- Installation of drainage across Industrial Avenue adjacent to Avenue A.
- General cleanup throughout the project.
- Preparation grading on the north side of US Route 2 in anticipation of base paving.
The following is the anticipated work schedule for the week beginning Monday, May 16, 2022:
- Continue with the installation of new drainage system on Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, May 9, 2022:
- Installation of new drainage system crossing over to the west side Industrial Avenue. Motorists will encounter a lane closure allowing for one lane of alternating travel.
- Continue with the installation of new drainage system on Industrial Avenue.
- Temporary paving of the road cuts on Industrial Avenue.
- Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction on Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:
- Continue with the installation of new drainage system on Industrial Avenue.
The following is a revised anticipated work schedule for the remainder of the week beginning Wednesday, April 20, 2022 @ 7:00 p.m.:
- Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction within the Industrial Avenue intersection.
- No work on the project.
The following is the anticipated work schedule for the week beginning Monday, April 18, 2022:
- Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
- Continue full-depth reconstruction east of Miller Lane
The following is the anticipated work schedule for the week beginning Monday, April 11, 2022:
- Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
- Continue full-depth reconstruction between Adams Drive and Industrial Avenue.
Nighttime drainage installation on VT Route 2 through the Miller Lane Intersection
The following is the anticipated work schedule for the week beginning Monday, April 4, 2022:
- Continue with the installation of storm drain through the Miller Lane intersection.
- Continue installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.
- Continue with the installation of storm drain from Miller Lane proceeding east.
New drainage installation continues easterly on VT Route 2
The following is the anticipated work schedule for the week beginning Monday, March 28, 2022:
- Mobilization of construction equipment back on site the beginning of the week.
- Continue with the installation of storm drain just east of Miller Lane proceeding east to Industrial Avenue.
- Installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.

The following is the anticipated work schedule for the week beginning Monday, February 7, 2022:
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 31, 2022:
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 24, 2022:
- Installation of trench boxes to facilitate auger boring.
- Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
- Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 across Miller Lane working on half the Lane at a time to allow for motorists access.
- Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 east of Miller Lane working to Industrial Avenue.
- Directional boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, January 10, 2022:
- Continue installation of new drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, January 3, 2022:
- Continue installation of drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.
The following is the anticipated work schedule for the week beginning Monday, December 27, 2021:
- Continued work on new signal foundations
Thursday and Friday:
- No work scheduled
- Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
- Continue work on the installation of a new signal for the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, December 13, 2021:
- Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
- Continue work on the installation of a new signal for the Industrial Avenue intersection.
The following is the anticipated work schedule for the week beginning Monday, December 6, 2021:
- General operations and clean up work throughout the project.
- Boring operations to install conduit under US Route 2 at the Industrial Avenue intersection in preparation for a new signal installation.
The following is the anticipated work schedule for the week beginning Monday, November 29, 2021:
- Continue full depth reconstruction and drainage improvements on the north side of Route 2.
The following is the anticipated work schedule for the week beginning Monday, November 22, 2021:
- No work schedule for this week.
- Continue full depth reconstruction on the north side (westbound) of Route 2
- Continue drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, November 8, 2021:
- Begin full depth reconstruction on the north side (westbound) of Route 2
- Begin drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, November 1, 2021:
- Begin full depth reconstruction on the north side (westbound) of Route 2
- Begin drainage improvements on the north side of Route 2
The following is the anticipated work schedule for the week beginning Monday, October 25, 2021:
- Line striping the newly paved roadway on the south side of US Route 2
- Driveway and side road approaches to be tied into the new eastbound lane
- Work necessary to change over the traffic pattern to include the newly paved south side of US Route 2. Motorists can expect traffic control to be present allowing for 1-lane of alternating travel.
- General work throughout the project
The following is the anticipated work schedule for the week beginning Monday, October 18, 2021:
- Fine grading the newly installed subbase roadway on the south side of US Route 2
- Paving the fine graded south side of US Route 2
- Weather permitting, installation of pavement markings
- General cleanup work within the southside of US Route 2 work area
The following is the anticipated work schedule for the week beginning Monday, October 11, 2021:
- No work due to the Indigenous Person's Day holiday
- Installation of the enclosed drainage system within the Industrial Avenue intersection, traffic control will be present allowing for 1 lane of alternating travel
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side working easterly
- Fine grading the southside work area on Route 2 in anticipation of base paving
The following is the anticipated work schedule for the week beginning Monday, October 4, 2021:
- Signal work at Industrial Avenue with no traffic disruptions
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side from Adams Drive working east
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction moving across US 2 from the south side over to the north side
Motorists can expect a lane closure with traffic control present during the nighttime work
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side on the western end of the project working east
The following is the anticipated work schedule for the week beginning Monday, September 20, 2021:
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
- Begin installation of the enclosed drainage system (stormwater) and full depth reconstruction across US 2
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
- Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side of US 2 at the west end of the project near Muddy Brook.
The following is the anticipated work schedule for the week beginning Monday, September 6, 2021:
- No work due to the Labor Day holiday
- Continue work on enclosed drainage system (storm water) within the US 2 and Industrial Avenue intersection
- Continue full depth reconstruction on the south side of Route 2 within the US 2 and Industrial Avenue intersection
The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Continue full depth reconstruction on the south side of Route 2 easterly from Engineers Drive
The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Continue full depth reconstruction on the south side of Route 2
The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
- Begin full depth reconstruction on the south side of Route 2
The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:
- Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
- Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2
Monday 7:00 p.m. to 6:00 p.m.:
- Weather permitting, line striping the detour area in anticipation of opening the lane on Tuesday.
- Work on enclosed drainage system at the eastern limit of the project
The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:
- Completion of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Lane shifts to begin onto the detoured roadway
- Continue work on enclosed drainage system (storm water) on Route 2
The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
- Continue construction of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Waterline testing on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:
- Continue construction of the detour roadway on the north side of Route 2
- Continue work on enclosed drainage system (storm water) on Route 2
- Continue waterline work on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:
- No work due to the Independence Day holiday
- Continue construction of the detour on the north side of Route 2.
- Begin work on enclosed drainage system (storm water) on Route 2
Designated lane shifts in both travel lanes within the construction area during working hours.

The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:
- Continue waterline installation on Industrial Avenue
- Continue construction of the detour on the north side of Route 2. This work will require designated lane shifts in both travel lanes within the construction area during working hours.

The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
- Continue waterline installation on Industrial Avenue
- Continue construction of the detour on the north side of Route 2. This work will requre designated lane shifts in both travel lanes within the construction area during working hours.


The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:
- New waterline tie-ins to existing services
- Continue waterline installation on Industrial Avenue
The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:
- Continue flushing, testing and chlorinating new waterline installed on Route 2
- Continue waterline installation on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:
- No work due to the Memorial Day holiday
- Flushing, testing and chlorinating new waterline installed on Route 2
- Continue waterline installation on Industrial Avenue


The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:
- Continue waterline work on both Route 2 and moving onto Industrial Avenue


The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
- Continue waterline work throughout the project limits
- Installation of water line sleeve across VT Route 2/Industrial Avenue intersection

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
- Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:
- Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
- The main entrance to Engineers Drive will be closed to motorists to allow for the waterline installation.
- Continue waterline work on the south side of Route 2 working from west to east.

The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:
- Continue waterline work on the south side of Route 2 working from west to east.


The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:
- Continue waterline work on the south side of Route 2 working from west to east.


The following is the anticipated work schedule for the week beginning Monday, April 12, 2021:
- Continue water line work on the south side of Route 2 working from west to east.
- Continue erosion control measures throughout the project limits
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
The following is the anticipated work schedule for the week beginning Monday, April 1, 2021:
- Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So. Burlington town line.
- Project delineation and erosion control measures to be installed throughout the project limits
- Tree removal within the State Right of Way within the Industrial Avenue section.
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
The following is the anticipated work schedule for the week beginning Monday, March 29, 2021:
- Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.
Motorists can expect minimal impact on the traffic within the work area.
The following is the anticipated work schedule for the week beginning Monday, March 22, 2021:
- Water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.
Motorists can expect intermediate impact on the traffic within the work area.
The following is the anticipated work schedule for the week beginning Monday, March 15, 2021:
- Installation of construction signs
- Tree cutting