installed concrete curb.
- Project clean up in preparation of winter shut down.
Culvert replacement work near the Riverview Cemetery due to the July 16 storm event
This week ending 11/3/23: Continued installation of concrete curb along the roadway near the Riverview Cemetery, and continued driveway tie-ins throughout the project.
The following is the anticipated work schedule for the week beginning November 5, 2023:
Sunday through Friday 7:00 p.m. to 7:00 a.m.:
- Continue backfilling the curb along the base of the slope near Riverview Cemetery.
- A large culvert replacement across U.S. Route 2 between Riverview Cemetery and Willis Farm Road due to the July 16 storm event.
Monday Through Friday - 7:00 a.m. to 5:30 p.m.:
- Weather permitting, continue paving driveway tie-ins and various patches throughout the project limits.
- Project clean up in preparation of winter shut down.
Continue form work for placement of concrete curb
This week ending 10/27/23: Began installation of concrete curb along the roadway near the Riverview Cemetery; Completed the drainage upgrade along the roadway near Riverview Cemetery; Began driveway tie-ins on the eastern end of the project; Installed pavement markings throughout the project.
The following is the anticipated work schedule for the week beginning October 29, 2023:
Sunday through Friday 7:00 p.m. to 7:00 a.m.:
- Continue forming and backfilling the curb along the base of the slope near Riverview Cemetery.
Monday Through Friday - 7:00 a.m. to 5:30 p.m.:
- Weather permitting, continue paving driveway tie-ins between Lemroy Court and Cochran Road.
- Continue installation of concrete curb near Riverview Cemetery.
Forms installed for the placement of concrete curb near Riverview Cemetery
This week ending 10/20/23: Completed the installation of shoulder material, centerline rumble strip and final mainline pavement markings throughout the project; Upgraded the drainage along the roadway near Riverview Cemetery; Completed the ditch and slope repair between Lemroy Court and the I-89 Exit 11 interchange.
The following is the anticipated work schedule for the week beginning October 22, 2023:
Sunday through Friday 7:00 p.m. to 7:00 a.m.:
- Begin forming the curb along the base of the slope near Riverview Cemetery.
Monday Through Friday - 7:00 a.m. to 6:30 p.m.:
- Weather permitting, continue paving driveway tie-ins between Lemroy Court and the eastern end of the project.
- Set concrete curb near Riverview Cemetery.
Final paving continues on the west end of the project
This week ending 10/13/23: Began installation of shoulder material between Locust Knoll and the I-89 Exit 11 interchange; Continued ditch and slope repair between Lemroy Court and the I-89 Exit 11 interchange.
The following is the anticipated work schedule for the week beginning October 22, 2023:
Sunday through Friday 7:00 p.m. to 7:00 a.m.:
- Continue ditching and slope work between Lemroy Court and the I-89 Exit 11 interchange.
Monday Through Friday - 7:00 a.m. to 6:30 p.m.:
- Weather permitting, paving driveway tie-ins between Lemroy Court and the eastern end of the project.
- Continue shoulder work between Lemroy Court and the eastern end of the project.
- Wednesday, weather permitting, continue the final lift of paving between Kenyan Road Road and the Richmond/Williston town line.
Shoulder material being installed from Lemroy Court to the east end of the project
This week ending 10/06/23: Completed installation of the second lift of pavement between Cochran Road and Lemroy Court. Completed the installation of guardrail between Riverview Cemetery and the I-89 Exit 11 interchange.
The following is the anticipated work schedule for the week beginning October 8, 2023:
Sunday and Monday:
- No work due to the Columbus / Indigenous Peoples' Day holiday
Monday 9:00 p.m. to 7:00 a.m., Tuesday through Friday 7:00 p.m. to 7:00 a.m.:
- Continue ditching and slope work between Lemroy Court and the I-89 Exit 11 interchange.
Tuesday Through Friday - 7:00 a.m. to 6:30 p.m.:
- Weather permitting, continue the final lift of paving between Kenyan Road Road and the Richmond/Williston town line.
- Weather permitting, paving driveway tie-ins between Lemroy Court and the eastern end of the project.
