Skip to main content
Google Map view of the project location along VT Route 118 in Montgomery

Status of Montgomery Bridge #19 - two lane bridge over a river with metal and concrete railing.

Existing Bridge #19

 

Anyone interested in receiving updates on this project may email their request to Stephanie Barrett at sbarrett@coibsinc.com referencing Montgomery Bridges.

Existing Bridge #20 - showing visible signs of wear and weather on the metal and concrete railing.

Existing Bridge #20

VT ROUTE 118 - MONTGOMERY BRIDGE PROJECTS

The Vermont Agency of Transportation in conjunction with A.L. St. Onge Contractor Inc. (St. Onge) will be replacing the bridge decks on VT Route 118 in Montgomery. Bridge 19 is over the Trout River just east of Comstock Bridge Road. Bridge 20 is over West Hill Brook between West Hill Road and Hill Road West.  

This project replaces both bridge decks that were constructed in 1953 with decking that has a greater load capacity than the existing. The bridge railings will also be replaced with new crash tested railings that ties into the surrounding community and satisfies the historic requirements.

The anticipated completion is November 2022.


WEEKLY CONSTRUCTION UPDATES

Pavement markings were placed this week.

 

The following is the anticipated work schedule for the week beginning Monday, November 28, 2022:

Monday:

  • Weather permitting, completion of pavement markings.

BR19 Montgomery

Bridge 19 line striped


Signal system for traffic control has been removed.

 

The following is the anticipated work schedule for the week beginning Monday, November 21, 2022:

Monday, Tuesday and Wednesday until noon:

  • Weather permitting, complete pavement markings on both bridges

Thursday and Friday - No work due to the Thanksgiving Day holiday.

BR19 Montgomery

Bridge 19 awaiting line striping


Both bridges are now paved.

he following is the anticipated work schedule for the week beginning Monday, November 14, 2022:

Monday through Friday:

  • Weather permitting, pavement markings on both bridges
  • General cleanup work
  • Motorists will notice a change in the traffic control early in the week with the signal system being removed.

VT118

Final paving on Bridge 19


There was minimal activities on the project this week.

The following is the anticipated work schedule for the week beginning Monday, November 7, 2022:

Monday through Friday:

  • Weather permitting, paving of the entire project followed by line striping.

Montgomery Bridge

Awaiting paving and line striping


Painting continued on the structural steel. The protective membrane was sprayed on both bridges.

The following is the anticipated work schedule for the week beginning Monday, October 31, 2022:

Monday through Friday:

  • Continue painting of the structural steel on bridge 19.

Monday:

  • Weather permitting, paving of the entire project.

Montgomery Bridge

Painting work on Bridge #20


PROJECT UPDATE: As weather allowed, painting continued on the structural steel. Approaches on both bridges were milled out.

The following is the anticipated work schedule for the week beginning Monday, October 24, 2022:

Monday through Friday:

  • Continue painting of the structural steel on both bridges.
  • Spraying of a protective membrane on both bridges to be completed.
  • Weather permitting, paving of the entire project.

VT118 BR20

Bridge #20 abutment work has begun with temporary paving was installed


PROJECT UPDATE: Bridge #19 is now cured and the rail is installed.

The following is the anticipated work schedule for the week beginning Monday, October 17, 2022:

Monday through Friday:

  • Continue painting of the structural steel on both bridges.
  • Grinding the approaches of both bridges in preparation of paving.
  • Spraying of a protective membrane on both bridges.

BR19 VT118

Bridge #19 southbound guardrail installed


PROJECT UPDATE: Both bridge decks are now installed.

The following is the anticipated work schedule for the week beginning Monday, October 10, 2022:

Monday through Friday:

  • Backfill Bridge #19 and install the bridge rail.
  • Painting of the structural steel on both bridges.

BR20 Montgomery

Bridge #20 southbound guardrail installed

BR19 Montgomery

Bridge #19 southbound concrete deck poured and curing


The following is the anticipated work schedule for the week beginning Monday, October 3, 2022:

Monday through Friday:

  • Strip the forms off Bridge #20
  • Bridge #19 will be in the curing period
  • Installation of guardrail on both bridges

BR20 Montgomery

Bridge #20 southbound deck poured and prepped for guardrail installation

BR19 Montgomery

Bridge #19 deck preparation for anticipated concrete pour tomorrow


The following is the anticipated work schedule for the week beginning Monday, September 26, 2022:

Monday through Friday:

  • Begin forming the southbound deck on Bridge #19 in preparation for concrete.
  • Installation of guardrail on the southbound side of Bridge #20.

