Pittsford Project Facts

Anyone interested in receiving weekly updates on this project can email Stephanie Barrett, Public Outreach Consultant at sbarrett@coibsinc.com referencing Pittsford Bridge in the request.  You may also email Stephanie with any questions or concerns about this project. Read more about this project by visiting the project fact sheet.

PROJECT FACT SHEET

Pittsford - U.S. ROUTE 7 - BRIDGE #108

North view of BR108 Pittsford

On March 4, 2024, The Vermont Agency of Transportation (VTrans) in conjunction with Belden Construction LLC began replacement of Bridge #108 on US Route 7 in Pittsford over the Furnace Brook at the intersection of US Route 7 and VT Route 3.  Also included in the project will be repaving of both the northbound and southbound bridge approaches, the realignment of VT Route 3 and Oxbow Road and other related work associated with the completion of this replacement. The completion date for this work is November 2025.
 

Motorists are now shifted onto the temporary bridge.  Traffic control will be present allowing for intermittent one-way alternating travel on U.S. Route 7 Monday through Friday during working hours. 

PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!


PROJECT UPDATES

TRAFFIC IMPACT: Little to no traffic impact as all work remains behind traffic barriers.

PROJECT UPDATE: No work thus far this week, due to the weather. Today and tomorrow crews will be working on season shut-down. This will be the final update for the 2024 construction season. Have a safe winter!

US7 BR108 Pittsford

Bridge deck prepped for concrete


TRAFFIC IMPACT: Little to no traffic impact as all work remains behind traffic barriers.

PROJECT UPDATE: Continued form work for the bridge deck.

The following is the anticipated work schedule for the week beginning December 2, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m.:, Saturday - 7:00 a.m. to 1:00 p.m.:

  • Bridge deck work continues..

US7 BR108 Pittsford

Rebar formwork on bridge deck awaiting concrete


TRAFFIC IMPACT: Traffic control will be present Monday through Friday during work hours allowing for intermittent one-way alternating travel on U.S. Route 7.

PROJECT UPDATE: Continued form work for the bridge deck.

The following is the anticipated work schedule for the week beginning December 2, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m.:, Saturday - 7:00 a.m. to 1:00 p.m.:

  • Form work for the bridge deck continues..

US7 BR108 Pittsford

Continued form work for the new bridge deck


PROJECT UPDATE: Began installing rebar along the deck and placed forms to prepare for the deck pour.

The following is the anticipated work schedule for the week beginning November 25, 2024:

Monday through Wednesday 7:00 a.m. to 7:00 p.m.:

  • Continue installing rebar and preparing the deck for concrete.

Thursday through Saturday:

  • No work due to the Thanksgiving Day holiday.

US7 Pittsford BR108

Rebar installed for the new bridge deck


PROJECT UPDATE: Steel beams were all installed (below).

The following is the anticipated work schedule for the week beginning November 18, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m., Saturday - 7:00 a.m. to 1:00 p.m.:

  • Begin formwork for the new bridge deck.
  • Backfilling around Abutment #1.
  • Later in the week, weather permitting, pouring of the concrete bridge deck. If this work does take place, please note there will be a 10-day curing processes which includes 24/7 running of heat pumps under the covered poured deck.

US7 Pittsford BR108

Steel beams installed for the new bridge deck


PROJECT UPDATE: Completed work on Abutment #2 prepping for beam installation; Began beam installation for the bridge deck.

The following is the anticipated work schedule for the week beginning November 11, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m., Saturday - 7:00 a.m. to 1:00 p.m.:

  • Begin installation of concrete forms along the bridge in preparation of the bridge deck.

BR108 Pittsford

Steel beam being installed for the new bridge deck


PROJECT UPDATE: Backfilled Abutment #1 footing area; Continued work on Abutment #2 prepping for beam installation.

The following is the anticipated work schedule for the week beginning November 4, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m., Saturday - 7:00 a.m. to 1:00 p.m.:

  • Finsih setting pads on Abutment #2 in anticipation of steel beam installation beginning on Wednesday.