- Continue shoulder work between Lemroy Court and the eastern end of the project.
Newly installed guardrail
This week ending 9/29/23: Completed installation of the second lift of pavement between Kenyan Road and the Richmond/Williston town line. Installed driveway tie-ins within the Richmond Village.
The following is the anticipated work schedule for the week beginning October 2, 2023:
Sunday through Friday - 7:00 p.m. to 6:30 a.m.:
- Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
- Continue ditching, shoulder work, and guardrail installation between Baker Street and the I-89 Exit 11 interchange.
Monday Through Friday - 6:30 a.m. to 6:30 p.m.:
- Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
- Later in the week, weather permitting, continue paving the final lift of pavement from Kenyon Road to the Richmond/Williston town line.
- Continue shoulder work from the eastern end of the project to Lemroy Court.
Continued paving wearing course (top) in Jonesville, working westerly
This week ending 9/22/23: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Began driveway tie-ins within the Richmond Village; Continued adjusting the sewer structures to pavement grade within the Richmond Village.
The following is the anticipated work schedule for the week beginning September 24, 2023:
Sunday through Friday - 7:00 p.m. to 6:30 a.m.:
- Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
- Continue ditching and shoulder work between Baker Street and the I-89 Exit 11 interchange.
Monday Through Friday - 6:30 a.m. to 6:30 p.m.:
- Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
- Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
- Continue driveway tie-ins from the eastern end of the project in Bolton to Lemroy Court.
- Continue shoulder work throughout the project limits.
Final paving began this morning on the east end of the project in Bolton, working westerly
This week ending 9/15/23: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Continued adjusting the sewer structures to pavement grade within the Richmond Village.
The following is the anticipated work schedule for the week beginning September 17, 2023:
Sunday through Friday - 7:00 p.m. to 6:30 a.m.:
- Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
- Continue signal upgrade work at the VT Route 117 & U.S. Route 2 Intersection and the Richmond Park and Ride intersection
Monday Through Friday - 6:30 a.m. to 6:30 p.m.:
- Weather permitting, begin the final lift of paving at the eastern most end of the project in Bolton proceeding westerly to Lemroy Court.
- Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
- Continue shoulder work throughout the project limits.
Base pavement completed throughout the project limits
This week ending 9/8/23: Completed slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line. Continued adjusting drainage and sewer structures to pavement grade between Lemroy Court and Baker Street.
The following is the anticipated work schedule for the week beginning September 11, 2023:
Monday through Friday - 7:00 p.m. to 6:30 a.m.:
- Weather permitting, continue paving the second course of pavement between Baker Street and the I-89 interchange.
- Continue adjustment of the drainage and sewer structures between Lemroy Court and Baker Street.
- Signal upgrade work at the VT Route 117 & U.S. Route 2 Intersection and the Richmond Park and Ride intersection
Monday Through Friday - 6:30 a.m. to 6:30 p.m.:
- Shoulder work from the eastern end of the project in Bolton to Lemroy Court in Richmond, in preparation of final final course of pavement to be placed.
The final stretch of roadway reconstruction on the west end of the project
This week ending 9/1/23: Completed the base course of bavement between Willis Farm Road and the I-89 interchange. Continued with slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line. Adjusted sewer structures to pavement grade within Richmond Village.
The following is the anticipated work schedule for the week beginning September 4, 2023:
Monday - No work due to the Labor Day holiday.
Tuesday through Friday - 7:00 p.m. to 6:30 a.m.:
- Weather permitting, continue paving the second course of pavement between Baker Street and the I-89 interchange.
- Adjustment of the drainage structures between Lemroy Court and Baker Street.
Tuesday Through Friday - 6:30 a.m. to 6:30 p.m.:
- Continue roadway reconstruction between Kenyon Road to the Richmond/Williston town line.
Base pavement installed end the west end of the project
This week ending 8/24/23: Completed slab removal and placement of subbase material on U.S. Route 2 between Willis Farm Road and the I-89 interchange. Began slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line.
