This project has been suspended until such time when the utility companies relocate their lines. Updates will resume prior to the contractor returning to work.

The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:

Monday through Friday:
  • Minimal work to include project preparation.

Prep work to install piping for stream diversion  2A Culvert

Excavation platform and stream diversion in preparation for construction

 

The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:
Monday through Friday:
  • Begin project setup work
Motorists should be aware of trucks entering/exiting the work area.

Traffic shifts with cone designation