This project will consist of a milling the existing roadway, new traveling surface, guardrail work, ditching and the installation of new shoulder material. 

Looking west on VT Route 289

Looking west on VT Route 289

Anyone with questions or concerns regarding the project may contact Stephanie Barrett, Public Information Consultant at 802-399-7847 or via email at sbarrett@coibsinc.com.

Essex-Colchester - Resurfacing VT Routes 2A & 289

The Vermont Agency of Transportation in conjunction with Frank W. Whitcomb Construction Corporation (FWW) is resurfacing of VT Route 2A from the intersection of VT Route 2A/Lincoln Street and North Street, Essex to the intersection of US Route 7 in Colchester, including SNR 127 between the intersection of VT Route 2A and US Route 7. This project also includes the resurfacing of VT 289 from the intersection of VT 117 to the intersection of VT Route 2A, including VT Route 2A between the on/off ramps of VT 289. The completion date for this work is November 2022.

The posted speed limit will be strictly enforced as the safety of the workers along with the motorists is of the utmost importance. We ask motorists to use extreme caution while traveling through the zone.


THIS PROJECT IS COMPLETE!

On behalf of the Vermont Agency of Transportation and myself, we would like to thank everyone for your patience and understanding during this construction project.

We hope you enjoy the improvements, not only for your safety, but also for the smooth ride.

Stay safe and buckle up!

VT-289

East end of newly paved and striped VT-289 facing west.


TRAFFIC IMPACTS:

  • None anticipated

CONSTRUCTION UPDATES:

This week: The installation of pavment markings and rumble strips on VT-289 is complete. This project will be substantially complete by Friday, June 23, 2023.

The following is the anticipated work schedule for the week beginning Monday, June 26, 2023:

Monday through Friday - 7:00 a.m. to 6:00 p.m.:

  • General clean up of the project
  • Demobilization of equipment

VT-289 Rumble Strip

Installation of rumble strip on VT-289 shoulder

 


This week: Permanent pavement markings on the north end of VT Route 2A in Colchester Village to include lettering and crosswalks was completed as well as final paving on the east end of Vt-289 and continued pavement markings near the exit ramps on VT-289.

The following is the anticipated work schedule for the week beginning Monday, June 19, 2023:

Monday through Friday - 7:00 a.m. to 6:00 p.m.:

  • Weather permitting, continue paving the final "wearing course" on the east end of VT-289.
  • Once paving is complete, installation of rumble strips for the centerline and the shoulders will be completed.
  • Continue pavement markings on VT Route 2A in Colchester to include lettering, crosswalks and stop bars.

VT-289 Wearing Course

Final paving being placed on VT-289


This week: Shoulder clean up (berm removal) and permanent pavement markings on the ramps including crosswalks and lettering was completed this week on the east end of VT-289. Paving was delayed due to the weather.

The following is the anticipated work schedule for the week beginning Monday, June 12, 2023:

Monday through Friday - 7:00 a.m. to 6:00 p.m.:

  • Weather permitting, paving the leveling course on the east end of VT-289.
  • Continue pavement markings on the VT-289 ramps.

This week: The eastern end of VT-289 was milled and prepped for paving.

The following is the anticipated work schedule for the week beginning Monday, June 5, 2023:

Monday through Friday - 7:00 a.m. to 6:00 p.m.:

  • Weather permitting, paving and line striping on the east end of VT-289

VT-289

Milling operations this week on the east end of VT-289


The completion of this project begins.

The following is the anticipated work schedule for the week beginning Tueday, May 30, 2023:

Tuesday through Friday - 7:00 a.m. to 6:00 p.m.:

  • Milling to begin on the east end of VT-289

VT-289 Milling

Milling operations August 2022


The installation of pavement markings on VT-289 is now complete as is the paving driveway and side road aprons on VT Route 2A.

The following is the anticipated work schedule for the week beginning Monday, November 28, 2022:

Monday through Friday - 8:00 a.m. to 4:00 p.m.:

  • On VT Route 2A: Weather permitting, completion of pavement markings and general project clean up work in anticipation of winter shut down. Motorists will encounter a lane closure where the markings are being placed with minimal traffic interruptions.
  • On VT-289: General project clean up work in anticipation of winter shut down.

