This project is complete!
We realize it was pressing at times, so thank you all for your patience and understanding during the construction.
We hope you enjoy the improvements, not only for your safety, but also for the smooth ride.
WISHING YOU ALL A HAPPY, SAFE HOLIDAY SEASON AND WINTER!
The following is the anticipated work schedule for the week beginning Monday, December 9, 2019:
Monday through Friday - Daytime:
- Weather permitting, continue miscellaneous construction activities throughout the project limits in preparation of winter shutdown.
MOTORISTS SHOULD PLAN FOR MINOR DELAYS
The following is the anticipated work schedule for the week beginning Monday, December 2, 2019:
Monday through Friday - Daytime:
- Weather permitting, continue miscellaneous construction activities throughout the project limits in preparation of winter shutdown.
MOTORISTS SHOULD PLAN FOR MINOR DELAYS
The following is the anticipated work schedule for the week beginning Monday, November 21, 2019:
Monday and Tuesday:
- Continue project cleanup work throughout the project limits in preparation of winter shutdown.
Wednesday through Friday:
- No work due to the Thanksgiving Day holiday
MOTORISTS SHOULD PLAN FOR DELAYS IN ESSEX AND JERICHO
The following is the anticipated work schedule for the week beginning Monday, November 18, 2019:
Monday through Friday - 6:30 a.m. to 7:00 p.m.
- Complete paving driveway tie-ins in Jericho
- Miscellaneous cleanup work throughout the project limits in preparation of winter shutdown.
MOTORISTS SHOULD PLAN FOR DELAYS IN ESSEX AND JERICHO
The following is the anticipated work schedule for the week beginning Monday, November 11, 2019:
Monday - No work due to the Veterans Day Holiday
Tuesday through Friday - 6:30 a.m. to 7:00 p.m.
- General cleanup work throughout the project limits
MOTORISTS SHOULD PLAN FOR MINIMAL DELAYS
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Monday, November 4, 2019:
Monday through Friday - 6:30 a.m. to 7:00 p.m.
- General cleanup work throughout the project limits
MOTORISTS SHOULD PLAN FOR MINIMAL DELAYS
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Saturday, October 26, 2019:
Saturday, Monday through Friday - 6:30 a.m. to 7:00 p.m.:
- Weather permitting, continue paving driveway tie-ins in Essex
- Weather permitting, continue pavement markings throughout the project limits
- General cleanup throughout the project limits
Sunday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue pavement markings throughout the project limits
- General cleanup throughout the project limits
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Saturday, October 19, 2019:
Saturday, Monday through Friday - 6:30 a.m. to 7:00 p.m.:
- Weather permitting, continue paving driveway tie-ins in Essex
- Weather permitting, continue pavement markings throughout the project limits
Sunday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue pavement markings throughout the project limits
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Monday, October 14, 2019:
Monday - No work due to the Columbus Day holiday
Tuesday through Saturday - 6:30 a.m. to 7:00 p.m. and
Tuesday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue paving driveway tie-ins in Essex
- Continue pavement markings throughout the project limits
- General cleanup work throughout the project limits
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
October 3, 2019
On behalf on the project team, we would like to apologize to the traveling public for the inconvenience caused by traffic delays within the Jericho Village area, early this afternoon. The team is currently working on corrective actions to minimize those delays moving forward, while the contractor continues to complete this project timely.
The following is the anticipated work schedule for the week beginning Saturday, October 5, 2019:
Saturday, Monday through Friday - 6:30 a.m. to 7:00 p.m. and
Sunday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue paving driveway tie-ins from the Jericho/Essex line proceeding west through Essex Town
- Installation of pavement markings throughout the project limits
- General cleanup work throughout the project limits
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Sunday night, September 29, 2019:
Nighttime work:
Sunday thru Friday - 7:00 p.m. to 6:00 a.m.:
Daytime work:
Monday through Friday - 6:30 a.m. to 7:00 p.m.:
- Weather permitting, continue paving driveway in Jericho proceeding west to Essex
- Continue shoulder work throughout the project limits
- Installation of pavement markings throughout the project limits
- General cleanup work throughout the project limits
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Friday night, September 20, 2019:
Daytime work:
Saturday, Monday through Friday - 6:30 a.m. to 7:00 p.m.:
- Weather permitting, continue paving driveway in Jericho proceeding west to Essex
- Shoulder work throughout the project limits
Nighttime work:
Friday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue paving side road and driveway tie-ins
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Friday night, September 13, 2019:
Daytime work:
Monday through Friday - 6:30 a.m. to 7:00 p.m.:
- Begin paving driveway tie-ins throughout the project limits
- Weather permitting, begin pavement markings
Monday & Tuesday - 6:30 a.m. to 7:00 p.m.:
- Weather permitting, bridge joint work throughout the project limits
Nighttime work:
Friday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, complete final paving of mainline in Essex
- Weather permitting, begin paving side road and driveway tie-ins
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!

