The following is the anticipated work schedule for the week beginning Monday, June 13, 2022:
- Completion of sidewalk areas within the Lime Kiln Road intersection.
- General cleanup work in various areas throughout the project.
The following is the anticipated work schedule for the week beginning Monday, June 6, 2022:
- Installation of granite curb, sidewalk end panel and patch pave at the Ethan Allen Avenue intersection.
- Painting of all crosswalks, stop bars and other associated lines throughout the project limits.
The following is the anticipated work schedule for the week beginning Monday, May 30, 2022:
- No work due to the Memorial Day holiday.
- Top soil, seed and matting to be placed between Ethan Allen Avenue to Susie Wilson Road.
- Curb and concrete sidewalk pad to be installed at the corner of Ethan Allen Avenue.
- Installation of a 50' fence on the north side of the path between Ethan Allen Avenue to Susie Wilson Road to protect against a ditch area.
- Return the Bus Shelter between Ethan Allen Avenue to Susie Wilson Road.
- Sign work throughout the project limits.
The following is the anticipated work schedule for the week beginning Monday, May 23, 2022:
- Work continues on the multi-use path between Ethan Allen Avenue to Susie Wilson Road.
- Installation of a 4' chain link fence on the east side of the UVM Fanny Allen Campus for protection at the ravine.
The following is the anticipated work schedule for the week beginning Monday, May 16, 2022:
- Work continues on the multi-use path from Ethan Allen Avenue to Susie Wilson Road.
- Paving of the path in front of the UVM Fanny Allen Campus.
- Paving of the path at the intersection of VT Route 15 and Barnes Avenue.
Motorists may encounter a lane closure and/or traffic control between 10:00 a.m. and 3:00 p.m. in the westbound lane at the Barnes Avenue intersection as well as between Susie Wilson Road and Ethan Allen Avenue.
The following is the anticipated work schedule for the week beginning Monday, May 9, 2022:
- Work continues on the multi-use path from Ethan Allen Avenue to Susie Wilson Road.
- Installation of concrete sidewalks in various areas throughout the project.
The following is the anticipated work schedule for the week beginning Monday, May 2, 2022:
- Work continues on the multi-use path from Ethan Allen Avenue to Susie Wilson Road.
- Installation of concrete sidewalks in various areas throughout the project.
Motorists can expect a lane closure westbound from Susie Wilson Road to Ethan Allen Avenue and/or traffic control within the work area(s) between 10:00 a.m. and 3:00 p.m.
The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:
- Work continues on the multi-use path within the UVM Fanny Allen Campus area proceeding on to the Barnes Avenue intersection later in the week.
There will be little to no impact. However, motorists may encounter a lane closure and/or traffic control within the work area(s) between 10:00 a.m. and 3:00 p.m.
The following is the anticipated work schedule for the week beginning Monday, April 18, 2022:
- Work resumes on the multi-use path within the UVM Fanny Allen Campus area and at the Barnes Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, April 11, 2022:
- Work resumes on the multi-use path within the UVM Fanny Allen Campus area and at the Ethan Allen Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, December 6, 2021:
- General clean up work throughout the project limits.
The following is the anticipated work schedule for the week beginning Monday, November 29, 2021:
- Continued sidewalk and curb work at Lime Kiln Road, National Guard Road and within the UVM Fanny Allen Campus areas. Motorists may encounter a lane closure within the work areas.
The following is the anticipated work schedule for the week beginning Monday, November 22, 2021:
- Continued sidewalk work at Lime Kiln Road and VT National Guard Road intersections. Motorists can expect a lane closure within each intersection during work activities.
- No work due to the Thanksgiving Day holiday.
The following is the anticipated work schedule for the week beginning Monday, November 11, 2021:
- Continued sidewalk at the Lime Kiln Road intersection. Motorists can expect a lane closure on both Lime Kiln Road and VT Route 15. After this intersection is complete, sidewalk work will continue onto other various areas throughout the project.
The following is the anticipated work schedule for the week beginning Monday, November 4, 2021:
Monday through Friday:
- Sidewalk work continues at the Lime Kiln Road intersection. Motorists can expect a lane closure on both Lime Kiln Road and VT Route 15. After this intersection is complete, sidewalk work will continue onto other various areas throughout the project.
This project is on hold until various utilities within the work zone have been relocated.
The following is the anticipated work schedule for the week beginning Monday, September 13, 2021:
- No work scheduled for this week as the project work swith the utility companies.
The following is the anticipated work schedule for the week beginning Monday, September 06, 2021:
- No work scheduled for this week as the project work swith the utility companies.
The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
- Minimal work scheduled for this week.
The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
- Work continues at the intersection of Lime Kiln Road intersection and National Guard Road to include electrical work for signals and pedestrian crossings.
The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
- Work continues at the intersection of Lime Kiln Road intersection to include electrical wiring to the traffic and pedestrian signals.
Motorists can expect lane closure from 10:00 a.m. to 3:00 p.m. at the Lime Kiln Road intersection. Pedestrians will follow a signed detour for the week.
The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:
- Work continues at the intersection of Lime Kiln Road intersection to include continued curb placement, sidewalk work and pedestrian signal foundation installation.
The following is the anticipated work schedule for the week beginning Monday, August 2, 2021:
- Removal of existing curb at the Lime Kiln Road intersection and install granite curb
- No work scheduled at this time
The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:
- Intersection work at Lime Kiln Road intersection to include the installation of pedestrian poles and piping
- Thursday: Granite curb installation in front of the Fanny Allen Campus
- Potential utility companies on site relocating lines
The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
- Minimal work to include project cleanup work
Monday through Friday:
- Pouring concrete sidewalk end panels in front of the UVM Fanny Allen Campus
- Paving the medians at Barnes Avenue
- Begin placement of sidewalk and pedestrian light poles at the Lime Kiln Road intersection.
Motorists can expect lane closures between 10:00 a.m. and 3:00 p.m. on Route 15 eastbound from Lime Kiln Road to Fanny Allen Campus along with Lime Rock Road and on Route 15 westbound and between National Guard Road and Ethan Allen Avenue.
West corner of Ethan Allen Avenue awaiting crosswalk lighting
The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:
- No work due to the Independence Day holiday
- Topsoil and hydroseeding continues along the newly paved sections of the pathway.
- Pouring concrete sidewalk panels at the intersections where new curb was installed in front of the UVM Fanny Allen Campus
Lane closures between 10:00 a.m. and 3:00 p.m. on Route 15 eastbound in front of the Fanny Allen Campus and on Route 15 westbound and between National Guard Road and Ethan Allen Avenue.Jug handle island & pathway at Route 15 eastbound and Campus Road
The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:
- Topsoil and hydroseeding continues along the newly paved sections of the pathway.
- Pouring concrete sidewalk panels at the intersections where new curb was installed.