VT 2A Colchester

Completion of driveway tie-ins on VT Route 2A


Rumble strips were installed on the VT-289 shoulders along with the completion of mainline pavement markings. Paving driveway and side road aprons on VT Route 2A continued along with the continued of pavement markings.

 

The following is the anticipated work schedule for the week beginning Monday, November 21, 2022:

Monday and Tuesday - 8:00 a.m. to 4:00 p.m., Wednesday 8:00 am to noon:

  • On VT Route 2A: Weather permitting, continue installation of pavement markings and placement of aggregate shoulder material.
  • On VT-289: Weather permitting, continue installation of crosswalks and stop bars on ramps.

Thursday and Friday - No work due to the Thanksgiving Day holiday.

 

VT-289_RT15

Pavement markings being placed at the VT-289 & VT Route 15 intersection


The centerline rumble strip was installed on VT-289 along with pavement markings. Began paving driveway and side road aprons on VT Route 2A along with installation of pavement markings.

 

The following is the anticipated work schedule for the week beginning Monday, November 14, 2022:

Monday through Friday - 8:30 a.m. to 3:30 p.m. on VT-289:

  • Weather permitting, continue installation of pavement markings.
  • Installation of shoulder rumble strips.
  • Placement of aggregate shoulder material along the sides of the road.

Monday through Friday - 8:30 a.m. to 3:00 p.m. on VT Route 2A:

  • Weather permitting, continue paving of driveway and side road aprons.
  •  Weather permitting, continue installation of pavement markings
  • Continue placement of aggregate shoulder material along the sides of the road.

VT2A Colchester

Driveway & side road tie-ins on VT Route 2A,Colchester


Paving on VT-289 is complete for this construction season.

The following is the anticipated work schedule for the week beginning Monday, November 7, 2022:

Monday through Friday - 8:30 a.m. to 3:30 p.m. on VT-289:

  • Weather permitting, installation of line striping throughout the newly paved roadway. Two-way traffic will be maintained, but motorists should expect lane shifts.
  • Bridge joint work on the two bridges on the ramps at the west end of VT-289.

Monday through Friday - 8:30 a.m. to 3:00 p.m. on VT Route 2A:

  • Weather permitting, paving of driveway and side road aprons. Motorists will encounter delays as traffic control will be present allowing for one lane of alternating traffic.

VT289

VT 289 paving complete


Paving on VT-289 continues; Prepping and paving driveway and side road tie-ins began on VT Route 2A.

The following is the anticipated work schedule for the week beginning Monday, October 31, 2022:

Monday through Friday - 8:30 a.m. to 3:30 p.m.:

  • Weather permitting, continue paving the final lift of asphalt (wearing course) on VT-289.

Note: There is no nighttime work scheduled at this time.

RT2A Colchester

VT Route 2A Colchester paved and line striped


PROJECT UPDATE: Final paving on VT-289 has begun. 

 

The following is the anticipated work schedule for the week beginning Monday, October 24, 2022:

Monday through Friday - 8:30 a.m. to 3:30 p.m.:

  • Weather permitting, continue paving the final lift of asphalt (wearing course) on VT-289. Two-way traffic will be maintained, but motorists should expect lane shifts.

Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:

  • Weather permitting, paving driveway and side road tie-ins throughout the project on VT Route 2A.  Motorists can expect  lane closure with traffic control allowing for one lane of alternating travel.

 

VT-289

Final mainline paving began VT-289 during daytime hours


PROJECT UPDATE: Paving on VT Route 2A and all the Exit ramps on VT-289 is complete. The final tie-ins of abutting side roads and driveways on VT Route 2A will be completed in the upcoming weeks, along with line striping. These final operations are weather dependent, but will be completed before winter.