The following is the anticipated work schedule for the week beginning Sunday, August 27, 2023:
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Weather permitting, paving between Lemroy Court to the I-89 interchange to include base course between Williston Farm Road to the I-89 interchange, and a second course between Lemroy Court through the Richmond Village to the I-89 interchange.
Monday Through Thursday - 7:00 a.m. to 6:30 p.m.; Friday 7:00 a.m. to noon:
- Continue roadway reconstruction between Kenyon Road to the Richmond/Williston town line
- Continue shoulder work between Cochran Road and Lemroy Court.
Roadway reconstruction proceeds on the west end of the project in Richmond
This week ending 8/18/23: Slab removal and placement of subbase material continued on U.S. Route 2 approximately 1/2 mile east of I-89 southbound Exit 11 on-ramp; Continued guardrail installation, ditching and slope repairs. Milling is complete between Kenyon Road and Richmond/Williston town line in preparation of roadway reconstruction.
The following is the anticipated work schedule for the week beginning Sunday, August 20, 2023:
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue with roadway reconstruction activities on the west end between Willis Farm Road and the I-89 interchange.
Monday Through Friday - 7:00 a.m. to 6:30 p.m.:
- Continue guardrail installation.
- Continue ditching and slope work along the shoulders throughout the project.
Roadway reconstruction continues on the west end of the project in Richmond
This week ending 8/11/23: Slab removal continued and placement of subbase material on U.S. Route 2 on the west end of the project; Continued paving the base course of pavement from Bridge Street and proceed west; New guardrail installation between the VYCC Farm and Snipe Ireland Road.
The following is the anticipated work schedule for the week beginning Sunday, August 13, 2023:
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction activities on the west end of the project proceeding west to the I-89 interchange.
Monday Through Wednesday - 7:00 a.m. to 6:30 p.m.:
- Weather permitting, final paving with the wearing course beginning at the east end of the project in Bolton proceeding west.
Thursday & Friday - 7:00 a.m. to 6:30 p.m.:
- Weather permitting, continued paving the base course of pavement on the gravel roadway on the west end of the project.
Base pavement placed this week within Richmond Village proceeding west
This week: Slab removal continued on U.S. Route 2 between River View Cemetery and Willis Farm Road; Completed slope and ditch work between Cochran Road and Lemroy Court.
The following is the anticipated work schedule for the week beginning Sunday, August 6, 2023:
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction activities from Willis Farm Road proceeding west to the I-89 interchange.
- Fine grading in preparation for base pavement between Baker Street and Willis Farm Road.
Thursday and Friday - 7:00 a.m. to 6:30 p.m.:
- Potential guardrail installation between Snipe Ireland Road and Lemroy Court
This week: Slab removal continued on U.S. Route 2 between Millet Street and Rivew View Cemetery; Completed guardrail installation in Jonesville; Slope and ditch work between Locust Knoll and Cochran Road was completed.
The following is the anticipated work schedule for the week beginning Sunday, July 31, 2023:
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction activities from River View Cemetery proceeding west to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Continue shoulder and ditch work between Lemroy Court and Locust Knoll.
- Guardrail installation between Snipe Ireland Road and Lemroy Court
Tuesday and Wednesday - 7:00 a.m. to 6:30 p.m.:
- Paving the base layer on U.S. Route 2 from Millet Street to the River View Cemetery
Nighttime US Route 2 - Excavating out existing roadway
This week: Work on roadway repairs from the recent heavy rainfall.
The following is the anticipated work schedule for the week beginning Sunday, July 23, 2023.
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Restart concrete slab removal and roadway reconstruction activities from Baker Street proceeding west to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Continue shoulder and ditch work between Lemroy Court and Cochran Road.
- Potential continuation of guardrail installation between Snipe Ireland Road and Lemroy Court.
This week: Limited operations this week due to the heavy rains. Guardrail work continued throughout the project.
The following is the anticipated work schedule for the week beginning Sunday, July 16, 2023.
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction from Millet Street proceeding west to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- General project cleanup work from Jonesville west towards Lemroy Court, Richmond.
- Guardrail installation continues between Snipe Ireland Road proceeding west towards Lemroy Court.
Guardrail work on US Route 2
ROUGH ROAD AHEAD!