Montgomery BR20

Bridge #20 southbound deck poured, allowing concrete to cure

Montgomery BR19

Bridge #19 steel work with weather protection


The following is the anticipated work schedule for the week beginning Monday, September 19, 2022:

Monday through Friday:

  • Continue installing bearing devices; Repairing some concrete superstructure and installing the new structural steel on Bridge #19

Montgomery BR20

Bridge #20 southbound deck awaiting concrete


The following is the anticipated work schedule for the week beginning Monday, September 12, 2022:

Monday through Friday:

  • Pouring of the concrete decking on Bridge #20
  • Installing bearing devices; Repairing some concrete piers and painting on Bridge #19

BR20 Montgomery

Preparing deck Bridge #20 for concrete pour


The following is the anticipated work schedule for the week beginning Monday, September 5, 2022:

Monday:

  • No work due to to the Labor Day holiday

Tuesday through Friday:

  • Decking; Installation of rebar; Forming the curb all on Bridge #20
  • Painting of the steel on Bridge #19

Montgomery BR#20

Installation of new bearing devices on Bridge #20


The following is the anticipated work schedule for the week beginning Monday, August 29, 2022:

Monday through Friday:

  • Painting of the steel on both bridges
  • Jacking up existing beams to install new bearing devices
  • Repairing the existing concrete piers on both bridges

BR20 Montgomery

Bridge #20 demolition of the southbound lane


PROJECT UPDATE:
The guardrails have been installed and traffic is now shifted over to the newly constructed northbound lane on both bridges.
The following is the anticipated work schedule for the week beginning Monday, August 22, 2022:
Monday through Friday:
  • Continue demolition of the southbound lane Bridge 20 deck
  • Begin demolition of the southbound lane of Bridge 19 deck

Bridge #20 guardrail installed - traffic shifted onto new decking


PROJECT UPDATE:
The northbound decks are complete on both bridges and awaiting installation of guardrails.

The following is the anticipated work schedule for the week beginning Monday, August 15, 2022:

Monday through Friday:
  • Guardrail installation on both bridges
  • Traffic to be shifted over to the newly constructed northbound lane
  • Begin demolition of Bridge 20 deck southbound lane

Bridge 20 Montgomery

Bridge #20 awaiting guardrail installation


PROJECT UPDATE:
Bridge #19 concrete deck as been poured. Traffic has not been shifted onto the new deck as there is a delay in the guardrail delivery.
The following is the anticipated work schedule for the week beginning Monday, August 8, 2022:
Monday through Friday:
  • Stripping of the formwork under Bridge 19.

Bridge #19 awaiting guardrail installation


PROJECT UPDATE:
Bridge #19 concrete deck to be poured tomorrow, July 29, 2022.
The following is the anticipated work schedule for the week beginning Monday, August 1, 2022:
Monday through Friday:
  • Guardrail installation on Bridge #20.
  • It is anticipated for the completed half of Bridge #20 to be opened to traffic by the end of this work week. Motorists will then see a shift in the traffic pattern.
  • Demolition of the remaining half of the original bridge to begin on Bridge #20.

Deck preparation work for concrete pour on Bridge #19


PROJECT UPDATE:
Bridge #20 deck was poured; Concrete is now curing. Work began on forming Bridge 19 decking.
The following is the anticipated work schedule for the week beginning Monday, July 25, 2022:
Monday through Friday:
  • Continue forming and installing reinforcing steel the decking on Bridge #19. It is anticipated to pour the concrete decking Thursday or Friday.
  • Excavation and backfilling activities on Bridge #20.