The following is the anticipated work schedule for the week beginning Friday, September 6, 2019:
Daytime work:
Monday through Saturday - 6:30 a.m. to 7:00 p.m.:
- Begin paving driveway tie-ins in Jericho proceeding west to Essex
- Continue shoulder work from Jericho to Essex
- Weather permitting, bridge joint work from Jericho to Essex
- Weather permitting, begin pavement markings
Nighttime work:
Friday thru Friday - 7:00 p.m. to 6:00 a.m.:
- Weather permitting, continue final paving in Essex
- Complete guardrail work
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the anticipated work schedule for the week beginning Tuesday, September 3, 2019:
Daytime work:
Monday through Friday - 6:30 a.m. to 7 p.m.:
- Sidewalk tip-down work to make ADA compliant between Essex Way and Sand Hill Road
Nighttime work:
Tuesday thru Friday - 7 p.m. to 6 a.m.:
- Weather permitting, continue final paving from Brown's Trace Road proceeding west to the Essex Jct/Village line.
- Continue ditch and shoulder cleanup between the Essex Jct/Essex Village line to Essex Way.
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
The following is the revised anticipated work schedule for the week beginning Monday, August 26, 2019:
Daytime work listed below will be between N. Underhill Station Road and Browns Trace Road.
Monday and Tuesday (Wednesday if necessary) - 5:30 a.m. to 6 p.m.:
- Weather permitting, continue paving driveway aprons within the Underhill Flats area
- Continue installation of shoulder material
Nighttime work listed below:
Wednesday and Thursday - 7 p.m. to 6 a.m.:
- Final paving to begin from Brown's Trace Road proceeding the Essex Jct/Village line.
- Continue structure elevation between Saxon Hill Road and the Essex Jct/Essex Village line.
- Weather permitting, structure rehabilitation work in Jericho between Brown's Trace Road and Weed Road.
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
WORK ACTIVITIES FOR THE WEEK BEGINNING SUNDAY, AUGUST 18, 2019:
Nighttime work listed below will be between Saxon Hill Road and the Essex Junction/Essex Village line.
Sunday through Thursday - 7 p.m. to 6 a.m.:
- Elevation of the structures throughout
- Continue shoulder and ditch excavation work
Daytime work listed below will be between N. Underhill Station Road and Brown Trace Road.
Monday through Friday - 5:30 a.m. to 6 p.m.:
- Weather permitting, continue paving driveway aprons
- Installation of shoulder material continues
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
WORK ACTIVITIES FOR THE WEEK BEGINNING SUNDAY, AUGUST 11, 2019:
Nighttime work listed below will be between Saxon Hill Road and the Essex Junction/Essex Village line.
Sunday through Thursday - 7 p.m. to 6 a.m.:
- Weather permitting, begin paving the leveling course
- Shoulder work continues
Daytime work listed below will be from N. Underhill Station Road to Brown Trace Road.
Monday through Friday - 5:30 a.m. to 6 p.m.:
- Weather permitting, continue paving driveway aprons
- Bridge joint work
Monday through Thursday - 5:30 a.m. to 6 p.m.:
- Installation of shoulder material
Thursday - 5:30 a.m. to 6 p.m.:
- Installation of the center line rumble strip
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.
WORK ACTIVITIES FOR THE WEEK BEGINNING SUNDAY, AUGUST 04, 2019:
Nighttime work this week will be between Whitcomb Meadows Lane and the Essex Junction/Essex Village line.
Sunday through Tuesday - 7 p.m. to 6 a.m.:
- Milling (grinding of the existing pavement) to be completed
Sunday through Thursday - 7 p.m. to 6 a.m.:
- Shoulder and ditch work continues
Daytime work this week will be from N. Underhill Station Road and proceed west
Monday through Friday - 5:30 a.m. to 6 p.m.:
- Weather permitting, final paving continues on Route 15 from Underhill proceeding west
- Paving of side roads and driveway aprons
- Begin sign installation throughout the project
Thursday and Friday - 5:30 a.m. to 6 p.m.:
- Installation of shoulder material
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Traffic control to be present allowing for one lane of alternating traffic within each work zone area, causing delays.




WORK ACTIVITIES FOR THE WEEK BEGINNING SUNDAY, JULY 28, 2019:
Sunday through Friday - 7 p.m. to 6 a.m.:
- Milling (grinding of the existing pavement) to begin at Whitcomb Meadows Lane and proceed west on VT Route 15 to Essex Junction/Essex Village line.