Due to the heavy rain fall today July 10, 2023, motorists traveling on U.S. Route 2 in Richmond, VT between Millet Street and River View Cemetery can expect to be traveling on a rough road surface.
Please be assured the contractor is doing their best to maintain this graveled roadway.
This week: Completed 800' of roadway reconstruction between Millet Street to Riverview Cemetery; Installed the second lift of pavement between Locust Knoll Road and Lemroy Court.
The following is the anticipated work schedule for the week beginning Sunday, July 9, 2023.
Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction from Millet Street proceeding west to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Continue placement of shoulder material and ditch work between Cochran Road to the eastern end of the project in Bolton.
- Guardrail installation between Snipe Ireland Road to Lucust Knoll Road.
Thursday and Friday - 7:00 a.m. to 6:30 p.m.:
- Base paving on the gravel surface and gravel installation on the shoulders from Millet Street to Riverview Cemetery.
Roadway reconstruction on US Route 2, Richmond
This week: Completed the roadway reconstruction and base pavement on U.S. Route 2 between Lemroy Court and Millet Street; Installed three new electrial sleeves within the US 2/Bridge Street intersection for the new traffic signal system; Placed shoulder gravel between Cochran Road and Locust Knoll Road.
The following is the anticipated work schedule for the week beginning Monday, July 3, 2023.
Monday and Tuesday:
- No work scheduled due to the Independence Day holiday unless there is required roadway maintenace needed.
Wednesday and Thursday - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction within the Richmond Village beginning at Millet Street and proceeding west to the I-89 interchange.
- Structure adjustment within the US 2/Bridge Street intersection.
Wednesday through Friday - 6:30 a.m. to 6:00 p.m.:
- Weather permitting, paving and placement of shoulder material between Locust Knoll Road and Lemroy Court.
Slab removal on US Route 2 west of the Bridge Street intersection
EXPECT DELAYS!!
Motorists should expect extended delays today, June 26, 2023 through Friday, June 30, 2023 from 9:00 a.m. to 3:00 p.m. within the Richmond Village due to paving operations.
This week: Began concrete removal on U.S. Route 2 between Lemroy Court and Millet Street. Completed paving the base course of the gravel surface between Snipe Ireland Road and Lemroy Court.
The following is the anticipated work schedule for the week beginning Sunday, June 25, 2023.
Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:
- Continue concrete slab removal and roadway reconstruction beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Roadway maintenance throughout the gravel surface area.
Monday through Thursday - 8:00 a.m. to 2:30 p.m.:
- Base paving on the gravel surface between Lemroy Court and Riverview Cemetery.
Slab removal on US Route 2 within the Richmond Village
This week: The milling of U.S. Route 2 between Lemroy Court and just east of the I-89 interchange was completed. Structures were lowered within the Richmond Village.
The following is the anticipated work schedule for the week beginning Sunday, June 18, 2023.
Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:
- Begin concrete slab removal and roadway reconstruction beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange.
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Roadway maintenance throughout the gravel surface area.
Thursday and Friday - 7:00 a.m. to 6:30 p.m.:
- Base paving on the gravel surface between Snipe Ireland Road and Lemroy Court.
Nighttime grinding of existing pavement on US Route 2 west of the Richmond Village
This week: Completed the existing roadway reconstruction between Snipe Ireland Road and Lemroy Court; Continued another 2500' of intermediate paving (second lift).
The following is the anticipated work schedule for the week beginning Sunday, June 11, 2023.
Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:
- Grinding the existing roadway beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange
- Lowering of the existing drainage structures
Monday through Friday - 7:00 a.m. to 6:30 p.m.:
- Roadway maintenance throughout the gravel surface area.
- General project clean-up work.
Continue paving the 2nd "lift" of pavement on US Route 2, Richmond
This week: Another 2500' of existing roadway was reconstructed and 7000' of roadway was paved with a second lift of asphalt between Cochran Road and the VYCC Farm.