Pittsford BR108 US7

Abutment #2 backfill work


PROJECT UPDATE: Poured the concrete sub-footing for Abutment #1; Prepped the footing for Abutment #1 in anticipation of pouring the concrete tomorrow; Backfilling work on Abutment #2.

The following is the anticipated work schedule for the week beginning October 21, 2024:

Monday through Friday 7:00 a.m. to 7:00 p.m., Saturday - 7:00 a.m. to 1:00 p.m.:

  • Begin forming Abutment #1 wall.
  • Continue backfilling around Abutment #2.

US7 Pittsford Br#108

Backfill work on Abutment #2


PROJECT UPDATE: Began form work for sub-footing on Abutment #1; Removed forms on Abutment #2.

The following is the anticipated work schedule for the week beginning October 14, 2024:

Saturday - 7:00 a.m. to 1:00 p.m., Monday through Friday 7:00 a.m. to 7:00 p.m.:

  • Concrete pour for sub footing on Abutment #1.
  • Backfill on the north side.

Pittsford BR108

Abutment #2


PROJECT UPDATE: Continued demolition of the existing pier, abutment and wing wall on the south side.

The following is the anticipated work schedule for the week beginning October 5, 2024:

Saturday - 7:00 a.m. to 1:00 p.m., Monday through Friday 7:00 a.m. to 7:00 p.m.:

  • Continue excavation to reach bedrock for the new Abutment #1.
  • Removal for Abutment #2 forms.

Pittsford BR108

Abutment #1 bedrock excavation


PROJECT UPDATE: Continued removal of the existing pier and abutment on the south side; Concrete was poured last Friday for Abutment #2..

The following is the anticipated work schedule for the week beginning September 28, 2024:

Saturday - 7:00 a.m. to 1:00 p.m., Monday through Friday 7:00 a.m. to 7:00 p.m.:

  • Complete the demolition of the existing abutment on the south end of the existing bridge.
  • Begin construction for the new Abutment #1.
  • Continue demolition of the old pier.

Pittsford BR108

Abutment #2 wall poured


PROJECT UPDATE: Began removal of existing abutment on the south side; Continue the formwork and rebar installation for Abutment #2 in anticipation of concrete pour tomorrow.

The following is the anticipated work schedule for the week beginning September 21, 2024:

Saturday - 7:00 a.m. to 1:00 p.m., Monday through Friday 7:00 a.m. to 7:00 p.m.:

  • Continue excavation and removal of the existing abutment on the south end of the existing bridge.
  • Continue demolition of the existing pier.

Pittsford BR108

Abutment #2 formwork


PROJECT UPDATE: Continued the demolition of the concrete beams on the southern end of the existing bridge; Poured the concrete footing for Abutment #2 on the north side of the bridge.

The following is the anticipated work schedule for the week beginning September 14, 2024:

Saturday, Monday through Friday 7:00 a.m. to 7:00 p.m.:

  • Continue demolition of the south end of the existing bridge.
  • Continue work on Abutment #2 on the north end of the bridge.

Pittsford BR108

Footing for Abutment #2 awaiting concrete


PROJECT UPDATE: Continued the demolition of the southern end of the existing bridge.

The following is the anticipated work schedule for the week beginning September 9, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue demolition of the south end of the existing bridge.
  • Begin forming the footing for Abutment #2 on the north end of the bridge.

Pittsford US7 BR108

Completion of the sub-footing for Abutment #2


PROJECT UPDATE: Began the demolition of the southern end of the existing bridge.

The following is the anticipated work schedule for the week beginning September 2, 2024:

Monday:

  • No work due to the Labor Day holiday.

Tuesday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue demolition of the south end of the existing bridge.

Pittsford BR108

Removal of the existing concrete deck by cutting panels and lifting off with a crane


PROJECT UPDATE: Completed the drilling for the support of excavation on the south side of the bridge; Placed concrete for Abutment #2 sub-footing on the north side of the bridge.

