VT Route 125 - Roadway Washout - Addison

The Vermont Agency of Transportation has closed VT Route 125 in Addison between 10 Acre Drive and Whitney Creek Drive after heavy rainfall washed away part of the road. 

A signed detour is currently in place. Motorists wanting to head west on VT 125 past the closure (to the Champlain Bridge) will continue north on VT 22A then turn left onto VT 17 west. All motorists wanting to head east on VT 125 past the closure (coming from the bridge) will continue east on VT 17 and then turn right to head south on VT 22A.

The following is the anticipated work schedule for the week beginning Monday, May 23, 2022.
Monday through Friday:
  • Roadway preparation to include fine grading.
  • Weather permitting, potential paving the newly constructed roadway.

Additional slope stabilization installed this week


The following is the anticipated work schedule for the week beginning Monday, May 16, 2022.
Monday through Friday:
  • Additional stone placement to be added to the bottom of the slope
  • Weather permitting, paving of the newly constructed roadway.

VT 125VT 125

Slope stabilization - More stone to be added at the bottom of the slope


The following is the anticipated work schedule for the week beginning Monday, May 9, 2022.
Wednesday through Friday:
  • Paving the newly constructed roadway.

There will not be any work on this project until the contractor returns to pave. The detour will remain in affect.
I will update you as soon as activity is scheduled.

VT 125 roadway awaiting paving


The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:
Monday and Friday:
  • Complete stone fill, slope stabilization and erosion control matting
  • Install final lift of roadway base material in preparation for paving

VT 125 Roadway Subbase

VT 125 Slope Stabilization, Installing matting


The following is the anticipated work schedule for the week beginning Monday, April 18, 2022:
Monday and Friday:
  • Continue with stone fill up the slope for stabilization along the lake shore
  • Erosion control
  • Install matting on the slope side
Friday:
  • Providing the week plans out, milling the asphalt approaches of the construction area

 

VT 125 Roadway Subbase

 

VT 125 Slope Stabilization


The following is the anticipated work schedule for the week beginning Monday, April 11, 2022:
Monday and Friday:
  • Continue building roadway subbase
  • Continue with stone fill up the slope for stabilization

The following is the anticipated work schedule for the week beginning Monday, April 4, 2022:
Monday and Friday:
  • Continue excavation of the existing waste material.
  • Continue with gravel and stone backfill.

Excavation of waste material; Backfilled with gravel and stone.


The following is the anticipated work schedule for the week beginning Monday, March 28, 2022:
Monday and Friday:
  • Continue with the installation of the stone work pad.
  • Continue with road stabilization and underdrain work.