This project will consist of a complete rehabilitation of the existing roadway subbase, new traveling surface with modified shoulders to accommodate bicyclists (where feasible), some culvert replacements, guardrail work, ditching, signage, and centerline rumble strip installations where criteria has been met. Additionally, existing traffic signal improvements on existing signals, a new signal at the intersection of Bridge Street.   

A view of U.S. Route 2 looking east

View of U.S. Route 2 looking east.

As an additional project, the bridge (#29) over I-89 will be replaced with a new two-span curved girder bridge. This bridge will be on a new alignment with traffic being maintained on the existing bridge. Some weekend lane closures (NB or SB) on I-89 is anticipated for steel erection and remove of the existing bridge. Work on this will not begin until May 2023 with a tentative completion of September 2025.

For questions/concerns regarding this project or to receive weekly project updates, you may email Stephanie Barrett, Public Information Consultant at sbarrett@coibsinc.com or call 802-399-7847. Please reference U.S. Route 2, Richmond - Bolton.

Project Fact Sheet

US Route 2 - Richmond to Bolton

The Vermont Agency of Transportation in conjunction with Kubricky Construction Corporation is reconstructing U.S. Route 2 from the Richmond-Williston town line extending easterly for approximately 8.25 miles to approximately halfway between the Notch Road and the Bolton Access Road in Bolton.

During the construction period, motorists should expect traffic flow to be maintained at all times with one-way alternating traffic during construction hours with control present. During one of the culvert replacements, a overnight closure of US-2 will be required. Motorists should also expect to be traveling on a gravel surface during construction.

The posted speed limit will be strictly enforced as the safety of the workers along with the motorists is of the utmost importance. We ask motorists to use extreme caution while traveling through the zone. Please note the fines for speeding within the construction zone will be doubled.


PLEASE USE CAUTION AND FOLLOW THE POSTED SPEED LIMITS!

Traffic Control with one-lane of alternating travel on US Route 2 between Kenyan Road and I-89 southbound Exit 11 on-ramp; Motorists can also expect extended traffic interruptions between 7:00 p.m. to 11:00 p.m. Sunday through Thursday within the US Route 2 and Bridge Street/Jericho Road intersection.


WEEKLY CONSTRUCTION UPDATE:

PROJECT UPDATE: Completed all mainline structure adjustements in preparation for final paving; Installation of the new mast pole foundations for the new traffic signals.

The following is the anticipated work schedule for the week beginning Sunday, April 21, 2023:

Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):

  • Continue installation of a new traffic signal infrastructure at the intersection of US Route 2 and Jericho/Bridge Street.
  • Installation of new gaurdrail between Kenyan Road and the I-89 southbound Exit 11 on-ramp.

US2_Bridge St.

US2 and Jericho Road intersection mast pole foundation work for traffic signal


PROJECT UPDATE: A temporary pedestrian crossing was installed; Installation of a new mass pole foundation.

The following is the anticipated work schedule for the week beginning Friday, April 12, 2023:

Friday, Sunday through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):

  • Continue installation of a new traffic signal infrastructure at the intersection of US Route 2 and Jericho/Bridge Street.

PROJECT UPDATE: Work resumed with the contractor remobilizing to the project.

The following is the anticipated work schedule for the week beginning April 8, 2023:

Monday:

  • No work due to the anticipated influx of motorists in Vermont for the Solor Eclipse.

Tuesday Through Thursday - 7:00 p.m. to 7:00 a.m. (nighttime work):

  • Begin installation of a new traffic infrastructure at the intersection of US Route 2 and Jericho/Bridge Street intersection.

US2_Richmond Culvert

US2 and Jericho/Bridge Street intersection facing west


This project is shut down for the 2023 construction season.

Project updates will resume in spring 2024, prior to any construction work.

Have a safe and happy holiday season / winter.

This week ending 11/16/23: Completed driveway tie-ins throughout the project; Installed guardrail delineations; Project clean up.

US2 Richmond Culvert

Culvert installed near the Riverview Cemetery due to the July 16 storm event


This week ending 11/10/23: Backfilled the newly installed concrete curbing west of the Richmond Village: Installation a new culvert near the Riverview Cemetery; Completed driveway tie-ins throughout the project.

The following is the anticipated work schedule for the week beginning November 13, 2023:

Monday Through Friday - 7:00 a.m. to 4:30 p.m.:

  • Backfilling the newly installed concrete curb.
  • Project clean up in preparation of winter shut down.

US2_Richmond Culvert

Culvert replacement work near the Riverview Cemetery due to the July 16 storm event


This week ending 11/3/23: Continued installation of concrete curb along the roadway near the Riverview Cemetery, and continued driveway tie-ins throughout the project.

