Williston Intersection Project - US 2 and Industrial Ave

DUE TO THE CLOSURE OF MUDDY BROOK BRIDGE ON KIMBALL/MARSHALL AVENUES, MOTORISTS ON ROUTE 2 WILL FIND AN INCREASE IN TRAFFIC INTERRUPTIONS AND SHOULD EXPECT EXTENDED DELAYS DURING PEAK COMMUTE HOURS IN THE MORNING AND EVENINGS. PLAN FOR EXTRA TRAVEL TIME THROUGH THE AREA.
 

The following is the anticipated work schedule for the week beginning Monday, August 2, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2

Monday 7:00 p.m. to 6:00 p.m.:

  • Weather permitting, line striping the detour area in anticipation of opening the lane on Tuesday.
  • Work on enclosed drainage system at the eastern limit of the project
Please note: There may be some additional intermittent nighttime operations as required this week, however none scheduled at this time.

Route 2 Williston

Detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:
Monday & Tuesday:
  • Completion of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
Wednesday through Friday:
  • Lane shifts to begin onto the detoured roadway
  • Continue work on enclosed drainage system (storm water) on Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Detour lane on the north side of Route 2 partially paved


The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:
Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Waterline testing on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Construction of detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:

Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Continue waterline work on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Construction of detour lane on the north side of Route 2

The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:

Monday:
  • No work due to the Independence Day holiday
Tuesday through Friday:
  • Continue construction of the detour on the north side of Route 2.
  • Begin work on enclosed drainage system (storm water) on Route 2

Designated lane shifts in both travel lanes within the construction area during working hours.

Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Last run of new waterline being installed

The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:

Monday through Thursday - 7:00 a.m. to 3:30 p.m.; Friday 7:00 a.m. to noon:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will require designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
 
Waterline work continues on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
Monday through Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will requre designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area
Building road base for upcoming detour

The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:

Monday through Wednesday - Daytime:
  • New waterline tie-ins to existing services
Thursday and Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Installed waterline piping

The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:

Monday through Friday - Daytime:
  • Continue flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Waterline piping waiting to be installed on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:

Monday:
  • No work due to the Memorial Day holiday
Tuesday through Friday - Daytime:
  • Flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Installation of Route 2 westbound new waterline with protective sleeve
Welding of Route 2 westbound & eastbound waterline and protective sleeves together

The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:

Monday through Thursday - Daytime; Friday 7:00 a.m. to noon :
  • Continue waterline work on both Route 2 and moving onto Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Route 2 Williston Continued installation of water pipe
Route 2 Williston

 


The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
Monday through Friday:
  • Continue waterline work throughout the project limits
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Wednesday and Thursday 7:00 p.m. to 6:00 a.m.:
  • Installation of water line sleeve across VT Route 2/Industrial Avenue intersection
Traffic control will be present allowing for 1-way alternating traffic within this work area, motorists should expect delays.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continued installation of water pipe followed by backfill excavated area

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Completion of waterline crossing over Engineers Drive

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Continue waterline work on the south side of US Route 2 with cones shifting traffic
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
Monday 3:00 a.m. to 10:00 a.m.
  • The main entrance to Engineers Drive will be closed to motorists to allow for the waterline installation.
Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
  PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continue waterline work on the south side of US Route 2 with cones designated lane shifts

The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
                                   Continue waterline work on the south side of US Route 2

The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, April 12, 2021:

 

Monday through Friday:
  • Continue water line work on the south side of Route 2 working from west to east.
  • Continue erosion control measures throughout the project limits

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!


The following is the anticipated work schedule for the week beginning Monday, April 1, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So. Burlington town line.
  • Project delineation and erosion control measures to be installed throughout the project limits
Wednesday through Friday:
  • Tree removal within the State Right of Way within the Industrial Avenue section.​

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, March 29, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect minimal impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 22, 2021:

Monday through Friday:
  • Water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect intermediate impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 15, 2021:

Monday through Friday:
  • Installation of construction signs
  • Tree cutting
Traffic control will be present allowing for one lane of alternating traffic within the work area.