The following is the anticipated work schedule for the week beginning Monday, June 5, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
Breaking up concrete subbase under existing roadway
Paving the 2nd "lift" of pavement from Cochran Road proceeding west
This week: Another 2500' of existing roadway was reconstructed and 3000' of newly reconstructed roadway base, between Snipe Ireland Road and Lemroy Court, was paved.
The following is the anticipated work schedule for the week beginning May 30, 2023:
Tuesday through Friday - 6:30 a.m. to 6:00 p.m.:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
Tuesday and Wednesday - 6:30 a.m. to 6:00 p.m.:
- Weather permitting, paving the 2nd "lift" of pavement between Cochran Road and Snipe Ireland Road.
Thursday and Friday - 6:30 a.m. to 6:00 p.m.:
- Continue paving the base layer of roadway on the gravel surface between Snipe Ireland Road and Lemroy Court.
Paving base (1st lift) between Snipe Ireland Road and Lemroy Court
This week: Another 2000' of existing roadway was reconstructed and 400' of underdrain was upgraded.
The following is the anticipated work schedule for the week beginning May 22, 2023.
Monday through Thursday - 6:30 a.m. to 6:00 p.m., Friday 6:30 a.m. to noon:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
Tuesday and Wednesday - 6:30 a.m. to 6:00 p.m.:
- Paving the base from approximatley Snipe Ireland Road proceeding west over the gravel roadway surface.
Thursday - 6:30 a.m. to 6:00 p.m., and Friday 6:30 a.m. to noon:
- Weather permitting, paving the 2nd layer of roadway from approximatley the west end of Cochran Road and proceeding west to Snipe Ireland Road.
Installation of dense-graded gravel for roadway subbase
This week: 1500' of new guardrail was installed; 2500' of existing roadway was reconstructed and 500' of underdrain was upgraded.
The following is the anticipated work schedule for the week beginning May 15, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
- Continue underdrain work from Snipe Ireland Road proceeding west to Lemroy Court.
Continued guardrail installation in Bolton
This week: Limited work took place this week due to the rain to include two days of continued roadway excavation, slope work and roadway maintenace.
The following is the anticipated work schedule for the week beginning May 8, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
- Underdrain work from Snipe Ireland Road proceeding west to Lemroy Court.
- Guardrail installation east of Snipe Ireland Road to the end of the project in Bolton.
Grading to keep the integretiy of the roadway due to the excessive rainfall
Full-depth roadway excavation began between Snipe Ireland Road and Lemroy Court. Guardrail installation began on the east end of the project in Bolton with much more to be installed as the project proceeds.
The following is the anticipated work schedule for the week beginning May 1, 2023:
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
- Ditch work on the east end of the project near Jonesville.
Full depth roadway excavation between Snipe Ireland Road and Lemroy Court
The following is the anticipated work schedule for the week beginning April 24, 2023.
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Begin full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
- Installation of new gaurdrail between Boys Club Road to the east end of the project in Bolton.
- Slope stabilization and ditch work on the west end of the project between the intersection of VT Route 117 to the Richmond/Williston Town Line.
Milling operations between Snipe Ireland Road to Lemroy Court
The following is the anticipated work schedule for the week beginning Monday, April 17, 2023:
Monday through Friday - 6:30 a.m. to 6:00 p.m.:
- Milling (grinding of the existing pavement) from Snipe Ireland Road proceeding west to Lemroy Court.
- Installation of guardrail throughout the project limits.
- Erosion control measures throughout the project limits.
The following is the anticipated work schedule for the week beginning Monday, April 10, 2023:
Monday through Friday - 6:30 a.m. to 5:00 p.m.:
- Crews will be working on U.S. Route 2 between Snipe Ireland Road and Lemroy Court to adjust the guardrail in preparation for continued roadway reconstruction to begin next week.
Completed paving the second lift of pavement to Jonesville along with continued driveway tie-ins. Completed installation of shoulder material throughout.
The following is the anticipated work schedule for the week beginning Monday, November 28, 2022:
Monday - Daytime:
- Continue paving driveway and side road tie-ins.
Tuesday through Friday:
- Clean-up work throughout the project in preparation for winter shut-down.
Completed paving the second lift of pavement to Jonesville along with driveway tie-ins. Continued installation of shoulder material throughout.