The following is the anticipated work schedule for the week beginning November 5, 2023:

Sunday through Friday 7:00 p.m. to 7:00 a.m.:

  • Continue backfilling the curb along the base of the slope near Riverview Cemetery.
  • A large culvert replacement across U.S. Route 2 between Riverview Cemetery and Willis Farm Road due to the July 16 storm event.

Monday Through Friday - 7:00 a.m. to 5:30 p.m.:

  • Weather permitting, continue paving driveway tie-ins and various patches throughout the project limits.
  • Project clean up in preparation of winter shut down.

US2 Curb

Continue form work for placement of concrete curb


This week ending 10/27/23: Began installation of concrete curb along the roadway near the Riverview Cemetery; Completed the drainage upgrade along the roadway near Riverview Cemetery; Began driveway tie-ins on the eastern end of the project; Installed pavement markings throughout the project.

The following is the anticipated work schedule for the week beginning October 29, 2023:

Sunday through Friday 7:00 p.m. to 7:00 a.m.:

  • Continue forming and backfilling the curb along the base of the slope near Riverview Cemetery.

Monday Through Friday - 7:00 a.m. to 5:30 p.m.:

  • Weather permitting, continue paving driveway tie-ins between Lemroy Court and Cochran Road.
  • Continue installation of concrete curb near Riverview Cemetery.

US2Richmond Curb

Forms installed for the placement of concrete curb near Riverview Cemetery


This week ending 10/20/23: Completed the installation of shoulder material, centerline rumble strip and final mainline pavement markings throughout the project; Upgraded the drainage along the roadway near Riverview Cemetery; Completed the ditch and slope repair between Lemroy Court and the I-89 Exit 11 interchange.

The following is the anticipated work schedule for the week beginning October 22, 2023:

Sunday through Friday 7:00 p.m. to 7:00 a.m.:

  • Begin forming the curb along the base of the slope near Riverview Cemetery.

Monday Through Friday - 7:00 a.m. to 6:30 p.m.:

  • Weather permitting, continue paving driveway tie-ins between Lemroy Court and the eastern end of the project.
  • Set concrete curb near Riverview Cemetery.

US2 Richmond paving

Final paving continues on the west end of the project


This week ending 10/13/23:  Began installation of shoulder material between Locust Knoll and the I-89 Exit 11 interchange; Continued ditch and slope repair between Lemroy Court and the I-89 Exit 11 interchange.

The following is the anticipated work schedule for the week beginning October 22, 2023:

Sunday through Friday 7:00 p.m. to 7:00 a.m.:

  • Continue ditching and slope work between Lemroy Court and the I-89 Exit 11 interchange.

Monday Through Friday - 7:00 a.m. to 6:30 p.m.:

  • Weather permitting, paving driveway tie-ins between Lemroy Court and the eastern end of the project.
  • Continue shoulder work between Lemroy Court and the eastern end of the project.
  • Wednesday, weather permitting, continue the final lift of paving between Kenyan Road Road and the Richmond/Williston town line.

Shoulder work US2

Shoulder material being installed from Lemroy Court to the east end of the project


This week ending 10/06/23:  Completed installation of the second lift of pavement between Cochran Road and Lemroy Court. Completed the installation of guardrail between Riverview Cemetery and the I-89 Exit 11 interchange.

The following is the anticipated work schedule for the week beginning October 8, 2023:

Sunday and Monday:

  • No work due to the Columbus / Indigenous Peoples' Day holiday

Monday 9:00 p.m. to 7:00 a.m., Tuesday through Friday 7:00 p.m. to 7:00 a.m.:

  • Continue ditching and slope work between Lemroy Court and the I-89 Exit 11 interchange.

Tuesday Through Friday - 7:00 a.m. to 6:30 p.m.:

  • Weather permitting, continue the final lift of paving between Kenyan Road Road and the Richmond/Williston town line.
  • Weather permitting, paving driveway tie-ins between Lemroy Court and the eastern end of the project.
  • Continue shoulder work between Lemroy Court and the eastern end of the project.

 

US2 Richmond

Newly installed guardrail


This week ending 9/29/23:  Completed installation of the second lift of pavement between Kenyan Road and the Richmond/Williston town line. Installed driveway tie-ins within the Richmond Village.

The following is the anticipated work schedule for the week beginning October 2, 2023:

Sunday through Friday - 7:00 p.m. to 6:30 a.m.:

  • Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
  • Continue ditching, shoulder work, and guardrail installation between Baker Street and the I-89 Exit 11 interchange.

Monday Through Friday - 6:30 a.m. to 6:30 p.m.:

  • Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
  • Later in the week, weather permitting, continue paving the final lift of pavement from Kenyon Road to the Richmond/Williston town line.
  • Continue shoulder work from the eastern end of the project to Lemroy Court.