The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
- Weather permitting, paving the south side of Route 15 in front of the Fanny Allen Campus and on the north side from National Guard Road to Barnes Avenue
- Topsoil and hydroseeding of the shoulders of all newly paved sections of the pathway.

The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:
- Pathway work continues on the north side of VT Route 15 between National Guard Road and Barnes Avenue
- Topsoil and hydroseeding of the shoulders of all newly paved sections of the pathway.
- Installation of sidewalk end panels at the intersections between Lime Kiln Road and Barnes Avenue.
- Installation of granite curbing at the intersections from Lime Kiln Road to Barnes Avenue.


The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:
- Pathway work continues on the south side of VT Route 15 between Lime Kiln Road and the UVM Fanny Allen Campus area.
- Pathway excavation work continues on the north side of VT Route 15 between Ethan Allen Avenue and Susie Wilson Road.
- Directional drilling between National Guard Road and Barnes Avenue to install a Burlington Telecom line.
Paving of the multi-use path on the south side of Route 15
The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:
- No work due to the Memorial Day holiday
- Pathway work continues on the south side of VT Route 15 within the UVM Fanny Allen Campus area.
- Pathway work continues on the north side of VT Route 15 between Ethan Allen Avenue and Susie Wilson Road. The existing sidewalk within this area will be removed. Pedestrians will still be able to pass through this area.
- Weather permitting, paving with 2" asphalt on all completed pathways, motorists should be aware of truck traffic entering/exiting the work area.


The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:
- Pathway work continues on the south side of VT Route 15 within the UVM Fanny Allen Campus area.
- Pathway work continues on the north side of VT Route 15 between Ethan Allen Avenue and Susie Wilson Road. The existing sidewalk within this area will be removed. Pedestrians will still be able to pass through this area.


The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
- Pathway work continues on the south side of VT Route 15 between Merrill Cemetery and the UVM Fanny Allen Campus
- Pathway work continues on the north side of VT Route 15 between Barnes Avenue and Ethan Allen Avenue.


The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
Monday through Friday:
- Pathway excavation and stone placement work to continue on the south side of VT Route 15 between Lime Kiln Road and UVM Medical Fanny Allen Campus.
- Excavation to begin from Barnes Avenue working east to Ethan Allen Drive on the north side of VT Route 15.
Motorists should expect a lane closure in each location between 10:00 a.m. and 3:00 p.m.
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
Monday through Friday:
- Pathway excavation and stone placement work to continue on the south side of VT Route 15 between Lime Kiln Road and UVM Medical Fanny Allen Campus AND between National Guard Road and Barnes Avenue on the north side of VT Route 15.
Motorists should expect a lane closure in each location between 10:00 a.m. and 3:00 p.m.
The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:
Monday through Friday:
- Pathway excavation work to continue between Lime Kiln Road and College Road jughandle (Merrill Cemetery), and National Guard Road and Barnes Avenue. Motorists should expect a lane closure in each location between 10:00 a.m. and 3:00 p.m.
- Directional drilling under National Guard Road to install conduit sleeves. Motorists should expect traffic control present.
The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:
Monday through Friday:
Construction to begin in two locations
- VT National Guard Road to Barnes Avenue
- Behind St. Michael's College Cemetery working east towards UVM Fanny Allen Campus
Motorists can expect traffic control to be present to assist in construction vehicles traveling in/out of the site locations.
Granite curb installed at the Lime Kiln Road intersection; Awaiting sidewalk placement