Monday through Friday - 5:30 a.m. to 6 p.m.:
From Jericho/Underhill line proceeding west to the Essex Town/Essex Jct line:
- Continue ditching and shoulder cleanup
- Continue guardrail work
- Begin sign installation
Tuesday through Friday - 5:30 a.m. to 6 p.m.:
From N. Underhill Station Road proceeding west to Whitcomb Meadows Lane
- Weather permitting, begin final paving (top course)
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS, MOST MORNINGS AND LATE AFTERNOONS!
Motorists should expect traffic control to be present allowing for one lane of alternating traffic causing delays.


DAYTIME WORK ACTIVITIES FOR THE WEEK BEGINNING MONDAY, JULY 22, 2019:
Monday through Friday from N. Underhill Station Road to the Essex/Jericho line:
- Elevating the drainage structures
- Ditching and shoulder cleanup
- Guardrail work
Wednesday through Saturday:
- Weather permitting, begin final paving (top course) from N. Underhill Station Road proceeding west to the Essex/Jericho line.
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS MOST MORNINGS AND LATE AFTERNOONS!
Motorists should expect traffic control to be present allowing for one lane of alternating traffic causing delays.
|
|
DAYTIME WORK ACTIVITIES FOR THE WEEK BEGINNING MONDAY, JULY 15, 2019 ARE AS FOLLOWS:
Monday:
- Milling (grinding of the existing pavement) to continue from approximately Jericho Village proceeding west to Essex.
Monday through Friday:
- Weather permitting, continue paving working westerly
- Continue ditch work in Underhill proceeding west to Jericho.
TRAFFIC CONCERNS: ONE LANE OF ALTERNATING TRAFFIC. MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS IN TWO DIFFERENT WORK ZONES.
DAYTIME WORK ACTIVITIES FOR THE WEEK BEGINNING MONDAY, JULY 8, 2019 ARE AS FOLLOWS:
Monday through Friday:
- Milling (grinding of the existing pavement) to continue from approximately Underhill Flats proceeding west to Jericho
- Continue ditch work in various locations throughout the project limits
Friday and Saturday:
- Weather permitting, paving to begin at N. Underhill Station Road proceeding west.
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS MOST MORNINGS AND LATE AFTERNOONS!



DAYTIME WORK ACTIVITIES FOR THE WEEK BEGINNING MONDAY, JULY 01, 2019 ARE AS FOLLOWS:
Monday through Wednesday until noon:
- Continue ditch work in Jericho Village
Tuesday, all day and Wednesday until noon:
- Milling (grinding of the existing pavement) to begin from N. Underhill Station Road to Underhill Flats
Thursday & Friday:
- No work due to the Independence Day Holiday. Happy - Safe 4th!
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS MOST MORNINGS AND LATE AFTERNOONS!
DAYTIME WORK ACTIVITIES FOR THE WEEK BEGINNING MONDAY, JUNE 24, 2019 ARE AS FOLLOWS:
Monday - Friday:
- Continue ditch work from N. Underhill Station Road to Underhill Flats
Monday – Wednesday:
- Continue guardrail installation between the Jericho Village and Leo Drive, Essex.
Thursday/Friday:
- Milling the existing roadway to begin at N. Underhill Station Road and proceed west.
MOTORISTS SHOULD PLAN FOR EXTENDED DELAYS DURING PEAK HOURS MOST MORNINGS AND LATE AFTERNOONS!
The anticipated work schedule for the week beginning Monday June 17, 2019 is as follows:
Monday thru Friday - Daytime activities:
- Continue guardrail installation in Underhill thru Jericho
- Continue ditch & shoulder work from N. Underhill Station Road thru Jericho
- Begin driveway tie-ins from N. Underhill Station Road thru Jericho
Motorists should expect traffic control to be present with one lane of alternating causing delays.
The anticipated work schedule for the week beginning Monday June 10, 2019 is as follows:
Monday thru Friday - Daytime activities:
- Continue guardrail installation from Underhill thru Jericho
- Ditch work from N. Underhill Station Road and proceeding to Jericho
Motorists should expect delays as traffic control will present allowing for one lane of alternating within the construction zones.
The anticipated work schedule for the week beginning Monday June 03, 2019 is as follows:
Monday thru Friday - Daytime activities:
- Continue sign installation throughout the project limits
- Ditch work to begin at N. Underhill Station Road and proceeding to west
Motorists should expect traffic control to be present with one lane of alternating causing delays.
The anticipated work schedule for the week beginning Tuesday, May 28, 2019 is as follows:
Tuesday thru Friday - Daytime:
- Installation of construction signs.
Motorists should see little to no impact on travel.