The following is a revised anticipated work schedule for the week beginning Monday, October 17, 2022:

Monday through Friday - 8:30 a.m. to 3:30 p.m.:

  • Weather permitting, continue paving the final lift of asphalt (wearing course) on VT-289.  Motorists can expect lane shifts.

 

The following is a anticipated work schedule for the week beginning Sunday, October 16 2022:

Sunday through Friday - 7:00 p.m. to 6:00 a.m.:

  • Weather permitting, continue paving the final lift of asphalt (wearing course) on VT-289.

VT-289 Exit7 Ramp

Final paving on VT-289 Exit 7 off-ramp


PROJECT UPDATE: Began final paving (wearing course) on VT Route 2A at the southern end and proceeded north.

 

The following is a anticipated work schedule for the week beginning Sunday, October 9, 2022:

Sunday through Friday - 7:00 p.m. to 6:00 a.m.:

  • Weather permitting, continue paving the final lift of asphalt (wearing course) on VT Route 2A.
  • Upon completion of the paving, installation of permanent line striping.
  • Side road and driveway tie-ins throughout the project limits on VT Route 2A.
  • After completion of paving on VT Route 2A, weather permitting, final paving on VT-289 to begin at the west end of the project to proceed easterly to the end at the VT Route 117 intersection.

VT2A Essex

Southern most end of VT Route 2A paving wearing course


PROJECT UPDATE: Prepped driveways for driveway tie-ins following the final paving on VT Route 2A.  Placement of shoulder aggregate on VT-289 ramps.

The following is a anticipated work schedule for the week beginning Sunday, October 2, 2022:

Sunday through Friday - 7:00 p.m. to 6:00 a.m.:

  • Weather permitting, paving the final lift of asphalt (wearing course) on VT Route 2A.

VT289 Essex

Placing shoulder aggregate on VT-289


PROJECT UPDATE: Activities were limited this week due to the heavy rainfall.  Berm removal continued on VT-289 along with paving of the wearing course on VT-289 at the Essex Way and Route 2A ramps.

The following is a anticipated work schedule for the week beginning Sunday, September 26, 2022:

Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:

  • Begin to raise and rehabilitate structures on VT-289 in anticipation of final paving.
  • Weather permitting, paving the final lift of asphalt (wearing course) on VT Route 2A.

VT-289 ramp

Westbound off-ramp paving at Essex Way on VT-289


PROJECT UPDATE: Shoulder cleanup/Berm removal on VT-289 work this week.

The wearing course is not yet complete throughout this entire project. Following this final paving, shoulder material will be placed and all driveway and sideroad tie-ins will be paved.

 

The following is a anticipated work schedule for the week beginning Sunday, September 18, 2022:

Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:

  • Continue berm removal, shoulder cleanup on VT-289.
  • Begin structure adjustments on VT Route 2A and VT-289.
  • Ditch work on SNR 127 between the intersection of VT Route 2A and US Route 7.

Motorists can expect minimal delays with traffic control and/or lane shifts within the work areas.

VT-289 Essex

Berm removal on VT-289


PROJECT UPDATE: Paving the leveling course continued on the milled area of VT-289.  

CONSTRUCTION ACTIVITIES:

The following is a anticipated work schedule for the week beginning Sunday, September 11, 2022:

Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:

  • Complete milling on VT-289 from the "jug handle" to the end at VT 117.
  • Begin berm removal, shoulder cleanup on VT-289.

VT-289 Essex

Continued VT-289 paving of the leveling course


PROJECT UPDATE: Paving the leveling course began on VT-289. 

There will not be any work on this project for the week beginning Sunday, September 4, 2022.

VT-289

VT-289 paving of the leveling course began


The following is the anticipated work schedule for the week beginning Sunday, August 28, 2022:

  • Weather permitting, paving leveling course on VT-289.  Work will start on the west end at the on/off ramps at the junction of VT Route 2A and proceed easterly.

Two-way traffic with traffic shifts will be maintained on VT-289;  Lane reductions on the on/off ramps


PROJECT UPDATE: Guardrail work is now complete. Milling continued on VT-289.
The following is the anticipated work schedule for the week beginning Sunday, August 21, 2022:
  • No work anticipated for this week.