BR20 Montgomery

Bridge #20 concrete deck poured


PROJECT UPDATE:
  • Bridge #20 decking is formed and it is anticipated to pour the concrete tomorrow, July 15, 2022.
The following is the anticipated work schedule for the week beginning Monday, July 18, 2022:
Monday through Friday:
  • Begin forming the decking on Bridge #19

Montgomery BR20

Prep work on Bridge #20 deck for concrete pour


The following is the anticipated work schedule for the week beginning Monday, July 11, 2022:
Monday through Friday:
  • Continue painting on Bridges 19.
  • Continue installation of new structural steel on bridge #19.
  • Continue decking on Bridge #20
  • Installation of rebar and forming the deck on Bridge #20, in anticipation of pouring the concrete decking on Friday.

Bridge #20 deck work


The following is the anticipated work schedule for the week beginning Monday, July 4, 2022:
Monday:
  • No work due to the Independence Day holiday.
Tuesday through Friday:
  • Surface preparation and painting primer Bridges 19.
  • Installation of new structural steel on both bridges.

Bridge 20 Montgomery

Installing new structural steel on Bridge #20


The following is the anticipated work schedule for the week beginning Monday, June 27, 2022:
Monday through Thursday and Friday until noon:
  • Painting of the primer coat on Bridges 20.
  • Installation of new structural steel on Bridge 20.
  • Repairing of the concrete substructures on Bridge 19.

Montgomery BR20

Continued removal of the old lead paint on Bridge #20


The following is the anticipated work schedule for the week beginning Monday, June 20, 2022:
Monday through Friday:
  • Begin surface preparation and painting of the structural steel on Bridges 20.
  • Continue match drilling structural steel plates on Bridge 19.

Bridge #20 Montgomery

Bridge #20 awaiting to be painted


The following is the anticipated work schedule for the week beginning Monday, June 13, 2022:
Monday through Friday:
  • Weather permitting, continue removal of existing paint on Bridges 19.
  • Match drilling structural steel plates on Bridge 19.

Montgomery BR#19


The following is the anticipated work schedule for the week beginning Monday, June 6, 2022:
Monday through Friday:
  • Weather permitting, continue removal of existing paint on Bridges 19 and 20.

Sand blasting in various areas on Bridge #20 over West Hill Brook


The following is the anticipated work schedule for the week beginning Monday, May 30, 2022:
Monday:
  • No work due to the Memorial Day holiday
Tuesday through Friday:
  • Begin removal of existing paint on Bridge 20. If time allows, will also work on Bridge 19.
  • Begin repair of the concrete substructures.

VT 118 BR#20VT 118 BR#20

Bridge #20 over West Hill Brook steel beams to be sand blasted in various areas


The following is the anticipated work schedule for the week beginning Monday, May 23, 2022:
Monday through Thursday and Friday until noon:
  • Installation of a containment system in anticipation of spot removal of existing paint on both bridges.

 

Bridge 20 awaiting containment system


The following is the anticipated work schedule for the week beginning Monday, May 16, 2022:
Monday through Friday:
  • Removal of the paint on the structural steel.
  • Begin preparation of the structural steel for future installation of new bearing stiffeners.

Bridge #20 Montgomery

Staging at concrete piers for repair on Bridge 20


The following is the anticipated work schedule for the week beginning Monday, May 9, 2022:
Monday through Friday:
  • Removal of the back walls on both bridges.
  • Continue stabilizing the roadway behind both bridge abutments.
  • Continue installation of staging at both bridges to repair the concrete piers.

Completed half deck removal on Bridge 19


The following is the anticipated work schedule for the week beginning Monday, May 2, 2022:
Monday through Friday:
  • Continued removal of the concrete decking on half of Bridge 19 over the Trout River.
  • Work on road stabilization on both bridge abutments.
  • Installation of staging at Bridge 19 piers.

BR20 Montgomery

Deck removed on 1-lane of Bridge 20

BR19 Montgomery

Start of deck removal on Bridge 19


The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:
Monday through Wednesday:
  • Continue with removal of the concrete decking on half of Bridge 20 over the West Hill Brook.
Wednesday through Friday:
  • Begin removal of the concrete decking on half of Bridge 19 over the Trout River.

Montgomery BR20

Deck removal on Bridge 20


On April 11, 2022, St. Onge began mobilization work setting up temporary traffic signals on the east end of Bridge 19 and the west end of Bridge 20, allowing for one lane of alternating traffic during the construction. In addition, temporary concrete barriers will be placed later this week to delineate working on one side of the bridges at a time.