Williston Intersection Project - US 2 and Industrial Ave

DUE TO THE CLOSURE OF MUDDY BROOK BRIDGE ON KIMBALL/MARSHALL AVENUES, MOTORISTS ON U.S. ROUTE 2 WILL FIND AN INCREASE IN TRAFFIC INTERRUPTIONS AND SHOULD EXPECT EXTENDED DELAYS DURING PEAK COMMUTE HOURS IN THE MORNING AND EVENINGS. PLAN FOR EXTRA TRAVEL TIME THROUGH THE AREA.
MOTORISTS WILL CONTINUE TO HAVE ACCESS TO ALL BUSINESSES HOWEVER, SOME MAY REQUIRE A TEMPORARY RELOCATION AS CONSTRUCTION PROGRESSES.

The following is the anticipated work schedule for the week beginning Monday, October 25, 2021:
Monday - 7:00 a.m. to 3:30 p.m.:
  • Line striping the newly paved roadway on the south side of US Route 2
Tuesday through Thursday - 7:00 a.m. to 3:30 p.m.:
  • Driveway and side road approaches to be tied into the new eastbound lane
Thursday - 7:00 p.m. to 6:00 a.m.:
  • Work necessary to change over the traffic pattern to include the newly paved south side of US Route 2. Motorists can expect traffic control to be present allowing for 1-lane of alternating travel.
Friday - 7:00 a.m. to 3:30 p.m.:
  • General work throughout the project

US Route 2 south side

Base pavement of US Route 2 eastbound


The following is the anticipated work schedule for the week beginning Monday, October 18, 2021:
Monday and Tuesday - 7:00 a.m. to 3:30 p.m.:
  • Fine grading the newly installed subbase roadway on the south side of US Route 2
Wednesday and Thursday - 7:00 a.m. to 3:30 p.m.:
  • Paving the fine graded south side of US Route 2
Friday - 7:00 a.m. to 3:30 p.m.:
  • Weather permitting, installation of pavement markings
  • General cleanup work within the southside of US Route 2 work area

US2 so side west viewUS2 so side east view

Subbase roadway US Route 2 western & eastern views, respectively


The following is the anticipated work schedule for the week beginning Monday, October 11, 2021:
Monday:
  • No work due to the Indigenous Person's Day holiday
Tuesday and Wednesday - 7:00 p.m. to 6:00 a.m.:
  • Installation of the enclosed drainage system within the Industrial Avenue intersection, traffic control will be present allowing for 1 lane of alternating travel
Tuesday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side working easterly
Thursday and Friday - 7:00 a.m. to 3:30 p.m.:
  • Fine grading the southside work area on Route 2 in anticipation of base paving

US2 Williston

Continued installation of drainage inlets


The following is the anticipated work schedule for the week beginning Monday, October 4, 2021:
Monday - 7:00 p.m. to 6:00 a.m.:
  • Signal work at Industrial Avenue with no traffic disruptions
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side from Adams Drive working east

Route 2 Drainage

Western most drainage structure installed

Route 2 Underdrain

Full depth excavation continues easterly


The following is the anticipated work schedule for the week beginning Monday, September 27, 2021:
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction moving across US 2 from the south side over to the north side

Motorists can expect a lane closure with traffic control present during the nighttime work

Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side on the western end of the project working east
Motorists can expect a lane shifts with traffic control present to allow from truck traffic in/out of the construction areas

RT @ Muddy Brook 1RT @ Muddy Brook 2

Installation of metal sheeting for ground stabilization during catch basin installation


The following is the anticipated work schedule for the week beginning Monday, September 20, 2021:
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Begin installation of the enclosed drainage system (stormwater) and full depth reconstruction across US 2
Motorists can expect a lane closure with traffic control present during the nighttime work.

US2 stormdrain

Continued stormwater drainage Installation on the south side of US Route 2


The following is the anticipated work schedule for the week beginning Monday, September 13, 2021:
Monday through Wednesday:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
Thursday and Friday:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side of US 2 at the west end of the project near Muddy Brook.