The following is the anticipated work schedule for the week beginning August 26, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Begin demolition of the south end of the existing bridge.

Pittsford BR108

Installation of forms for the sub-footing on Abutment #2


PROJECT UPDATE: Continued drilling for the support of excavation on the south side of the bridge; Completed demolition of the north end of the existing bridge.

The following is the anticipated work schedule for the week beginning August 19, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Complete installation of the final "piles" of support of excavation.
  • Begin forming the sub-footing for the northern abutment.

BR108 US7 Pittsford

North end of the old bridge has been removed


PROJECT UPDATE: Continued drilling for the support of excavation on the south side of the bridge; Continued demolition on the north end of the existing bridge.

The following is the anticipated work schedule for the week beginning August 12, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue installation of the final four "piles' of support of excavation.
  • Continue demolition of the northern end and abutment of the existing bridge.

BR108 US7 Pittsford

North end of the old bridge being removed


PROJECT UPDATE: Continued drilling for the support of excavation on the south side of the bridge; Began demolition on the north end of the existing bridge; Pedestrian path is now open.

The following is the anticipated work schedule for the week beginning August 5, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue installation of support of excavation.
  • Continue demolition of the northern end of the existing bridge.

Pittsford RT7

Demolition began on the north end of the existing bridge


PROJECT UPDATE: Began drilling for the support of excavation on the south side of the bridge; Paving of the temporary pedestrian path will be completed tomorrow along with switching over the water service to the temporary waterline .

The following is the anticipated work schedule for the week beginning July 29, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue installation of support of excavation.
  • Begin demolition of the northern end of the existing bridge.

Pittsford RT7

Drill used to "drive pile" for the support of excavation


PROJECT UPDATE: Completed the installation of the temporary pedestrian bridge along with the temporary waterline.

The following is the anticipated work schedule for the week beginning July 22, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Begin installation of support of excavation.
  • Complete the installation of the temporary pedestrian path.
  • Begin demolition of the northern end of the existing bridge.

RT7 Pittsford Ped BR

Pedestrian bridge completed on the east side of U.S. Route 7, Pittsford


PROJECT UPDATE:  Continued the installation of the temporary pedestrian bridge along with the temporary waterline.

The following is the anticipated work schedule for the week beginning July 15, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue work on tying in the tempoary pedestrian bridge.
  • Continue the installation of the temporary pedestrian path.
  • Continue work on the installation of temporary waterline along the pedestrian bridge.

Ped bridge RT7 Pittsford

Pedestrian bridge placed on the east side of U.S. Route 7, Pittsford


PROJECT UPDATE: Completed the foundation work on the north side of the temporary pedestrian bridge.

The following is the anticipated work schedule for the week beginning July 8, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue work on the installation of the tempoary pedestrian bridge.
  • Installation of the temporary pedestrian path.
  • Continue work on the installation of temporary waterline along the pedestrian bridge.

Temp ped bridge

Work on the temporary waterline


PROJECT UPDATE: Continued assembling the temporary pedestrian bridge on the east side of the project; Installed temporary waterline connections.

The following is the anticipated work schedule for the week beginning July 1, 2024:

Monday through Wednesday and Friday 7:00 a.m. to 5:00 p.m.:

  • Continue work on the installation of the tempoary pedestrian bridge foundations.

Thursday:

  • No Work due to the Independence Day holiday.

Temp ped bridge

Continued assembly work of the temporary pedestrian bridge


PROJECT UPDATE: Began assembling the temporary pedestrian bridge on the east side of the project.

The following is the anticipated work schedule for the week beginning June 24, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Work on the installation of the tempoary pedestrian bridge foundations.
  • Work to begin on temporary waterline connections.

Pittsford Bridge

Temporary pedestrian bridge sections being assembled


PROJECT UPDATE: Weekend closure of VT Route 3 withing the construction vacinity on U.S. Route 7 allowed for construction of the roadway approaches onto the temporary bridge. On Monday, June 10th at 6:00 a.m. all traffic was shifted onto the new temporary bridge.

