The Vermont Agency of Transportation in conjunction with A.L. St. Onge Contractor Inc. (St. Onge) will be replacing the deteriorating 6' x 6' concrete box structure with a 4' x 8' pre-cast concrete box structure located on VT Route 118 in Berkshire, approximately 1 mile from the intersection of VT Route 118 and VT Route 105.
The anticipated completion is October 2021.
The following is the anticipated work schedule for the week beginning Monday, November 1, 2021:
- It is anticipated that today and tomorrow final paving and line striping will be completed. If weather doesn't permit this will take place next week, weather permitting.
- Construction signage removal to complete the project.
The following is the anticipated work schedule for the week beginning Monday, October 21, 2021:
- Weather and scheduling permitting, final paving (wearing course), weather permitting
- Weather permitting, line striping
The following is the anticipated work schedule for the week beginning Monday, October 18, 2021:
- If weather doesnt permit paving tomorrow, October 22, final paving (wearing course)
- and line striping
The following is the anticipated work schedule for the week beginning Monday, October 11, 2021:
- No work due to the Indigenous People's Day holiday
- Weather and scheduling permitting, final paving (wearing course) and line striping
The following is the anticipated work schedule for the week beginning Monday, October 4, 2021:
- Continue removal of temporary detour
- Weather and scheduling permitting, final paving (wearing course) and line striping.
The following is the anticipated work schedule for the week beginning Monday, September 27, 2021:
- Continue removal of temporary detour
- Weather and scheduling permitting, final paving (wearing course) and line striping.
The following is the anticipated work schedule for the week beginning Monday, September 20, 2021:
- Weather permitting, final paving (wearing course)
- Begin removal of temporary detour
The following is the anticipated work schedule for the week beginning Monday, September 13, 2021:
- Guardrail installation
The following is the anticipated work schedule for the week beginning Monday, September 6, 2021:
- No work due to the Labor Day holiday
- Weather permitting, paving of the roadway approaches
The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
- Placement of dense graded stone on roadway approaches
The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
- Backfilling around abutments
The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
- Begin installation of box culvert sections
The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:
- Begin installation of box culvert sections
The following is the anticipated work schedule for the week beginning Monday, August 2, 2021:
- Backfilling around the concrete footings
- Begin mobilization of box culvert sections to site
The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:
- Minimal work to allow for the newly poured concrete footings cure.


The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
- Continue work on concrete footings to include some ledge removal and begin forming.

The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:
- Continue work on concrete footings on the east end on the project

The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:
- No work due to the Independence Day holiday
- Continue work on concrete footings for the new culvert
- Allowing curing time for concrete poured this week

The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:
- Preparing form work for pouring concrete footings.
Old culvert removed
Prep work for concrete footings
The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
- Excavation work to remove existing culvert.

The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:
- Continue prep work and paving of the temporary approaches in anticipation of opening up the detour roadway.
Temporary culvert pipe installed: Work continues on the detour roadway
The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:
- Prep work and paving of the temporary approaches in anticipation of opening up the detour roadway.
Culvert piping to be installed for detour roadway
Prep work for temporary culvert installation
The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:
- No work due to the Memorial Day holiday
- Installation of temporary culvert, prepping for detour roadway.


The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:
- Minimal work continues for the installation of a temporary bridge.

The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
- Continue excavation work for the installation of a temporary bridge.

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
- Continue excavation work for the installation of a temporary bridge. Motorists should be aware of minimal delays for trucks entering/exiting the work area.
Excavation work for temp bridge installation
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
Monday through Friday:
Continue installation of temporary bridge. Motorists should be aware of trucks in/out of the work area.
The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:
St. Onge has begun clearing for the installation of a two-way temporary detour through the construction zone and will continue periodically throughout this week.
Motorists should expect minimal impact in their travels this week.