 

Route 2 Stormwater

Installation of stormwater drainage on the south side of US Route 2 and Industrial Avenue Intersection


The following is the anticipated work schedule for the week beginning Monday, September 6, 2021:
Monday:
  • No work due to the Labor Day holiday
Tuesday through Friday:
  • Continue work on enclosed drainage system (storm water) within the US 2 and Industrial Avenue intersection
  • Continue full depth reconstruction on the south side of Route 2 within the US 2 and Industrial Avenue intersection

US2 drainage section

Completed section of full-depth reconstruction on the south side of US Route 2


The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
Monday through Thursday - 7:00 a.m. to 3:30 p.m.; Friday 7:00 a.m. to noon:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Continue full depth reconstruction on the south side of Route 2 easterly from Engineers Drive
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Utility pole relocated to allow for construction to proceed easterly past the intersection


The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Continue full depth reconstruction on the south side of Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Williston RT2 Stormwater

Continue storm water installation


The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Begin full depth reconstruction on the south side of Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

 

Installation of new drainage inlet


The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:

Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2

Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Industrial Ave detour

Traffic is shifted as the detour lane on the north side of Route 2 now open


The following is the anticipated work schedule for the week beginning Monday, August 2, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2

Monday 7:00 p.m. to 6:00 p.m.:

  • Weather permitting, line striping the detour area in anticipation of opening the lane on Tuesday.
  • Work on enclosed drainage system at the eastern limit of the project
Please note: There may be some additional intermittent nighttime operations as required this week, however none scheduled at this time.

Route 2 Williston

Detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:

Monday & Tuesday:
  • Completion of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
Wednesday through Friday:
  • Lane shifts to begin onto the detoured roadway
  • Continue work on enclosed drainage system (storm water) on Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Detour lane on the north side of Route 2 partially paved


The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:

Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Waterline testing on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Construction of detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:

Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Continue waterline work on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Construction of detour lane on the north side of Route 2

The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:

Monday:
  • No work due to the Independence Day holiday
Tuesday through Friday:
  • Continue construction of the detour on the north side of Route 2.
  • Begin work on enclosed drainage system (storm water) on Route 2

Designated lane shifts in both travel lanes within the construction area during working hours.

Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Last run of new waterline being installed

The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:

Monday through Thursday - 7:00 a.m. to 3:30 p.m.; Friday 7:00 a.m. to noon:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will require designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
 
Waterline work continues on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
Monday through Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will requre designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area
Building road base for upcoming detour

The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:

Monday through Wednesday - Daytime:
  • New waterline tie-ins to existing services
Thursday and Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Installed waterline piping

The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:

Monday through Friday - Daytime:
  • Continue flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Waterline piping waiting to be installed on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:

Monday:
  • No work due to the Memorial Day holiday
Tuesday through Friday - Daytime:
  • Flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Installation of Route 2 westbound new waterline with protective sleeve
Welding of Route 2 westbound & eastbound waterline and protective sleeves together

The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:

Monday through Thursday - Daytime; Friday 7:00 a.m. to noon :
  • Continue waterline work on both Route 2 and moving onto Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Route 2 Williston Continued installation of water pipe
Route 2 Williston

 


The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
Monday through Friday:
  • Continue waterline work throughout the project limits
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Wednesday and Thursday 7:00 p.m. to 6:00 a.m.:
  • Installation of water line sleeve across VT Route 2/Industrial Avenue intersection
Traffic control will be present allowing for 1-way alternating traffic within this work area, motorists should expect delays.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continued installation of water pipe followed by backfill excavated area

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Completion of waterline crossing over Engineers Drive

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Continue waterline work on the south side of US Route 2 with cones shifting traffic
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
Monday 3:00 a.m. to 10:00 a.m.
  • The main entrance to Engineers Drive will be closed to motorists to allow for the waterline installation.
Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
  PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continue waterline work on the south side of US Route 2 with cones designated lane shifts

The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
                                   Continue waterline work on the south side of US Route 2

The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, April 12, 2021:

 

Monday through Friday:
  • Continue water line work on the south side of Route 2 working from west to east.
  • Continue erosion control measures throughout the project limits

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!


The following is the anticipated work schedule for the week beginning Monday, April 1, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So. Burlington town line.
  • Project delineation and erosion control measures to be installed throughout the project limits
Wednesday through Friday:
  • Tree removal within the State Right of Way within the Industrial Avenue section.​

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, March 29, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect minimal impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 22, 2021:

Monday through Friday:
  • Water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect intermediate impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 15, 2021:

Monday through Friday:
  • Installation of construction signs
  • Tree cutting
Traffic control will be present allowing for one lane of alternating traffic within the work area.