VT-289 Milling

Milling on VT-289


PROJECT UPDATE: Milling operations and temporary line striping continued on VT-289; Guardrail replacement and adjustments continued throughout VT-289.
The following is the anticipated work schedule for the week beginning Sunday, August 14, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Shoulder work to include berm removal throughout VT-289

Milling VT-289 eastbound Exit 9 ramp to VT Route 15


PROJECT UPDATE: Guardrail replacement is complete and drainage structures have been raised to accommodate final paving on VT Route 2A; Milling work began VT-289 on the western end and is proceeding easterly.
The following is the anticipated work schedule for the week beginning Sunday, August 7, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Milling continues on VT-289. Vehicles should expect to travel on grooved (scarified) payment - USE CAUTION!
  • Guardrail replacement continues throughout the project limits on VT-289.

Milling VT-289 westbound ramp to VT Route 2A


PROJECT UPDATE: Guardrail work continues on VT Route 2A; Milling work on VT-289 was delayed.
The following is the anticipated work schedule for the week beginning Sunday, July 31, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Milling to begin on VT-289. Vehicles should expect to travel on grooved (scarified) payment - USE CAUTION!
  • Continue guardrail replacement throughout the project limits on VT Route 2A.
 

PROJECT UPDATE: Paving of the leveling course on VT Route 2A is now complete through Colchester; Guardrail work began to include installation of new end sections, replacement of damaged posts and beams all on Route 2A.
The following is the anticipated work schedule for the week beginning Sunday, July 25, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Milling to begin on VT-289. Vehicles should expect to travel on grooved (scarified) payment - USE CAUTION!
  • Continue guardrail replacement throughout the project limits on VT Route 2A.

VT2A Colchester

Leveling course of pavement on VT Route 2A colchester is complete

VT2A Essex-Colchester

Guardrail work began on VT Route 2A


PROJECT UPDATE: Berm removal is complete; Slope repairs behind the guardrail on VT Routes 2A & 289 is complete; Paving of the leveling course on VT Route 2A is complete through Essex and working through Colchester.
The following is the anticipated work schedule for the week beginning Sunday, July 17, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Weather permitting, continue paving the leveling course on VT Route 2A on the northern end of the project in Colchester.
  • Begin guardrail replacement throughout the project limits on VT Route 2A.

RT2A Essex-Colchester

Paving leveling course on VT Route 2A Essex-Colchester


The following is the anticipated work schedule for the week beginning Sunday, July 10, 2022:
Sunday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Weather permitting, begin paving the leveling course on VT Route 2A on the southern end of the project in Essex.
  • Continue milling on the northern section of VT Route 2A in Colchester to the intersection of US Route 2/7 and SNR 127.

Shoulder work on VT Route 2A Essex-Colchester


The following is the anticipated work schedule for the week beginning Monday, July 4, 2022:
Monday:
  • No work due to the Independence Day holiday.
Tuesday through Thursday 7:00 p.m. to 6:00 a.m.:
  • Continued berm removal on the roadway shoulders throughout the project area on VT Route 2A.
  • Begin repairing slopes behind the guardrails throughout the project area on VT Route 2A.

There will not be any work on this project the week beginning June 26, 2022. Work will resume on July 5, 2022, following the Independence Day Holiday.

Berm removal from the shoulders of VT Route 2A Essex-Colchester


The following is the anticipated work schedule for the week beginning Sunday, June 19, 2022:
Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Milling continues to progress northerly to the end of the project limits on VT Route 2A at the intersection of VT Route 2A, US Route 7 and SNR 127.
  • Begin guardrail replacement throughout the project limits on VT Route 2A.
  • Begin shoulder repair throughout the project limits on VT Route 2A.
RT 2A EssexRT 2A Essex
Milling operations at the southern end of the project in Essex working north to Colchester

The following is the anticipated work schedule for the week beginning Sunday, June 12, 2022:
Sunday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Milling begins on VT Route 2A at the southern end of the project approximately the intersection of VT-2A/Lincoln Street and North Street.