The following is the anticipated work schedule for the week beginning Monday, November 21, 2022:
Monday, Tuesday - Daytime and Wednesday until noon:
- Continue installing shoulder material between Snipe Ireland Road and the eastern end of the project in Bolton.
- Clean-up work throughout the project in preparation for winter shut-down.
Thursday and Friday: No work due to the Thanksgiving Day holiday.
Paving the second lift of pavement began on the eastern end of the project in Bolton and proceeded westerly. Drainage upgrade work continued between Snipe Ireland Road and Cochran road.
The following is the anticipated work schedule for the week beginning Monday, November 14, 2022:
Monday through Friday - Daytime:
- Weather permitting, continue paving the second lift of asphalt westerly from approximately Boys Club Road to Snipe Ireland Road.
- Continue installing shoulder material and driveway/side road tie-ins.
General project cleanup work began. Drainage upgrade work continued between Bridge Street and Lemroy Court continued.
The following is the anticipated work schedule for the week beginning Monday, November 7, 2022:
Monday through Friday - Daytime:
- Weather permitting, paving the second lift of asphalt from the eastern end of the project in Bolton to Snipe Ireland Road.
- Continue drainage upgrade between Snipe Ireland Road and Cochran Road.
Driveway tie-ins have been completed from the eastern end of the project to Notch Road. Drainage upgrade work continued between Bridge Street and Lemroy Court.
The following is the anticipated work schedule for the week beginning Monday, October 31, 2022:
Monday through Friday - Daytime:
- Project clean-up work on the eastern end of the project between Snipe Ireland Road and Long Trail parking lot.
- Continue drainage upgrade within Richmond Village.
PROJECT UPDATE: Base paving is now complete on all the unpaved, reconstructed roadway. Drainage upgrade work continued including the west end of Richmond Village.
The following is the anticipated work schedule for the week beginning Monday, October 24, 2022:
Monday through Friday - Daytime:
- Weather permitting, driveway and side road tie-ins along with the installation of shoulder material all between Snipe Ireland Road to the eastern end of the project in Bolton.
- Continue drainage upgrade between Bridge Street and Lemroy Court.
PROJECT UPDATE: Fine grading operations continued along with drainage work in Richmond Village. Paving between Cochran Road and Snipe Ireland Road began today and will continue into tomorrow.
The following is the anticipated work schedule for the week beginning Monday, October 17, 2022:
Monday through Friday - Daytime:
- Weather permitting, paving on U.S. Route 2 from Snipe Ireland Road proceeding westerly.
- Continue drainage upgrade between Bridge Street and Lemroy Court.
Monday through Thursday - Nighttime 7:00 p.m. to 6:00 a.m.:
- Drainage upgrade on the west end of Richmond Village.
PROJECT UPDATE: The roadway excavation and slab removal has been completed to approximately Snipe Ireland Road, which was the goal for the 2022 construction season.
The following is the anticipated work schedule for the week beginning Monday, October 10, 2022:
Monday through Friday - Daytime:
- Fine grading and roadway maintenance will continue between Cochran Road and Snipe Ireland Road.
Monday through Thursday - Nighttime 7:00 p.m. to 6:00 a.m.:
- Drainage upgrade between Bridge Street and Lemroy Court.
- Project clean-up work throughout
PROJECT UPDATE: Base pavement has been placed from the eastern most end of the project in Bolton to Cochran Road. Today, paving will continue westbound from approximately Cochran Road.
The following is the anticipated work schedule for the week beginning Monday, October 3, 2022:
Monday and Tuesday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
Monday through Friday - Daytime:
- Continue drainage work within Richmond Village.
- Fine grading and roadway maintenance will continue between Cochran Road and Snipe Ireland Road.
The following is the anticipated work schedule for the week beginning Monday, September 26, 2022:
Monday through Friday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Drainage work within Richmond Village.
- Roadway maintenance will continue throughout the week.
Tuesday:
- Weather permitting, continue paving westbound between Notch Road, Bolton to Cochran Road, Richmond.