The following is the anticipated work schedule for the week beginning June 17, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Begin work for the installation of a tempoary pedestrian bridge on the east side of the project.
  • Prepping the existing bridge deck for removal by coring holes.

Offloading Temp BR108 pcs

Construction for new roadway approaches onto the temporary bridge


PROJECT UPDATE: Work continued on assembling the temporary bridge.

The following is the anticipated work schedule for the week beginning June 10, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Equipment mobilization.
  • Begin preparation for the removal of the existing bridge.

Offloading Temp BR108 pcs

Installation of deck panels on the temporary bridge


PROJECT UPDATE:  Work continued on assembling the temporary bridge.

The following is the anticipated work schedule for the week beginning June 3, 2024:

Monday through Friday 7:00 a.m. to 5:00 p.m.:

  • Complete assembling the temporary bridge.
  • Begin construction of the roadway approaches for the temporary U.S. Route 7 alignment onto the temporary bridge in preparation of shifting traffic over.

ROAD CLOSURE NOTIFICATION: There will be a weekend closure of VT Route 3 within the construction vicinity beginning on Friday, June 7, 2024, at 12:00 p.m. (noon) until Monday, June 10, 2024, at 6:00 a.m. thus causing motorists to follow a signed detour. Motorists wanting to use VT Route 3 traveling south from the project site should continue on U.S. Route 7 to Bus Route 4. Any motorist wanting to use VT Route 3 traveling north towards the project site should use Bus Route 4 to U.S. Route 7.

Offloading Temp BR108 pcs

Continued assemling of temporary bridge


PROJECT UPDATE: Continued installation of tower supports for the temporary bridge; Continued assembling the temporary bridge.

The following is the anticipated work schedule for the week beginning May 27, 2024:

Monday:

  • No work due to the Memorial Day holiday.

Tuesday through Friday 7:00 a.m. to 5:00 p.m.:

  • Continue assembling the temporary bridge.

ROAD CLOSURE NOTIFICATION: There will be a weekend closure of VT Route 3 within the construction vicinity beginning on Friday, June 7, 2024, at 12:00 p.m. (noon) until Monday, June 10, 2024, at 6:00 a.m. thus causing motorists to follow a signed detour. Motorists wanting to use VT Route 3 traveling south from the project site should continue on U.S. Route 7 to Bus Route 4. Any motorist wanting to use VT Route 3 traveling north towards the project site should use Bus Route 4 to U.S. Route 7.

Offloading Temp BR108 pcs

Temporary bridge being assembled


PROJECT UPDATE: Continued installation of tower supports for the temporary bridge; Began installation of the temporary bridge; Continued receiving temporary bridge pieces.

The following is the anticipated work schedule for the week beginning May 20, 2024:

Monday through Thursday 7:00 a.m. to 3:30 p.m., Friday 7 a.m. to noon:

  • Continue installation of the tower supports for the temporary bridge.
  • Continue assembling the temporary bridge.
  • Continue receiving temporary bridge pieces throughout the week causing possible intermittent lane closure to off-load the pieces.

Offloading Temp BR108 pcs

Began assembling temporary bridge


PROJECT UPDATE: Began installation of tower supports for the temporary bridge; Installed caps on the southern piles; Continued removal of the overhang on the existing bridge; Continued receiving temporary bridge pieces.

The following is the anticipated work schedule for the week beginning May 13, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Continue installation of the tower supports for the temporary bridge.
  • Installation of temporary bridge pieces.
  • Continue receiving temporary bridge pieces throughout the week causing possible intermittent lane closure to off-load the pieces.

Offloading Temp BR108 pcs

Offloading of temporary bridge pieces


PROJECT UPDATE: Completed the installation of "piles" on the south side of the bridge; Completed capping the north side piles; Continued removal of the overhang on the existing bridge.

