Pavement and line striping have been installed and grass has been planted.
- No work scheduled for this week.
The new 42" culvert is installed and VT Route 2A has been repaved within the construction area.
- No work due to the Independence Day holiday.
- General clean up work within the construction area.
The new 42" culvert was installed and backfilled along with the first lift of pavement.
- Reconstruction of the stream bed at both the inlet and outlet ends of the culvert.
- Replacement of the disrupted concrete sidewalk and curb.
- One-way alternating traffic with traffic control present to allow for paving and line striping the constructed area.
Trench boxes were removed and the new headwalls were backfilled in preparation of placing the new culvert.
- Excavation of VT Route 2A to place the new culvert; Backfill and pave the area traffic can expect the following impact:
- 6:30 p.m. to 9:00 p.m. traffic will be reduced to alternating one-way.
- 9:00 p.m. to approximately 8:00 a.m. Route 2A will be closed between Helena Drive and Zephyr Road/Paul Street intersection, and the detour will be in effect.
Monday through Thursday - Daytime:
- Minimal activity in preparation for final work on Friday, June 24, 2022 beginning at 6:30 p.m.
- Motorists seeking to travel north on VT Route 2A will detour at "Taft Corners to U.S. Route 2 east to VT Route 117 (River Road) north to "Five Corners" then back onto VT Route 2A.
- Motorists seeking to travel south on VT Route 2A will be detoured to "Five Corners" south onto VT Route 117 (River Road) to U.S. Route 2 west and back onto VT Route 2A at "Taft Corners".
The following is the anticipated daytime work schedule for the week beginning Monday, June 13, 2022:
- Removal of trench boxes and begin backfilling of the headwalls.
- 6:30 p.m. to 9:00 p.m. traffic will be reduced to alternating one-way.
- 9:00 p.m. to approximately 8:00 a.m. Route 2A will be closed between Helena Drive and Zephyr Road/Paul Street intersection, and the detour will be in effect.
The following is the anticipated daytime work schedule for the week beginning Monday, June 6, 2022:
- Continue excavation work for the installation of new headwalls at the inlet and outlet ends of the culvert.
Work has resumed on this project.
- Work begins on the installation of new headwalls at the inlet and outlet ends of the culvert.
Motorists can anticipate lane shifts with traffic control present
The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
- Minimal work to include project preparation.
- Begin project setup work