Paving US2

Continued paving wearing course (top) in Jonesville, working westerly


This week ending 9/22/23: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Began driveway tie-ins within the Richmond Village; Continued adjusting the sewer structures to pavement grade within the Richmond Village.

The following is the anticipated work schedule for the week beginning September 24, 2023:

Sunday through Friday - 7:00 p.m. to 6:30 a.m.:

  • Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
  • Continue ditching and shoulder work between Baker Street and the I-89 Exit 11 interchange.

Monday Through Friday - 6:30 a.m. to 6:30 p.m.:

  • Weather permitting, continue the final lift of paving at the eastern end of the project between Cochran Road and Lemroy Court.
  • Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
  • Continue driveway tie-ins from the eastern end of the project in Bolton to Lemroy Court.
  • Continue shoulder work throughout the project limits.

US2 Bolton Wearing Course

Final paving began this morning on the east end of the project in Bolton, working westerly


This week ending 9/15/23: Completed installation of the second lift of pavement between Baker Street and the I-89 Exit 11 interchange. Continued adjusting the sewer structures to pavement grade within the Richmond Village.

The following is the anticipated work schedule for the week beginning September 17, 2023:

Sunday through Friday - 7:00 p.m. to 6:30 a.m.:

  • Continue adjustment of the drainage structures between Lemroy Court and Baker Street.
  • Continue signal upgrade work at the VT Route 117 & U.S. Route 2 Intersection and the Richmond Park and Ride intersection

Monday Through Friday - 6:30 a.m. to 6:30 p.m.:

  • Weather permitting, begin the final lift of paving at the eastern most end of the project in Bolton proceeding westerly to Lemroy Court.
  • Weather permitting, continue paving the second lift of pavement from Kenyon Road to the Richmond/Williston town line.
  • Continue shoulder work throughout the project limits.

US2 Richmond

Base pavement completed throughout the project limits


This week ending 9/8/23: Completed slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line. Continued adjusting drainage and sewer structures to pavement grade between Lemroy Court and Baker Street.

The following is the anticipated work schedule for the week beginning September 11, 2023:

Monday through Friday - 7:00 p.m. to 6:30 a.m.:

  • Weather permitting, continue paving the second course of pavement between Baker Street and the I-89 interchange.
  • Continue adjustment of the drainage and sewer structures between Lemroy Court and Baker Street.
  • Signal upgrade work at the VT Route 117 & U.S. Route 2 Intersection and the Richmond Park and Ride intersection

Monday Through Friday - 6:30 a.m. to 6:30 p.m.:

  • Shoulder work from the eastern end of the project in Bolton to Lemroy Court in Richmond, in preparation of final final course of pavement to be placed.

US2Richmond Rehab

The final stretch of roadway reconstruction on the west end of the project


This week ending 9/1/23: Completed the base course of bavement between Willis Farm Road and the I-89 interchange. Continued with slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line. Adjusted sewer structures to pavement grade within Richmond Village.

The following is the anticipated work schedule for the week beginning September 4, 2023:

Monday - No work due to the Labor Day holiday.

Tuesday through Friday - 7:00 p.m. to 6:30 a.m.:

  • Weather permitting, continue paving the second course of pavement between Baker Street and the I-89 interchange.
  • Adjustment of the drainage structures between Lemroy Court and Baker Street.

Tuesday Through Friday - 6:30 a.m. to 6:30 p.m.:

  • Continue roadway reconstruction between Kenyon Road to the Richmond/Williston town line.

US2 Richmond

Base pavement installed end the west end of the project


This week ending 8/24/23: Completed slab removal and placement of subbase material on U.S. Route 2 between Willis Farm Road and the I-89 interchange. Began slab removal and placement of subbase material between Kenyon Road and the Richmond/Willston town line.

The following is the anticipated work schedule for the week beginning Sunday, August 27, 2023:

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Weather permitting, paving between Lemroy Court to the I-89 interchange to include base course between Williston Farm Road to the I-89 interchange, and a second course between Lemroy Court through the Richmond Village to the I-89 interchange.

Monday Through Thursday - 7:00 a.m. to 6:30 p.m.; Friday 7:00 a.m. to noon:

  • Continue roadway reconstruction between Kenyon Road to the Richmond/Williston town line
  • Continue shoulder work between Cochran Road and Lemroy Court.

US2 Richmond

Roadway reconstruction proceeds on the west end of the project in Richmond


This week ending 8/18/23: Slab removal and placement of subbase material continued on U.S. Route 2 approximately 1/2 mile east of I-89 southbound Exit 11 on-ramp; Continued guardrail installation, ditching and slope repairs. Milling is complete between Kenyon Road and Richmond/Williston town line in preparation of roadway reconstruction.

The following is the anticipated work schedule for the week beginning Sunday, August 20, 2023:

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue with roadway reconstruction activities on the west end between Willis Farm Road and the I-89 interchange.

Monday Through Friday - 7:00 a.m. to 6:30 p.m.:

  • Continue guardrail installation.
  • Continue ditching and slope work along the shoulders throughout the project.

US2 Richmond

Roadway reconstruction continues on the west end of the project in Richmond 


This week ending 8/11/23: Slab removal continued and placement of subbase material on U.S. Route 2 on the west end of the project; Continued paving the base course of pavement from Bridge Street and proceed west; New guardrail installation between the VYCC Farm and Snipe Ireland Road.

The following is the anticipated work schedule for the week beginning Sunday, August 13, 2023:

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction activities on the west end of the project proceeding west to the I-89 interchange.

Monday Through Wednesday - 7:00 a.m. to 6:30 p.m.:

  • Weather permitting, final paving with the wearing course beginning at the east end of the project in Bolton proceeding west.

Thursday & Friday - 7:00 a.m. to 6:30 p.m.:

  • Weather permitting, continued paving the base course of pavement on the gravel roadway on the west end of the project.

US 2 Richmond

Base pavement placed this week within Richmond Village proceeding west


This week: Slab removal continued on U.S. Route 2 between River View Cemetery and Willis Farm Road; Completed slope and ditch work between Cochran Road and Lemroy Court.

The following is the anticipated work schedule for the week beginning Sunday, August 6, 2023:

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction activities from Willis Farm Road proceeding west to the I-89 interchange.
  • Fine grading in preparation for base pavement between Baker Street and Willis Farm Road.

Thursday and Friday - 7:00 a.m. to 6:30 p.m.:

  • Potential guardrail installation between Snipe Ireland Road and Lemroy Court

This week: Slab removal continued on U.S. Route 2 between Millet Street and Rivew View Cemetery; Completed guardrail installation in Jonesville; Slope and ditch work between Locust Knoll and Cochran Road was completed.

The following is the anticipated work schedule for the week beginning Sunday, July 31, 2023:

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction activities from River View Cemetery proceeding west to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Continue shoulder and ditch work between Lemroy Court and Locust Knoll.
  • Guardrail installation between Snipe Ireland Road and Lemroy Court

Tuesday and Wednesday - 7:00 a.m. to 6:30 p.m.:

  • Paving the base layer on U.S. Route 2 from Millet Street to the River View Cemetery

RT2 Roadway recon

Nighttime US Route 2 - Excavating out existing roadway


This week: Work on roadway repairs from the recent heavy rainfall.

The following is the anticipated work schedule for the week beginning Sunday, July 23, 2023.

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Restart concrete slab removal and roadway reconstruction activities from Baker Street proceeding west to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Continue shoulder and ditch work between Lemroy Court and Cochran Road.
  • Potential continuation of guardrail installation between Snipe Ireland Road and Lemroy Court.

This week: Limited operations this week due to the heavy rains. Guardrail work continued throughout the project.

The following is the anticipated work schedule for the week beginning Sunday, July 16, 2023.

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction from Millet Street proceeding west to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • General project cleanup work from Jonesville west towards Lemroy Court, Richmond.
  • Guardrail installation continues between Snipe Ireland Road proceeding west towards Lemroy Court.

Guardrail work

Guardrail work on US Route 2


ROUGH ROAD AHEAD!

Due to the heavy rain fall today July 10, 2023, motorists traveling on U.S. Route 2 in Richmond, VT between Millet Street and River View Cemetery can expect to be traveling on a rough road surface.

Please be assured the contractor is doing their best to maintain this graveled roadway.


This week: Completed 800' of roadway reconstruction between Millet Street to Riverview Cemetery; Installed the second lift of pavement between Locust Knoll Road and Lemroy Court.

The following is the anticipated work schedule for the week beginning Sunday, July 9, 2023.

Sunday through Friday (morning) - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction from Millet Street proceeding west to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Continue placement of shoulder material and ditch work between Cochran Road to the eastern end of the project in Bolton.
  • Guardrail installation between Snipe Ireland Road to Lucust Knoll Road.

Thursday and Friday - 7:00 a.m. to 6:30 p.m.:

  • Base paving on the gravel surface and gravel installation on the shoulders from Millet Street to Riverview Cemetery.

RT2 Richmond

Roadway reconstruction on US Route 2, Richmond


This week: Completed the roadway reconstruction and base pavement on U.S. Route 2 between Lemroy Court and Millet Street; Installed three new electrial sleeves within the US 2/Bridge Street intersection for the new traffic signal system; Placed shoulder gravel between Cochran Road and Locust Knoll Road.

The following is the anticipated work schedule for the week beginning Monday, July 3, 2023.

Monday and Tuesday:

  • No work scheduled due to the Independence Day holiday unless there is required roadway maintenace needed.

Wednesday and Thursday - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction within the Richmond Village beginning at Millet Street and proceeding west to the I-89 interchange.
  • Structure adjustment within the US 2/Bridge Street intersection.

Wednesday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Weather permitting, paving and placement of shoulder material between Locust Knoll Road and Lemroy Court.

US2 west of Bridge St

Slab removal on US Route 2 west of the Bridge Street intersection


EXPECT DELAYS!!

Motorists should expect extended delays today, June 26, 2023 through Friday, June 30, 2023 from 9:00 a.m. to 3:00 p.m. within the Richmond Village due to paving operations.


This week:  Began concrete removal on U.S. Route 2 between Lemroy Court and Millet Street. Completed paving the base course of the gravel surface between Snipe Ireland Road and Lemroy Court.

The following is the anticipated work schedule for the week beginning Sunday, June 25, 2023.

Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:

  • Continue concrete slab removal and roadway reconstruction beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Roadway maintenance throughout the gravel surface area.

Monday through Thursday - 8:00 a.m. to 2:30 p.m.:

  • Base paving on the gravel surface between Lemroy Court and Riverview Cemetery.

US2 Slab Removal

Slab removal on US Route 2 within the Richmond Village


This week: The milling of U.S. Route 2 between Lemroy Court and just east of the I-89 interchange was completed. Structures were lowered within the Richmond Village.

The following is the anticipated work schedule for the week beginning Sunday, June 18, 2023.

Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:

  • Begin concrete slab removal and roadway reconstruction beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange.

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Roadway maintenance throughout the gravel surface area.

Thursday and Friday - 7:00 a.m. to 6:30 p.m.:

  • Base paving on the gravel surface between Snipe Ireland Road and Lemroy Court.

RT2 Richmond

Nighttime grinding of existing pavement on US Route 2 west of the Richmond Village


This week: Completed the existing roadway reconstruction between Snipe Ireland Road and Lemroy Court; Continued another 2500' of intermediate paving (second lift).

The following is the anticipated work schedule for the week beginning Sunday, June 11, 2023.

Sunday through Thursday - 7:00 p.m. to 7:00 a.m.:

  • Grinding the existing roadway beginning at Lemroy Court and proceeding west through Richmond Village to the I-89 interchange
  • Lowering of the existing drainage structures

Monday through Friday - 7:00 a.m. to 6:30 p.m.:

  • Roadway maintenance throughout the gravel surface area.
  • General project clean-up work.

US2 Lift 2 paving

Continue paving the 2nd "lift" of pavement on US Route 2, Richmond


This week: Another 2500' of existing roadway was reconstructed and 7000' of roadway was paved with a second lift of asphalt between Cochran Road and the VYCC Farm.

The following is the anticipated work schedule for the week beginning Monday, June 5, 2023.

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.

Richmond Concrete

Breaking up concrete subbase under existing roadway

US2 from Cochran Rd

Paving the 2nd "lift" of pavement from Cochran Road proceeding west


This week: Another 2500' of existing roadway was reconstructed and 3000' of newly reconstructed roadway base, between Snipe Ireland Road and Lemroy Court, was paved.

The following is the anticipated work schedule for the week beginning May 30, 2023:

Tuesday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.

Tuesday and Wednesday - 6:30 a.m. to 6:00 p.m.:

  • Weather permitting, paving the 2nd "lift" of pavement between Cochran Road and Snipe Ireland Road.

Thursday and Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue paving the base layer of roadway on the gravel surface between Snipe Ireland Road and Lemroy Court.

RT2 Base Paving

Ricmond Base Paving

Paving base (1st lift) between Snipe Ireland Road and Lemroy Court


This week: Another 2000' of existing roadway was reconstructed and 400' of underdrain was upgraded.

The following is the anticipated work schedule for the week beginning May 22, 2023.

Monday through Thursday - 6:30 a.m. to 6:00 p.m., Friday 6:30 a.m. to noon:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.

Tuesday and Wednesday - 6:30 a.m. to 6:00 p.m.:

  • Paving the base from approximatley Snipe Ireland Road proceeding west over the gravel roadway surface.

Thursday - 6:30 a.m. to 6:00 p.m., and Friday 6:30 a.m. to noon:

  • Weather permitting, paving the 2nd layer of roadway from approximatley the west end of Cochran Road and proceeding west to Snipe Ireland Road.

RT2 Richmond

Installation of dense-graded gravel for roadway subbase


This week: 1500' of new guardrail was installed; 2500' of existing roadway was reconstructed and 500' of underdrain was upgraded.

The following is the anticipated work schedule for the week beginning May 15, 2023.

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
  • Continue underdrain work from Snipe Ireland Road proceeding west to Lemroy Court.

US2 Richmond GR

Continued guardrail installation in Bolton


This week: Limited work took place this week due to the rain to include two days of continued roadway excavation, slope work and roadway maintenace.

The following is the anticipated work schedule for the week beginning May 8, 2023.

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
  • Underdrain work from Snipe Ireland Road proceeding west to Lemroy Court.
  • Guardrail installation east of Snipe Ireland Road to the end of the project in Bolton.

US2 Richmond

Grading to keep the integretiy of the roadway due to the excessive rainfall


Full-depth roadway excavation began between Snipe Ireland Road and Lemroy Court. Guardrail installation began on the east end of the project in Bolton with much more to be installed as the project proceeds.

The following is the anticipated work schedule for the week beginning May 1, 2023:

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Continue full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
  • Ditch work on the east end of the project near Jonesville.

RT2 Richmond

Full depth roadway excavation between Snipe Ireland Road and Lemroy Court


The following is the anticipated work schedule for the week beginning April 24, 2023.

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Begin full-depth roadway excavation and slab removal between Snipe Ireland Road proceeding west to Lemroy Court.
  • Installation of new gaurdrail between Boys Club Road to the east end of the project in Bolton.
  • Slope stabilization and ditch work on the west end of the project between the intersection of VT Route 117 to the Richmond/Williston Town Line.

US2 Richmond

Milling operations between Snipe Ireland Road to Lemroy Court


The following is the anticipated work schedule for the week beginning Monday, April 17, 2023:

 

Monday through Friday - 6:30 a.m. to 6:00 p.m.:

  • Milling (grinding of the existing pavement) from Snipe Ireland Road proceeding west to Lemroy Court.
  • Installation of guardrail throughout the project limits.
  • Erosion control measures throughout the project limits.

The following is the anticipated work schedule for the week beginning Monday, April 10, 2023:

 

Monday through Friday - 6:30 a.m. to 5:00 p.m.:

  • Crews will be working on U.S. Route 2 between Snipe Ireland Road and Lemroy Court to adjust the guardrail in preparation for continued roadway reconstruction to begin next week.

Completed paving the second lift of pavement to Jonesville along with continued driveway tie-ins. Completed installation of shoulder material throughout.

The following is the anticipated work schedule for the week beginning Monday, November 28, 2022:

Monday - Daytime:

  • Continue paving driveway and side road tie-ins.

Tuesday through Friday:

  • Clean-up work throughout the project in preparation for winter shut-down.

RT2 Jonesville

Placement of shoulder material along with driveway tie-ins on US Route 2, Jonesville


Completed paving the second lift of pavement to Jonesville along with driveway tie-ins. Continued installation of shoulder material throughout.

The following is the anticipated work schedule for the week beginning Monday, November 21, 2022:

Monday, Tuesday - Daytime and Wednesday until noon:

  • Continue installing shoulder material between Snipe Ireland Road and the eastern end of the project in Bolton.
  • Clean-up work throughout the project in preparation for winter shut-down.

Thursday and Friday: No work due to the Thanksgiving Day holiday.

RT2 Shoulder work

Placement of shoulder material on US Route 2, Bolton


Paving the second lift of pavement began on the eastern end of the project in Bolton and proceeded westerly. Drainage upgrade work continued between Snipe Ireland Road and Cochran road.

The following is the anticipated work schedule for the week beginning Monday, November 14, 2022:

Monday through Friday - Daytime:

  • Weather permitting, continue paving the second lift of asphalt westerly from approximately Boys Club Road to Snipe Ireland Road.
  • Continue installing shoulder material and driveway/side road tie-ins.

RT2 Bolton

Second lift of pavement being placed on US Route 2, Bolton


General project cleanup work began. Drainage upgrade work continued between Bridge Street and Lemroy Court continued.

The following is the anticipated work schedule for the week beginning Monday, November 7, 2022:

Monday through Friday - Daytime:

  • Weather permitting, paving the second lift of asphalt from the eastern end of the project in Bolton to Snipe Ireland Road.
  • Continue drainage upgrade between Snipe Ireland Road and Cochran Road.

US RT2 Richmond

 

US Route 2, Richmond drainage inlet installed


Driveway tie-ins have been completed from the eastern end of the project to Notch Road. Drainage upgrade work continued between Bridge Street and Lemroy Court. 

The following is the anticipated work schedule for the week beginning Monday, October 31, 2022:

Monday through Friday - Daytime:

  • Project clean-up work on the eastern end of the project between Snipe Ireland Road and Long Trail parking lot.
  • Continue drainage upgrade within Richmond Village.

RT2 Richmond

US Route 2, Richmond drainage upgrade work


PROJECT UPDATE: Base paving is now complete on all the unpaved, reconstructed roadway. Drainage upgrade work continued including the west end of Richmond Village.

The following is the anticipated work schedule for the week beginning Monday, October 24, 2022:

Monday through Friday - Daytime:

  • Weather permitting, driveway and side road tie-ins along with the installation of shoulder material all between Snipe Ireland Road to the eastern end of the project in Bolton.
  • Continue drainage upgrade between Bridge Street and Lemroy Court.

RT 2 Richmond

US Route 2, Richmond paving the unpaved, reconstruction roadway


PROJECT UPDATE: Fine grading operations continued along with drainage work in Richmond Village. Paving between Cochran Road and Snipe Ireland Road began today and will continue into tomorrow.

The following is the anticipated work schedule for the week beginning Monday, October 17, 2022:

Monday through Friday - Daytime:

  • Weather permitting, paving on U.S. Route 2 from Snipe Ireland Road proceeding westerly.
  • Continue drainage upgrade between Bridge Street and Lemroy Court.

Monday through Thursday - Nighttime 7:00 p.m. to 6:00 a.m.:

  • Drainage upgrade on the west end of Richmond Village. 

RT2 Richmond

US Route 2, Richmond west of Cochran Road; Spraying calcium chloride to aid with roadway compaction


PROJECT UPDATE: The roadway excavation and slab removal has been completed to approximately Snipe Ireland Road, which was the goal for the 2022 construction season.

The following is the anticipated work schedule for the week beginning Monday, October 10, 2022:

Monday through Friday - Daytime:

  • Fine grading and roadway maintenance will continue between Cochran Road and Snipe Ireland Road.

Monday through Thursday - Nighttime 7:00 p.m. to 6:00 a.m.:

  • Drainage upgrade between Bridge Street and Lemroy Court. 
  • Project clean-up work throughout

RT2 Richmond

Roadway excavation to stabilize the subbase on US Route 2, Richmond 


PROJECT UPDATE: Base pavement has been placed from the eastern most end of the project in Bolton to Cochran Road. Today, paving will continue westbound from approximately Cochran Road.

The following is the anticipated work schedule for the week beginning Monday, October 3, 2022:

Monday and Tuesday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.

Monday through Friday - Daytime:

  • Continue drainage work within Richmond Village.
  • Fine grading and roadway maintenance will continue between Cochran Road and Snipe Ireland Road.

RT 2 Richmond paving

Base paving on US Route 2, Richmond 


The following is the anticipated work schedule for the week beginning Monday, September 26, 2022:

Monday through Friday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Drainage work within Richmond Village.
  • Roadway maintenance will continue throughout the week.

Tuesday:

  • Weather permitting, continue paving westbound between Notch Road, Bolton to Cochran Road, Richmond.

Richmond ditching

Removing ledge for drainage/ditch work on US Route 2, Richmond 


The following is the anticipated work schedule for the week beginning Monday, September 19, 2022:

Monday through Friday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Weather permitting, continue paving westbound between Notch Road, Bolton to Cochran Road, Richmond.
  • Drainage work throughout the project limits.
  • Roadway maintenance will continue throughout the week.

 

RT2 Bolton

Base course paving began on US Route 2 in Bolton


The following is the anticipated work schedule for the week beginning Monday, September 12, 2022:

Monday - Daytime:

  • Roadway preparation for paving between the Long Trail Parking Lot and Boys Club Road.

Tuesday and Wednesday - Daytime:

  • Paving base course between the Long Trail Parking Lot and Boys Club Road.

Monday through Friday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Ditching and turf establishment between Cochran Road to the eastern end of the project in Bolton.

RT2 Jonesville

New dense graded gravel installed on US Route 2 in Jonesville west of the I-89 overpass


The following is the anticipated work schedule for the week beginning Monday, September 5, 2022:

Monday:

  • No work due to the Labor Day holiday

Tuesday through Friday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Drainage work within Richmond Village (with minimal traffic delays as two-way traffic will be maintained within this work area)

RT2 Jonesville

Roadway excavation continues on US Route 2 in Jonesville


The following is the anticipated work schedule for the week beginning Monday, August 29, 2022:

Monday through Friday - Daytime:

  • Continue full-depth roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Weather permitting and contractor availability, fine grading and paving base course in Bolton from the Long Trail Parking Lot to Boys Club Road.

Monday through Thursday - 7:00 p.m. to 6:00 a.m.:

  • Continue with slope repair between Exit 11 interchange and the westerly end Richmond Village

Sub-grading excavated US Route 2 Jonesville


Due to unforeseen utility issues, the work scheduled for this weekend has been postponed.

BEGINNING TOMORROW, FRIDAY at 7:00 p.m. to SUNDAY 7:00 a.m.:

Replacement of culvert pipe under US Route 2 just east of the intersection of US Route 2 and Jericho Road/Bridge Street. Traffic control will be present allowing for one lane of alternating travel throughout this time to complete the project. MOTORISTS SHOULD EXPECT EXTENDED DELAYS THROUGHOUT THE DAYTIME ON SATURDAY WITHIN THE US ROUTE 2 & JERICHO ROAD/BRIDGE STREET INTERSECTION.
The following is the anticipated work schedule for the week beginning Monday, August 22, 2022:
Monday through Friday - Daytime:
  • Continue roadway excavation and slab removal between Cochran Road and Snipe Ireland Road.
  • Weather permitting, paving base course in Bolton from the Long Trail Parking Lot to Boys Club Road.
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Drainage and slope repair between Exit 11 interchange and the westerly end Richmond Village

RT 2 Richmond

Milling up the existing pavement on US Route 2 proceeding westerly


The following is the anticipated work schedule for the week beginning Monday, August 15, 2022:
Monday through Wednesday - Daytime:
  • Milling from Jonesville proceeding easterly for approximately 1-1/2 miles
Monday through Friday - Daytime:
  • Continue roadway excavation and slab removal from the Richmond-Bolton town line proceeding easterly
  • Fine grading from Notch Road, Bolton to Jonesville
  • Stone fill and drainage work throughout the project limits
  • Potential paving the first course of pavement on the east end of the project, in Bolton
Friday - 7:00 p.m. to 7:00 a.m.:
  • Replacement of culvert pipe under US Route 2 just east of the intersection of US Route 2 and Jericho Road/Bridge Street. Traffic control will be present allowing for one lane of alternating travel.

Richmond-Bolton

Roadway excavation/Slab removal on US Route 2 in Bolton proceeding west


Monday through Friday - Daytime:
  • Continue roadway excavation and slab removal between Boys Club Road and Cochran Road
  • Slope repairs in multiple locations between Lemroy Court, Richmond and Cochran Road, Jonesville.

RT2 Bolton

Roadway excavation/Slab removal on US Route 2 in Bolton proceeding west


The following is the anticipated work schedule for the week beginning Monday, August 1, 2022:
Monday through Friday - Daytime:
All work will be east of the US Route 2 bridge over I-89.
  • Continue roadway excavation and slab removal between Boys Club Road and Long Trail Parking Lot.
  • Slope repairs in multiple locations between Lemroy Court, Richmond and Cochran Road, Jonesville.

RT2 Closed drainage

Underdrain installation on US Route 2 in Bolton proceeding west


The following is the anticipated work schedule for the week beginning Monday, July 25, 2022:
Monday through Friday - Daytime:
All work will be east of the US Route 2 bridge over I-89.
  • Continue ledge removal working westerly
  • Continue installation of underdrain working westerly
  • Continue roadway excavation on the east end of the project in Bolton working westerly
  • Continue guardrail work working westerly

RT 2 Bolton

Roadway excavation on US Route 2 in Bolton proceeding west


The following is the anticipated work schedule for the week beginning Monday, July 18, 2022:
Monday through Friday - Daytime:
All work will be east of the US Route 2 bridge over I-89.
  • Continue ledge removal working west
  • Continue installation of underdrain on the east end of the project in Bolton working westerly
  • Begin slab removal and roadway excavation on the east end of the project in Bolton working westerly.

US2 Richmond-Bolton


The following is the anticipated work schedule for the week beginning Monday, July 11, 2022:
Monday through Friday - Daytime:
  • Continue ledge removal working west
  • Continue installation of underdrain on the east end of the project in Bolton working west
  • Continue grinding up the existing pavement on the east end of the project in Bolton working westerly.

RT 2

Milling on VT Route 2 in Bolton working west


The following is the anticipated work schedule for the week beginning Monday, July 4, 2022:
Monday:
  • No work due to the Independence Day holiday
Tuesday through Friday - Daytime:
  • Continue ledge removal on the east end of the project in Bolton working west
  • Begin installation of underdrain on the east end of the project in Bolton working west
Thursday and Friday:
  • Begin grinding up the existing pavement on the east end of the project in Bolton working westerly.

Bolton Ledge Removal

Ledge removal began on the Bolton end of the project


The following is the anticipated work schedule for the week beginning Monday, June 27, 2022:
Monday through Thursday - Daytime; Friday until noon:
  • Continue sign installation
  • Continue equipment mobilization
  • Begin ledge removal on the east end of the project in Bolton working west
  • Begin installation of underdrain on the east end of the project in Bolton working west

The following is the anticipated work schedule for the week beginning Monday, June 20, 2022:
Monday through Friday:
  • Installation of construction signage in preparation of work to begin on June 27, 2022.
  • Equipment mobilization.