The following is the anticipated work schedule for the week beginning May 6, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Installation of the tower supports for the temporary bridge.
  • Continue removing overhang on the existing bridge.
  • Installation of pile caps on the south side of the bridge.
  • Continue receiving temporary bridge pieces throughout the week causing possible intermittent lane closure to off-load the pieces.

Pittsford Removal of existing BR

Removal of the overhang on existing bridge


PROJECT UPDATE: Continued drilling for installation of "piles" on the south side of the bridge; Completed capping the north side piles.

The following is the anticipated work schedule for the week beginning April 29, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Complete drilling pile on the south side of the bridge for the installation of the temporary bridge.
  • Continue work on the north side of the bridge in preporation for the installation of the temporary bridge including removal of the overhang areas.
  • Begin receiving temporary bridge pieces throughout the week causing possible lane closure to off-load the pieces.

RT7 Pittsford BR108

Installation of pads for the towers to be installed for the temporary bridge


PROJECT UPDATE: Completed removal of the overhang on the existing bridge; Continued drilling for installation of "piles" on the south side of the bridge; Began capping the north side piles.

The following is the anticipated work schedule for the week beginning April 15, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Continue drilling pile on the south side of the bridge for the installation of the temporary bridge.
  • Continue work on the north side pile caps.
  • Side slope work in preporation for the installation of the temporary bridge.

RT7 Pittsford BR108

Removal of the existing bridge overhang


PROJECT UPDATE: Removal of the overhang on the existing bridge continued along with drilling for installation of "piles" on the north side of the bridge; Installation of piles began on the south side of the bridge.

The following is the anticipated work schedule for the week beginning April 15, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Continue drilling pile on the south side of the bridge for the installation of the temporary bridge.
  • Completion the removal of the final pieces of overhang on the existing bridge.
  • Work on the north side pile caps.

Pittsford BR#108

"Piles" drilled on the south side of the temporary bridge


PROJECT UPDATE: Removal of the overhang on the existing bridge continued along with drilling for installation of "piles" on the north side of the bridge. All work on Monday, April 8 will be off-road and will not have any traffic impact.

The following is the anticipated work schedule for the week beginning April 8, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Continue drilling two piles on the north side of the bridge then switching to the south side of the bridge and begin drilling piles for the installation of the temporary bridge.
  • Complete the removal of the original bridge overhang.

Pittsford BR#108

"Piles" drilled on the north side of the temporary bridge


PROJECT UPDATE: Removal of the overhang on the existing bridge.  Began drilling for installation of sheeting ("piles") for the installation of the temporary bridge.

The following is the anticipated work schedule for the week beginning April 1, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Continue drilling for installation of sheeting for the installation of the temporary bridge.

Pittsford BR#108

Driving "Pile"


PROJECT UPDATE: The median at the intersection of U.S. Route 7 and VT Route 3 has been removed; Traffic has been shifted; Concrete barriers have been placed; The bridge rail on the west side of the bridge has been removed; Drilling began for the installation of the temporary bridge.

The following is the anticipated work schedule for the week beginning March 25, 2024:

Monday through Friday 7:00 a.m. to 3:30 p.m.:

  • Removal of the overhang on the existing bridge.
  • Drilling for installation of sheeting ("piles") for the installation of the temporary bridge.Bridge 108 Pittsford 

Median removed


PUBLIC INFORMATION MEETING

The Vermont Agency of Transportation (VTrans) will be joining the Town of Pittsford Selectboard Meeting to be held on March 20, 2024 to discuss an overview of this project after will be open for any questions or concerns regarding this project.

WHEN: Wednesday, March 20, 2024 at 6:30 p.m.

WHERE: Pittsford Town Office - 426 Plains Road Pittsford, VT 05763

Join Zoom meeting online:

https://us02web.zoom.us/j/82595761731?pwd=SFh5UGxIb3IyWlB1SXg4MnFuWGEwQT

Join by phone: 1-111-111-1111 Meeting ID: to be determined Passcode: