Williston Intersection Project - US 2 and Industrial Ave

MOTORISTS WILL CONTINUE TO HAVE ACCESS TO ALL BUSINESSES ON ROUTE 2 HOWEVER, SOME MAY REQUIRE A TEMPORARY RELOCATION AS CONSTRUCTION PROGRESSES.
TWO-WAY TRAFFIC WILL BE MAINTAINED AT ALL TIMES.
MOTORISTS CAN EXPECT TRAFFIC CONTROL AT THE MUDDY BROOK BRIDGE DUE TO PAVING ON MAY 18 (AND MAY 19, IF NECESSARY).
 
The following is the anticipated work schedule for the week beginning Monday, May 23, 2022:
Monday 7:00 p.m. to 6:00 a.m.:
  • Installation of drainage across Industrial Avenue adjacent to Avenue A.
Tuesday:
  • General cleanup throughout the project.
Wednesday through Thursday - Daytime; Friday until noon:
  • Preparation grading on the north side of US Route 2 in anticipation of base paving.

Industrial Ave

Drainage Inlets installed on the west side of Industrial Avenue


The following is the anticipated work schedule for the week beginning Monday, May 16, 2022:
Monday through Friday - Daytime:
  • Continue with the installation of new drainage system on Industrial Avenue.

Continued installation of the new drainage system on the east side of Industrial Avenue


The following is the anticipated work schedule for the week beginning Monday, May 9, 2022:
Monday - 7:00 p.m. to 6:00 a.m.
  • Installation of new drainage system crossing over to the west side Industrial Avenue. Motorists will encounter a lane closure allowing for one lane of alternating travel.
Wednesday through Friday - Daytime:
  • Continue with the installation of new drainage system on Industrial Avenue.
Thursday - 7:00 p.m. to 12:00 a.m.
  • Temporary paving of the road cuts on Industrial Avenue.

Installation of drainage inlets on the west side of Industrial Avenue


The following is an add to this week's work schedule for Wednesday, April 27, 2022:
Wednesday 7:00 p.m. to 6:00 a.m.
  • Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction on Industrial Avenue.
NOTE: It is not anticipated to change the already scheduled daytime activities

The following is the anticipated work schedule for the week beginning Monday, April 25, 2022:

Monday through Friday - Daytime:
  • Continue with the installation of new drainage system on Industrial Avenue.

Route 2 Williston

Installation of a drainage inlet at the corner of Route 2 and Industrial Avenue


The following is a revised anticipated work schedule for the remainder of the week beginning Wednesday, April 20, 2022 @ 7:00 p.m.:
Wednesday 7:00 p.m. to 12:00 a.m. and
Thursday: 7:00 p.m. to 6:00 a.m.
  • Motorists can expect traffic control present allowing for one lane of alternating traffic for full-depth reconstruction within the Industrial Avenue intersection.
NOTE: There will be regular daytime activities on Wednesday from 12:00 p.m. until 7:00 p.m.
Friday:
  • No work on the project.

The following is the anticipated work schedule for the week beginning Monday, April 18, 2022:
Monday through Friday - Daytime:
  • Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
  • Continue full-depth reconstruction east of Miller Lane

Full depth reconstruction of the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, April 11, 2022:

Monday through Friday - Daytime:
  • Continue with the installation of storm drain from the Industrial Avenue intersection proceeding up Industrial Avenue.
  • Continue full-depth reconstruction between Adams Drive and Industrial Avenue.

Nighttime drainage installation on VT Route 2 through the Miller Lane Intersection


The following is the anticipated work schedule for the week beginning Monday, April 4, 2022:
Monday and Tuesday - 7:00 p.m. to 6:00 a.m.:
  • Continue with the installation of storm drain through the Miller Lane intersection.
Monday through Friday - Daytime:
  • Continue installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.
Wednesday through Friday - Daytime:
  • Continue with the installation of storm drain from Miller Lane proceeding east.

 

New drainage installation continues easterly on VT Route 2


The following is the anticipated work schedule for the week beginning Monday, March 28, 2022:

Monday and Friday:
  • Mobilization of construction equipment back on site the beginning of the week.
  • Continue with the installation of storm drain just east of Miller Lane proceeding east to Industrial Avenue.
  • Installation of conduit on both the north and south sides of the Industrial Avenue intersection for the new traffic signal.
Route 2 Williston

US Route 2 awaiting 2022 construction to begin


The following is the anticipated work schedule for the week beginning Monday, February 7, 2022:
Monday and Friday:
  • Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.

   

Boring operation to install conduit under US Route 2  

 

                                                            Site Restoration after area boring was completed                                                        


The following is the anticipated work schedule for the week beginning Monday, January 31, 2022:
Monday through Friday:
  • Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.

The following is the anticipated work schedule for the week beginning Monday, January 24, 2022:

Monday:
  • Installation of trench boxes to facilitate auger boring.
Tuesday through Friday:
  • Weather permitting, continue boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.

The following is the anticipated work schedule for the week beginning Monday, January 17, 2022:
Monday through Wednesday:
  • Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 across Miller Lane working on half the Lane at a time to allow for motorists access.
Thursday and Friday:
  • Continue installation of new drainage improvements and full-depth reconstruction on the north side of US Route 2 east of Miller Lane working to Industrial Avenue.
  • Directional boring under US Route 2 to install conduit piping for the new traffic signal at the Industrial Avenue intersection.

Continued installation of new drainage inlet on the north side of US Route 2

 


The following is the anticipated work schedule for the week beginning Monday, January 10, 2022:
Monday through Friday:
  • Continue installation of new drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.

Installation of new drainage inlet on the north side of US Route 2


The following is the anticipated work schedule for the week beginning Monday, January 3, 2022:
Monday through Friday:
  • Continue installation of drainage improvements on the north side of US Route 2 from Adams Drive to Industrial Avenue.

RT2 Light Pole Found.

Mast light pole foundation casing for the new signal southeast side of US Route 2

 


The following is the anticipated work schedule for the week beginning Monday, December 27, 2021:
Monday through Wednesday:
  • Continued work on new signal foundations

Thursday and Friday:

  • No work scheduled

Auguring the foundation casing for the new signal mast arm pole


The following is the anticipated work schedule for the week beginning Monday, December 20, 2021:
Monday through Friday:
  • Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
  • Continue work on the installation of a new signal for the Industrial Avenue intersection.

Casing and steel rebar for new signal foundations


The following is the anticipated work schedule for the week beginning Monday, December 13, 2021:
Monday through Friday:
  • Continue installation of drainage improvements on the north side of Route 2 between Adams Drive and Industrial Avenue.
  • Continue work on the installation of a new signal for the Industrial Avenue intersection.
 

The following is the anticipated work schedule for the week beginning Monday, December 6, 2021:
Monday and Tuesday - 7:00 a.m. to 3:30 p.m.:
  • General operations and clean up work throughout the project.
Wednesday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Boring operations to install conduit under US Route 2 at the Industrial Avenue intersection in preparation for a new signal installation.

RT2 Williston

Continue with full depth reconstruction

RT2 Williston

Preparation to set back barriers to widen roadway for winter maintenance


The following is the anticipated work schedule for the week beginning Monday, November 29, 2021:
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue full depth reconstruction and drainage improvements on the north side of Route 2.

RT2 Williston

Full depth reconstruction on US Route 2


The following is the anticipated work schedule for the week beginning Monday, November 22, 2021:
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • No work schedule for this week.

US2 & Industrial Ave

Installation of a drainage inlet at the northeast corner of US Route 2 and Industrial Avenue


The following is the anticipated work schedule for the week beginning Monday, November 15, 2021:
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue full depth reconstruction on the north side (westbound) of Route 2
  • Continue drainage improvements on the north side of Route 2

US Route 2

Full depth reconstruction now on the north side of US Route 2 westbound


The following is the anticipated work schedule for the week beginning Monday, November 8, 2021:

Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Begin full depth reconstruction on the north side (westbound) of Route 2
  • Begin drainage improvements on the north side of Route 2

US2

New temporary traffic pattern in place


The following is the anticipated work schedule for the week beginning Monday, November 1, 2021:
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Begin full depth reconstruction on the north side (westbound) of Route 2
  • Begin drainage improvements on the north side of Route 2

 

US RT 2 Williston

Relocation of barriers on US Route 2 eastbound in anticipation of new lane shift


The following is the anticipated work schedule for the week beginning Monday, October 25, 2021:
Monday - 7:00 a.m. to 3:30 p.m.:
  • Line striping the newly paved roadway on the south side of US Route 2
Tuesday through Thursday - 7:00 a.m. to 3:30 p.m.:
  • Driveway and side road approaches to be tied into the new eastbound lane
Thursday - 7:00 p.m. to 6:00 a.m.:
  • Work necessary to change over the traffic pattern to include the newly paved south side of US Route 2. Motorists can expect traffic control to be present allowing for 1-lane of alternating travel.
Friday - 7:00 a.m. to 3:30 p.m.:
  • General work throughout the project

US Route 2 south side

Base pavement of US Route 2 eastbound


The following is the anticipated work schedule for the week beginning Monday, October 18, 2021:
Monday and Tuesday - 7:00 a.m. to 3:30 p.m.:
  • Fine grading the newly installed subbase roadway on the south side of US Route 2
Wednesday and Thursday - 7:00 a.m. to 3:30 p.m.:
  • Paving the fine graded south side of US Route 2
Friday - 7:00 a.m. to 3:30 p.m.:
  • Weather permitting, installation of pavement markings
  • General cleanup work within the southside of US Route 2 work area

US2 so side west viewUS2 so side east view

Subbase roadway US Route 2 western & eastern views, respectively


The following is the anticipated work schedule for the week beginning Monday, October 11, 2021:
Monday:
  • No work due to the Indigenous Person's Day holiday
Tuesday and Wednesday - 7:00 p.m. to 6:00 a.m.:
  • Installation of the enclosed drainage system within the Industrial Avenue intersection, traffic control will be present allowing for 1 lane of alternating travel
Tuesday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side working easterly
Thursday and Friday - 7:00 a.m. to 3:30 p.m.:
  • Fine grading the southside work area on Route 2 in anticipation of base paving

US2 Williston

Continued installation of drainage inlets


The following is the anticipated work schedule for the week beginning Monday, October 4, 2021:
Monday - 7:00 p.m. to 6:00 a.m.:
  • Signal work at Industrial Avenue with no traffic disruptions
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side from Adams Drive working east

Route 2 Drainage

Western most drainage structure installed

Route 2 Underdrain

Full depth excavation continues easterly


The following is the anticipated work schedule for the week beginning Monday, September 27, 2021:
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction moving across US 2 from the south side over to the north side

Motorists can expect a lane closure with traffic control present during the nighttime work

Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side on the western end of the project working east
Motorists can expect a lane shifts with traffic control present to allow from truck traffic in/out of the construction areas

RT @ Muddy Brook 1RT @ Muddy Brook 2

Installation of metal sheeting for ground stabilization during catch basin installation


The following is the anticipated work schedule for the week beginning Monday, September 20, 2021:
Monday through Thursday - 7:00 p.m. to 6:00 a.m.:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
Monday through Friday - 7:00 a.m. to 3:30 p.m.:
  • Begin installation of the enclosed drainage system (stormwater) and full depth reconstruction across US 2
Motorists can expect a lane closure with traffic control present during the nighttime work.

US2 stormdrain

Continued stormwater drainage Installation on the south side of US Route 2


The following is the anticipated work schedule for the week beginning Monday, September 13, 2021:
Monday through Wednesday:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side within the US 2 and Industrial Avenue intersection
Thursday and Friday:
  • Continue installation of the enclosed drainage system (stormwater) and full depth reconstruction on the south side of US 2 at the west end of the project near Muddy Brook.

 

Route 2 Stormwater

Installation of stormwater drainage on the south side of US Route 2 and Industrial Avenue Intersection


The following is the anticipated work schedule for the week beginning Monday, September 6, 2021:
Monday:
  • No work due to the Labor Day holiday
Tuesday through Friday:
  • Continue work on enclosed drainage system (storm water) within the US 2 and Industrial Avenue intersection
  • Continue full depth reconstruction on the south side of Route 2 within the US 2 and Industrial Avenue intersection

US2 drainage section

Completed section of full-depth reconstruction on the south side of US Route 2


The following is the anticipated work schedule for the week beginning Monday, August 30, 2021:
Monday through Thursday - 7:00 a.m. to 3:30 p.m.; Friday 7:00 a.m. to noon:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Continue full depth reconstruction on the south side of Route 2 easterly from Engineers Drive
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Utility pole relocated to allow for construction to proceed easterly past the intersection


The following is the anticipated work schedule for the week beginning Monday, August 23, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Continue full depth reconstruction on the south side of Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Williston RT2 Stormwater

Continue storm water installation


The following is the anticipated work schedule for the week beginning Monday, August 16, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project on U.S. Route 2
  • Begin full depth reconstruction on the south side of Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

 

Installation of new drainage inlet


The following is the anticipated work schedule for the week beginning Monday, August 9, 2021:

Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2

Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

PLEASE FOLLOW THE POSTED SPEED LIMITS!

Industrial Ave detour

Traffic is shifted as the detour lane on the north side of Route 2 now open


The following is the anticipated work schedule for the week beginning Monday, August 2, 2021:
Monday through Friday:
  • Continue work on enclosed drainage system (storm water) on the southeast end of the project within the Adam Drive area on Route 2

Monday 7:00 p.m. to 6:00 p.m.:

  • Weather permitting, line striping the detour area in anticipation of opening the lane on Tuesday.
  • Work on enclosed drainage system at the eastern limit of the project
Please note: There may be some additional intermittent nighttime operations as required this week, however none scheduled at this time.

Route 2 Williston

Detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 26, 2021:

Monday & Tuesday:
  • Completion of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
Wednesday through Friday:
  • Lane shifts to begin onto the detoured roadway
  • Continue work on enclosed drainage system (storm water) on Route 2
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Detour lane on the north side of Route 2 partially paved


The following is the anticipated work schedule for the week beginning Monday, July 19, 2021:

Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Waterline testing on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Construction of detour lane on the north side of Route 2


The following is the anticipated work schedule for the week beginning Monday, July 12, 2021:

Monday through Friday:
  • Continue construction of the detour roadway on the north side of Route 2
  • Continue work on enclosed drainage system (storm water) on Route 2
  • Continue waterline work on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Construction of detour lane on the north side of Route 2

The following is the anticipated work schedule for the week beginning Monday, July 5, 2021:

Monday:
  • No work due to the Independence Day holiday
Tuesday through Friday:
  • Continue construction of the detour on the north side of Route 2.
  • Begin work on enclosed drainage system (storm water) on Route 2

Designated lane shifts in both travel lanes within the construction area during working hours.

Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Last run of new waterline being installed

The following is the anticipated work schedule for the week beginning Monday, June 28, 2021:

Monday through Thursday - 7:00 a.m. to 3:30 p.m.; Friday 7:00 a.m. to noon:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will require designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
 
Waterline work continues on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, June 21, 2021:
Monday through Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
  • Continue construction of the detour on the north side of Route 2. This work will requre designated lane shifts in both travel lanes within the construction area during working hours.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area
Building road base for upcoming detour

The following is the anticipated work schedule for the week beginning Monday, June 14, 2021:

Monday through Wednesday - Daytime:
  • New waterline tie-ins to existing services
Thursday and Friday - Daytime:
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Installed waterline piping

The following is the anticipated work schedule for the week beginning Monday, June 7, 2021:

Monday through Friday - Daytime:
  • Continue flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Waterline piping waiting to be installed on Industrial Avenue

The following is the anticipated work schedule for the week beginning Monday, May 31, 2021:

Monday:
  • No work due to the Memorial Day holiday
Tuesday through Friday - Daytime:
  • Flushing, testing and chlorinating new waterline installed on Route 2
  • Continue waterline installation on Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Installation of Route 2 westbound new waterline with protective sleeve
Welding of Route 2 westbound & eastbound waterline and protective sleeves together

The following is the anticipated work schedule for the week beginning Monday, May 24, 2021:

Monday through Thursday - Daytime; Friday 7:00 a.m. to noon :
  • Continue waterline work on both Route 2 and moving onto Industrial Avenue
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Route 2 Williston Continued installation of water pipe
Route 2 Williston

 


The following is the anticipated work schedule for the week beginning Monday, May 17, 2021:
Monday through Friday:
  • Continue waterline work throughout the project limits
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
Wednesday and Thursday 7:00 p.m. to 6:00 a.m.:
  • Installation of water line sleeve across VT Route 2/Industrial Avenue intersection
Traffic control will be present allowing for 1-way alternating traffic within this work area, motorists should expect delays.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continued installation of water pipe followed by backfill excavated area

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
PLEASE FOLLOW THE POSTED SPEED LIMITS!
Completion of waterline crossing over Engineers Drive

The following is the anticipated work schedule for the week beginning Monday, May 10, 2021:

Monday through Friday:
  • Continue waterline work within the Industrial Avenue intersection on the south side of Route 2 proceeding east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.

Continue waterline work on the south side of US Route 2 with cones shifting traffic
The following is the anticipated work schedule for the week beginning Monday, May 3, 2021:
Monday 3:00 a.m. to 10:00 a.m.
  • The main entrance to Engineers Drive will be closed to motorists to allow for the waterline installation.
Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area.
  PLEASE FOLLOW THE POSTED SPEED LIMITS!
Continue waterline work on the south side of US Route 2 with cones designated lane shifts

The following is the anticipated work schedule for the week beginning Monday, April 26, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect traffic control allowing for construction vehicles in/out of the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!
                                   Continue waterline work on the south side of US Route 2

The following is the anticipated work schedule for the week beginning Monday, April 19, 2021:

Monday through Friday:
  • Continue waterline work on the south side of Route 2 working from west to east.
Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, April 12, 2021:

 

Monday through Friday:
  • Continue water line work on the south side of Route 2 working from west to east.
  • Continue erosion control measures throughout the project limits

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!


The following is the anticipated work schedule for the week beginning Monday, April 1, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So. Burlington town line.
  • Project delineation and erosion control measures to be installed throughout the project limits
Wednesday through Friday:
  • Tree removal within the State Right of Way within the Industrial Avenue section.​

Motorist can expect minimal impact on the traffic within the work area. PLEASE FOLLOW THE POSTED SPEED LIMITS!

The following is the anticipated work schedule for the week beginning Monday, March 29, 2021:

Monday through Friday:
  • Continue water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect minimal impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 22, 2021:

Monday through Friday:
  • Water line work on the south side of Route 2 at the west end of the project, near the Williston/So, Burlington town line.

​​Motorists can expect intermediate impact on the traffic within the work area.


The following is the anticipated work schedule for the week beginning Monday, March 15, 2021:

Monday through Friday:
  • Installation of construction signs
  • Tree cutting
Traffic control will be present allowing for one lane of alternating traffic within the work area.