The following is the anticipated work schedule for the week beginning Monday, September 19, 2022:
Monday through Friday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Weather permitting, continue paving westbound between Notch Road, Bolton to Cochran Road, Richmond.
- Drainage work throughout the project limits.
- Roadway maintenance will continue throughout the week.
The following is the anticipated work schedule for the week beginning Monday, September 12, 2022:
Monday - Daytime:
- Roadway preparation for paving between the Long Trail Parking Lot and Boys Club Road.
Tuesday and Wednesday - Daytime:
- Paving base course between the Long Trail Parking Lot and Boys Club Road.
Monday through Friday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Ditching and turf establishment between Cochran Road to the eastern end of the project in Bolton.
The following is the anticipated work schedule for the week beginning Monday, September 5, 2022:
Monday:
- No work due to the Labor Day holiday
Tuesday through Friday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Drainage work within Richmond Village (with minimal traffic delays as two-way traffic will be maintained within this work area)
The following is the anticipated work schedule for the week beginning Monday, August 29, 2022:
Monday through Friday - Daytime:
- Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Weather permitting and contractor availability, fine grading and paving base course in Bolton from the Long Trail Parking Lot to Boys Club Road.
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
- Continue with slope repair between Exit 11 interchange and the westerly end Richmond Village
Due to unforeseen utility issues, the work scheduled for this weekend has been postponed.
BEGINNING TOMORROW, FRIDAY at 7:00 p.m. to SUNDAY 7:00 a.m.:
- Continue roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
- Weather permitting, paving base course in Bolton from the Long Trail Parking Lot to Boys Club Road.
- Drainage and slope repair between Exit 11 interchange and the westerly end Richmond Village
The following is the anticipated work schedule for the week beginning Monday, August 15, 2022:
- Milling from Jonesville proceeding easterly for approximately 1-1/2 miles
- Continue roadway excavation and slab removal from the Richmond-Bolton town line proceeding easterly
- Fine grading from Notch Road, Bolton to Jonesville
- Stone fill and drainage work throughout the project limits
- Potential paving the first course of pavement on the east end of the project, in Bolton
- Replacement of culvert pipe under US Route 2 just east of the intersection of US Route 2 and Jericho Road/Bridge Street. Traffic control will be present allowing for one lane of alternating travel.
Monday through Friday - Daytime:
- Continue roadway excavation and slab removal between Boys Club Road and Cochran Road
- Slope repairs in multiple locations between Lemroy Court, Richmond and Cochran Road, Jonesville.
- Continue roadway excavation and slab removal between Boys Club Road and Long Trail Parking Lot.
- Slope repairs in multiple locations between Lemroy Court, Richmond and Cochran Road, Jonesville.
The following is the anticipated work schedule for the week beginning Monday, July 25, 2022:
- Continue ledge removal working westerly
- Continue installation of underdrain working westerly
- Continue roadway excavation on the east end of the project in Bolton working westerly
- Continue guardrail work working westerly
The following is the anticipated work schedule for the week beginning Monday, July 18, 2022:
- Continue ledge removal working west
- Continue installation of underdrain on the east end of the project in Bolton working westerly
- Begin slab removal and roadway excavation on the east end of the project in Bolton working westerly.
- Continue ledge removal working west
- Continue installation of underdrain on the east end of the project in Bolton working west
- Continue grinding up the existing pavement on the east end of the project in Bolton working westerly.
The following is the anticipated work schedule for the week beginning Monday, July 4, 2022:
- No work due to the Independence Day holiday
- Continue ledge removal on the east end of the project in Bolton working west
- Begin installation of underdrain on the east end of the project in Bolton working west
- Begin grinding up the existing pavement on the east end of the project in Bolton working westerly.
The following is the anticipated work schedule for the week beginning Monday, June 27, 2022:
- Continue sign installation
- Continue equipment mobilization
- Begin ledge removal on the east end of the project in Bolton working west
- Begin installation of underdrain on the east end of the project in Bolton working west
The following is the anticipated work schedule for the week beginning Monday, June 20, 2022:
- Installation of construction signage in preparation of work to begin on June 27, 2022.
- Equipment mobilization.